Lighting & Power Services, Inc. v. Roberts

354 F.3d 817, 2004 WL 51248
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 13, 2004
Docket02-3697
StatusPublished
Cited by1 cases

This text of 354 F.3d 817 (Lighting & Power Services, Inc. v. Roberts) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lighting & Power Services, Inc. v. Roberts, 354 F.3d 817, 2004 WL 51248 (8th Cir. 2004).

Opinion

HANSEN, Circuit Judge.

Lighting & Power Services (“LPS”) filed suit against Wayne M. Roberts, Inc. (“Roberts”) to recover additional construction costs pursuant to the Miller Act, 40 U.S.C.A. §§ 3131-3133 (West Supp.2003). 1 A jury found in favor of Roberts. On appeal, LPS argues that the district court erroneously instructed the jury on the total cost method of recovery. We agree, we reverse the judgment of the district court, and we remand for further proceedings.

I. Background

This dispute stems from a government construction project at Jefferson Barracks in St. Louis, Missouri. Roberts was the general contractor for the United States government; LPS was Roberts’s electrical subcontractor. The construction contract required Roberts to obtain a payment *819 bond under the Miller Act to protect subcontractors and suppliers. 2 The renovation was scheduled for completion in six months, but ultimately took over twenty-two months. Both parties conceded that the government caused the delays.

LPS filed suit under the Miller Act, seeking to recover the additional costs it incurred as a result of the delay. 3 LPS used the total cost method to calculate its damages and sought $110, 641.00. The district court instructed the jury as follows:

Instruction No. 5
In this case, the plaintiff seeks to prove its alleged damages by evidence of its total costs of performing its subcontract with Wayne M. Roberts, Inc. In order to establish damages in this way, the plaintiff must prove by a preponderance of the evidence that:
1. It is impracticable for the plaintiff to prove its actual losses directly;
2. The plaintiffs bid that was accepted by Wayne M. Roberts, Inc. was reasonable;
3. Plaintiffs actual costs were reasonable;
4. Defendant has some responsibility in causing plaintiffs actual losses; and
5. Plaintiff incurred damages as a consequence.

(Appellant’s App. at 129.) The jury returned a verdict in favor of Roberts. On appeal, LPS argues that subpart four of the instruction was given in error because the Miller Act permits LPS to recover its additional costs of labor and materials regardless of Roberts’s responsibility for causing those costs. Roberts responds that subpart four of the instruction was required by the law of this circuit because LPS chose to calculate its damages using the total cost method.

II. Standard of Review

A district court has broad discretion in formulating jury instructions. Generally, we review jury instructions given by a district court for abuse of discretion. Hartley v. Dillard’s, Inc., 310 F.3d 1054, 1058 (8th Cir.2002). Our review is limited to determining whether the instructions, when taken as a whole and in light of the particular issues presented, fairly and adequately presented the evidence and the applicable law to a jury. Id. at 1058-59. We will not reverse for instructional error *820 unless we find that the error affected the substantial rights of the parties. Id. at 1059.

A litigant’s objection to a jury instruction must comply with Federal Rule of Civil Procedure 51 in order to be preserved for appellate review. At the time of this trial, Rule 51 required a party to make objections to a jury instruction before the jury retired. When a party fails to comply with Rule 51, we are limited to reviewing the district court’s decision for plain error. Jones Truck Lines, Inc. v. Full Serv. Leasing Corp., 83 F.3d 253, 256-57 (8th Cir.1996).

After carefully reviewing the transcript, we hold that LPS’s objections to instruction five were sufficient for the purposes of Rule 51, as it existed at the time of trial. During the instructions conference at the conclusion of evidence, LPS made known on the record its precise objections to the court’s proposed instruction, particularly as to subpart four of instruction number five. (Tr. Vol.HI, pp. 68, 69, 72, 74.) The trial court also clearly indicated that it was overruling the objections and would give the objected-to instruction to the jury. (Id. at 82.) This court has held that Rule 51 does not require rigid formality in making an objection, as long as the district court was clearly aware of a litigant’s objections. Brown v. Sandals Resorts Int'l, 284 F.3d 949, 953 n. 6 (8th Cir.2002) (citing Meitz v. Garrison, 413 F.2d 895, 899 (8th Cir.1969)). We are convinced that the district court well understood the nature of LPS’s objection, and that it would have given the same instruction even if LPS’s counsel had restated the objection after the jury was instructed and before it commenced deliberation. See Ross v. Garner Printing Co., 285 F.3d 1106, 1112 (8th Cir.2002).

We note that Rule 51 was substantially revised effective December 1, 2003. 4 The Supreme Court’s order of March 27, 2003, amending the Rule states that the amended rule “shall govern in all proceedings in civil cases thereafter commenced, and, insofar as just and practicable, all proceedings then pending.” Applying new Rule 51(b) and (c) to the record of the instruction conference held in this case, we conclude that LPS’s objection to instruction five was both adequate and timely.

III. Jury Instruction 5

We first address the question of whether, in order to recover delay damages under the Miller Act, a subcontractor *821 is required to show that the general contractor was at least partially to blame for the subcontractor’s actual losses. We hold that the Miller Act does not require that the general contractor be at fault in order for the subcontractor to recover on the Miller Act payment bond.

This court first addressed this question in Consol. Elec. & Mech., Inc. v. Biggs Gen. Contracting, Inc., 167 F.3d 432 (8th Cir.1999). In Consolidated, an electrical subcontractor sued a general contractor and a surety company on a payment bond under the Miller Act. Consolidated, 167 F.3d at 433-34.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lighting & Power Services, Inc. v. Wayne M. Roberts
354 F.3d 817 (Eighth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
354 F.3d 817, 2004 WL 51248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lighting-power-services-inc-v-roberts-ca8-2004.