Dobler v. Malloy

190 N.W.2d 46, 1971 N.D. LEXIS 145
CourtNorth Dakota Supreme Court
DecidedAugust 31, 1971
DocketCiv. 8689
StatusPublished
Cited by5 cases

This text of 190 N.W.2d 46 (Dobler v. Malloy) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dobler v. Malloy, 190 N.W.2d 46, 1971 N.D. LEXIS 145 (N.D. 1971).

Opinion

ERICKSTAD, Judge.

This case originated in the district court, Stark County, North Dakota, on a claim for relief based upon contract, wherein the plaintiff Emil Dobler, doing business as Queen City Lumber, and hereinafter referred to as Dobler, sought damages for breach of contract from the defendants, Harry L. Malloy and his wife Lorraine Malloy, both hereinafter referred to as Malloy. Malloy counterclaimed for damages, alleging breach of contract by Dob-ler.

The district court sitting without a jury found for Malloy and ordered judgment in the sum of $7,054.64 plus costs. Dobler thereafter moved to amend and supplement the findings of fact, conclusions of law, and order for judgment, and, in the alternative, for a new trial. The district court denied the motion.

Dobler appeals to this court from the judgment entered in this case on June 1, 1970. He demands a trial de novo. He also appeals from the order of the district court denying his motion to amend the findings of fact and conclusions of law and his alternative motion requesting a new trial.

Malloy contends that Dobler’s appeal from this order is invalid, since the appeal was taken prior to the service of the order. Dobler’s notice of appeal is dated August 6, 1970. It was filed with the clerk of court on August 7, 1970. The affidavit of service by mail of the order denying the motion is dated August 7, 1970. The order denying the motion is dated August 5, 1970, and was filed on August 12,1970.

The question of the timing of an appeal is governed by Section 28-27-04, N.D.C.C.

“28-27-04. Time for appeal. — An appeal from a judgment may be taken within ninety days after the entry thereof by default or after written notice of the entry thereof, in case the party *49 against whom it is entered has appeared in the action, and from an order within sixty days after written notice of the same shall have been given to the party appealing.”

It is the intent of this section to prevent the lapse of a party’s right to appeal by tolling the statutory period within which an appeal can be taken until the party has received written notice of the entry of judgment or written notice of the order adverse to him.

An appealing party may waive the service of a written notice. He need not do so, but he may. In this case, he waived the service of written notice by taking the appeal; accordingly, the purpose of Section 28-27-04 was fulfilled. Klaudt v. Klaudt, 156 N.W.2d 72, 76 (N.D.1968). An appeal from an order can be taken before such order is filed with the clerk of the district court. Lake Grocery Co. v. Chiostri, 31 N.D. 616, 154 N.W. 533 (1915). Dobler’s appeal from this order is valid, since it was taken within the statutory period allowed for an appeal from an order.

On September 18, 1968, Dobler and Mal-loy entered into a written agreement for the construction of Malloy’s future home near Dickinson, North Dakota. This written agreement provides in part as follows:

“It is agreed that the First Party [Dobler] will provide and furnish all materials and that said materials are to be of top quality, equipment, skills and labor necessary to do a proficient workmanlike job according to the highest standards of labor in the Dickinson area.
“It is further agreed that the said dwelling will be built on a cost-plus basis as follows:
“Labor — cost plus 25%
“Materials — cost plus 10%
“Sub-contracts — 5%
“Equipment Rentals — 5%
“This cost-plus feature shall not apply to materials obtained from First Party which are to be provided at a 10% discount, or what is commonly referred to as a contractor’s discount.
“It is further agreed that the First Party agrees to employ David Olheiser who shall be in charge of all phases of construction and generally an overseer and foreman with the absolute right to inspect and reject all materials and labor put on or into the premises, with owner having final authority.
“It is further agreed that the owner or his agent shall have the right of inspection at any time and in the event that owner or his agents object to any material or to the quality of the labor being performed, that the owner shall have the right to terminate this agreement for good cause shown unless such condition or conditions are corrected by First Party within five (5) days’ time. Likewise, if owner fails to make the payments as set forth in the following schedule without good cause, the First Party shall have the right to discontinue work upon five (5) days’ notice to owner and terminate this contract.
“It is further agreed that the cost of the finished product, with paint, including but not limited to the dwelling and garage proper, sidewalk, twenty-five feet of concrete driveway to garage, scraped out road from present access road to garage in a U or Y design, cess pool and attachments, septic tank and attachments with overflow features and pump all completely hooked up and functional, including water (less well) hooked up and functioning, plumbing, heat and air-conditioning, electrical, carpet and tile flooring, less certain rooms indicated as unfinished in the basement, but also including landscaping around the house and scraping in or filling ditch on east boundary of property, shall not exceed a total cost to owner of Thirty-nine Thousand Eight Hundred Dollars ($39,800.- *50 00), notwithstanding the cost-plus feature of this Agreement,* and that this figure is an absolute maximum to be paid by owner under this contract, unless changes, approved in writing by the owner, shall raise the cost of the total finished product to a figure in excess of $39,800.00.” [A footnote to page 2 of the contract provides that: “ *It is agreed that the owner shall have the benefit of whichever method proves to be the least expensive, either cost-plus or the maximum of $39,800.00 on a contract basis.”]

Prior to and during the course of the construction of Malloy’s home, numerous changes were made in the architect’s floor plan and in the specifications outlined in the written agreement. The dimensions of the house were changed by expanding the bedroom wing of the house, by expanding the garage, and by altering the design of the family dining area. These changes were made prior to the pouring of the footings and the foundation. Subsequently, closets, walls, doors, and stairways were relocated, and the size of the living room was expanded at the expense of the formal dining area. Several items called for in the contract to make a complete house were deleted. These items included the electrical system and carpeting.

In addition, many other changes were ordered to upgrade certain materials used in the house from top quality to superior quality items. These changes included superior tile, shingles, bricks, doors, and a superior garage door. Of the many changes made in the house, the only items agreed to in writing were the deletion of the electrical system and carpeting. Neither party disputes that these changes were made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glatt v. Bank of Kirkwood Plaza
383 N.W.2d 473 (North Dakota Supreme Court, 1986)
Dorgan v. Mercil
269 N.W.2d 99 (North Dakota Supreme Court, 1978)
State v. Stokes
240 N.W.2d 867 (North Dakota Supreme Court, 1976)
Dobler v. Malloy
214 N.W.2d 510 (North Dakota Supreme Court, 1973)
Petrulli v. Approved Dry Wall Construction, Inc.
284 So. 2d 27 (District Court of Appeal of Florida, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
190 N.W.2d 46, 1971 N.D. LEXIS 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dobler-v-malloy-nd-1971.