Van Nice v. Christian Reformed Church

231 N.W. 604, 59 N.D. 564, 1930 N.D. LEXIS 174
CourtNorth Dakota Supreme Court
DecidedJune 28, 1930
StatusPublished
Cited by3 cases

This text of 231 N.W. 604 (Van Nice v. Christian Reformed Church) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Nice v. Christian Reformed Church, 231 N.W. 604, 59 N.D. 564, 1930 N.D. LEXIS 174 (N.D. 1930).

Opinion

*567 ChRistiaNSON, J.

In April, 1928, the plaintiff and defendant entered into a written contract whereby the plaintiff agreed to construct a church for the defendant. The church was constructed, and, controversy having arisen between the parties in respect to several matters involved in or growing out of the transaction between them, plaintiff brought this action to recover the sum of $5,378.16, which he claims is the balance due him for the work performed and material furnished in the construction of the church. The complaint, among other things, alleges that during the course of the construction certain changes were made in the plans, and that owing to certain defects which developed as the building was being constructed (according to the plans and specifications) it became necessary to repair such defects; that as a consequence additional labor and material was required, and compensation is asked for the value of the material and labor so furnished.

*568 The defendant in its answer admits that certain changes were made in the plans but that such changes were made in due season and in such manner and at such times as not to necessitate any additional expense either for material or work on the part of the plaintiff. The answer further alleges that the plaintiff has failed to pay for certain material used in the construction and that liens have been filed against the building for such material. The answer, by counterclaim, alleges that the plaintiff failed to erect the building properly and in accordance with the plans and specifications; that it was defectively constructed and left in a defective and incomplete condition, and that, consequently, defendant was damaged in the sum of $5,000, for which judgment is asked. The plaintiff interposed a reply denying the new matter in •the answer.

The case was tried to a jury and resulted in a verdict in favor of the plaintiff for $4,500. The defendant moved for a new trial. The motion was denied and it has appealed from the judgment and from the order denying a new trial.

The facts necessary to an understanding of the questions presented for determination on this appeal are substantially as follows: The members of the defendant church, having decided to construct a new church building, selected a building committee and this committee employed an architect who prepared plans and specifications for the proposed church building. Thereafter the building committee advertised for bids for the construction of the church in accordance with the plans and specifications which had been prepared by the architect. Bids were received from a number of builders, among others,- from the plaintiff. The plaintiff was not the lowest bidder. All proposed bids were rejected, but after the rejection of the bids certain conversations were had between the plaintiff and the members of the building committee with the result that the plaintiff and such committee arrived at an understanding as regards the construction of the church and a written contract was entered into between them. The contract was first signed by the plaintiff and was later signed by the representatives of the defendant at a meeting of the building committee at which the plaintiff was present. There is a square conflict in the evidence as to some things said to have transpired at this meeting. The written contract contained a provision to the effect that the plaintiff should be paid *569 $800 for a certain item of glass to be furnished in tbe construction of the building. The written contract shows that this provision is stricken out with pen and ink. The plaintiff claims that this provision was a part of the contract at the time it was executed by the parties; that it was stricken out after the contract had been signed by both the parties and that as a matter of fact it was and is a part of the contract.

The members of the building committee, on the other hand, testified that this was stricken out at the suggestion of the plaintiff and in his presence after he had signed the contract but before it was signed by the representatives of the defendant. The testimony upon this feature of the case was submitted to the jury under appropriate instructions and so far as the record shows, both parties had a fair trial of that question.

The written contract contains the following provision: “Art. 30. Guaranty Bonds. The owner shall have the right, prior to the signing of the contract, to require the. contractor to furnish bond covering the faithful performance of the contract and the payments of all obligations arising thereunder, in such form as the owner may prescribe and with such sureties as he may approve. If such bond is required by instructions given previous to the submission of bids, the premium shall be paid by the contractor; if subsequent thereto, it shall be paid by the owner.”

It is undisputed that the building committee required the defendant to furnish a bond conditioned as provided in this article and that such requirement was made at the meeting at which the building committee signed the contract and prior to the signing. It is also undisputed that no bond was required by instructions given previous to the submission of bids by the various bidders. In the circumstances it is obvious that if the provision in the written contract governs, the plaintiff was and is entitled to recover the amount of the premium paid by him for the surety bond required, namely, $244. The defendant, however, claims, and offered to prove, that during the negotiations had between the parties at the meeting at which the contract was signed by the representatives of the defendant, the plaintiff agreed to pay the premium on the surety bond. The trial court excluded the testimony of the witnesses for the defendant who sought to testify to this effect and likewise sustained an objection to the offer of proof. The proffered *570 testimony was objected to on the ground that it tended to contradict and vary the terms of the written contract. There is no allegation in the answer and no claim that the representatives of the defendant were induced t'o sign the contract through any misrepresentation or fraud on the part of the plaintiff or through mistake or duress. According to the testimony of the representatives of the defendant they signed it knowingly and deliberately, and according to such testimoiry they took scrupulous care to eliminate from the contract the item relating to the payment for certain glass. That the testimony sought to be introduced by the defendant contradicting the provisions of the written contract was properly excluded seems too clear for controversy. Such testimony was clearly within the rule which prohibits the introduction of oral testimony to contradict or vary the terms of a written contract.

Error is also predicated upon the rulings of the court which permitted the plaintiff to introduce evidence showing that he performed extra work and furnished additional material in installing additional bracing of the roof and in installing certain windows in a manner different from that prescribed in the plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dobler v. Malloy
190 N.W.2d 46 (North Dakota Supreme Court, 1971)
Peterson v. Bober
56 N.W.2d 331 (North Dakota Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
231 N.W. 604, 59 N.D. 564, 1930 N.D. LEXIS 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-nice-v-christian-reformed-church-nd-1930.