Moorhead Construction Co., Inc., a Corporation, Appellee-Cross-Appellant v. City of Grand Forks, a Municipal Corporation, Appellant-Cross-Appellee

508 F.2d 1008, 1975 U.S. App. LEXIS 16751
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 3, 1975
Docket74-1216, 74-1234
StatusPublished
Cited by36 cases

This text of 508 F.2d 1008 (Moorhead Construction Co., Inc., a Corporation, Appellee-Cross-Appellant v. City of Grand Forks, a Municipal Corporation, Appellant-Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moorhead Construction Co., Inc., a Corporation, Appellee-Cross-Appellant v. City of Grand Forks, a Municipal Corporation, Appellant-Cross-Appellee, 508 F.2d 1008, 1975 U.S. App. LEXIS 16751 (8th Cir. 1975).

Opinion

GIBSON, Chief Judge.

In this court-tried diversity case, the plaintiff Moorhead Construction Co., Inc., recovered a judgment of $109,994.26. *1011 for breach of contract. A counterclaim of the defendant City of Grand Forks, North Dakota, was dismissed with prejudice. In its original complaint Moor-head, a Minnesota corporation, sought $125,000 in extra expenses and lost profits incurred in performing a contract with the City to build a sewage treatment facility.

The City had divided the construction project into two phases, each to be performed by separate contractors. Phase I was designed by the City’s own engineering department and covered primarily the earth work and site preparation for four aerated-anaerobic treatment ponds, including installation of piping and appurtenances such as foundations for compressor and meter buildings. The four ponds or earthen cells were to be formed by building earthen dikes or embankments in a square pattern divided into four large, square, water-tight sections. The phase I contractor, Valley-Mayo, was scheduled to complete its work in September, 1969, before phase II was to commence. The phase I contractor, however, did not substantially complete its contract until November, 1970. The final acceptance by the City of the phase I work was not until October, 1971, when the contractor was paid in full and discharged.

Phase II of the project was designed by Richmond Engineering, Inc., of Grand Forks, the City’s agent and supervisor for the project. It consisted of completing the buildings, constructing manhole installations and access bridges into and over the ponds, and installing all electrical and mechanical equipment. When completed, the aeration equipment would treat the City’s sewage primarily in the aerated cells; secondary treatment would occur in lagoons. The separate phase II contract was awarded to the plaintiff Moorhead in July, 1969, with completion scheduled for October 30, 1969. Its accepted bid was $409,333.00. However, due to adverse weather, soil conditions, and delays, which are the subject 'of this litigation, phase II was not completed until November, 1971, and the facility commenced operations in January, 1972.

Moorhead posited two bases for recovery: (1) “changed conditions” requiring an equitable adjustment of the contract price under a clause contained in the contract, and (2) the City’s alleged breach of the contract by delay and failure to prepare the construction site as warranted. The City counterclaimed for liquidated damages due to delay and faulty work. The City’s appeal contests the District Court’s findings as to liability and its assessment of damages. Moorhead cross-appeals for lost profits which the court refused to award.

As an initial point on appeal, the City challenges the District Court’s July 25, 1973, grant of summary judgment on the City’s third party complaint against the phase I contractor, Valley-Mayo. Although Valley-Mayo has apparently not been fully joined as a party to this appeal, the issue of the propriety of the judgment is properly before this court. 1 The grant of summary judgmenl *1012 pursuant to Valley-Mayo’s Rule 56 motion was based on the court’s holding that there existed no issues of material fact to be decided to determine Valley-Mayo’s liability to the City, and that the City was entitled, as a matter of law, to no relief. Fed.R.Civ.P. 56(c).

A review of the record indicates that the court’s factual findings are supported by the record and are not clearly erroneous. They are entitled to affirmance. Fed.R.Civ.P. 52(a). The only issue of law essential to the dismissal was whether, in the event Moorhead successfully recovered from Grand Forks, the City could in turn recover against Valley-Mayo under the phase I contract’s one-year “hold harmless” indemnity bond. The fundamental principle of third party practice is that in order to maintain a third party complaint, a direct line of liability must be alleged to exist between the third party plaintiff and third party defendant independent of that between the first party plaintiff and defendant. 6 C. Wright and A. Miller, Federal Practice and Procedure § 1442 at 206 (1971); Fed.R.Civ.P. 14(a); cf. United States Fidelity & Guaranty Co. v. American State Bank, 372 F.2d 449, 450 (10th Cir. 1967). Thus, the City’s arguments that Moorhead’s claim actually rests on delays and changed conditions caused ultimately by the phase I contractor, Valley-Mayo, and not by the City, are of no avail. The causal relationship is of no avail to the City if the legal basis for indemnity between it and Valley-Mayo has been terminated. The City previously had accepted Valley-Mayo’s work and discharged it from further obligations under its contract, without reserving any claims. Absent fraud or latent defects, the City thus waived any rights against Valley-Mayo which may have arisen because of delay or on the performance bond. 5 Williston on Contracts § 724 (3d ed. 1961). Valley-Mayo’s obligations to the City were discharged by the contractor’s acknowledged full and exact performance. 5A Corbin on Contracts § 1230 at 510 (1964). The District Court’s order dismissing the third party complaint against Valley-Mayo with costs is affirmed.

The City’s various assertions of error challenging its liability for Moor-head’s extra costs are essentially challenges to the District Court’s findings of fact intertwined with contract interpretation. On appeal this court is not authorized to conduct a de novo review of cases tried without a jury. The District Court’s findings must be sustained if not clearly erroneous. Fed.R.Civ.P. 52(a); Brown v. Scott, 454 F.2d 693, 694 (8th Cir.), cert. denied, 409 U.S. 846, 93 S.Ct. 50, 34 L.Ed.2d 86 (1972). The District Court based its finding of contract liability upon the “changed conditions” clause, and the City’s breach of an implied warranty that the site would be prepared and the soil compacted in accordance with phase I specifications.

At the time Moorhead bid on the phase II contract, the phase I earth work had just commenced. Because an inspection of the site by Moorhead would not then have disclosed the difficult site conditions which it would later face due to excess moisture and lack of compaction, Moorhead in estimating its bid necessarily relied upon the City to provide a construction site prepared in accord with the specifications of phase I. Those specifications, according to the District Court, called inter alia for 90% compaction of the soil embankments and cell bottoms. The court construed the phase I compaction specifications as implied warranties in the phase II contract. Construction of the contract is a matter for the court under North Dakota law. Eickhof Construction Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Md Holdings v. Nextgen Energy
Vermont Superior Court, 2026
Bulfin v. Rainwater
E.D. Missouri, 2021
Lighting & Power Services, Inc. v. Roberts
354 F.3d 817 (Eighth Circuit, 2004)
Lighting & Power Services, Inc. v. Wayne M. Roberts
354 F.3d 817 (Eighth Circuit, 2004)
United States v. Basin Electric Power Cooperative
248 F.3d 781 (Eighth Circuit, 2001)
McKie v. Huntley
2000 SD 160 (South Dakota Supreme Court, 2000)
Lopez De Robinson v. United States
162 F.R.D. 256 (D. Puerto Rico, 1995)
Municipality of Anchorage v. Frank Coluccio Construction Co.
826 P.2d 316 (Alaska Supreme Court, 1992)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
Prichard Bros., Inc. v. Grady Co.
436 N.W.2d 460 (Court of Appeals of Minnesota, 1989)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Mooney v. Frierdich
784 F.2d 875 (Eighth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
508 F.2d 1008, 1975 U.S. App. LEXIS 16751, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moorhead-construction-co-inc-a-corporation-appellee-cross-appellant-v-ca8-1975.