Mergentime Corp. v. Washington Metropolitan Area Transportation Authority

400 F. Supp. 2d 145, 2005 U.S. Dist. LEXIS 38878, 2005 WL 3208227
CourtDistrict Court, District of Columbia
DecidedNovember 28, 2005
DocketCIV. 89-1055(TFH)
StatusPublished

This text of 400 F. Supp. 2d 145 (Mergentime Corp. v. Washington Metropolitan Area Transportation Authority) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mergentime Corp. v. Washington Metropolitan Area Transportation Authority, 400 F. Supp. 2d 145, 2005 U.S. Dist. LEXIS 38878, 2005 WL 3208227 (D.D.C. 2005).

Opinion

MEMORANDUM OPINION

THOMAS F. HOGAN, Chief Judge.

In Herman Melville’s Moby-Dick, the first mate is the ironically named Star-buck, a star-crossed sailor who cannot “buck the stars” and avoid his fatal destiny. Just so this protracted litigation. This star-crossed case has been in the hands of two prior judges in this Court, who both died shortly after rendering opinions in this litigation. Indeed, due to no fault of any court or counsel, this litigation has begun to assume the dimensions of Jarndyce v. Jarndyce, the protracted litigation in Charles Dickens’s Bleak House. Charles Dickens, Bleak House (J.M. Dent & Sons 1972) (1953).

Most recently, this star-crossed judicial journey comes before the Court after a 25-day bench trial to determine whether defendant and counter-plaintiff Washington Metropolitan Area Transit Authority (“WMATA”) justifiably terminated for default the joint venture contractor responsible for construction of the Shaw Street and U Street Stations and connecting tunnels for the Washington, D.C. metropolitan area’s subway system, called the Metrorail System (“Metro”), on May 11, 1990. The joint venture and plaintiffs in the case— two construction companies, Mergentime *151 Corporation (“Mergentime”) and Perini Corporation (“Perini”) (collectively, “M/P” or “the Joint Venture”) — allege wrongful termination and claims for breach of contract under the terminated Shaw Street Station (“Shaw Station”) and U Street Station contracts. WMATA counterclaimed to recover reprocurement costs, liquidated damages, and other credits and damages. Counter-defendant Insurance Company of North America (“INA”) was the surety for the performance bonds on both contracts and also asserts claims against WMATA.

After carefully reviewing all the evidence presented, the representations made at trial, the record in this case, and applicable law, the Court concludes that WMA-TA’s termination for default of the Joint Venture was justified and that the Joint Venture is liable to WMATA for damages as detailed below. The Court also concludes that WMATA is responsible to the Joint Venture for the outstanding claims detailed below.

Historical Overview of the Dispute and Litigation

To determine the disputed issues, including whether WMATA lawfully terminated M/P for default, this Court must decipher a complex factual history that began in 1984 with WMATA’s bid invitation for construction of the Shaw Station. In addition, the litigation history has involved years of discovery, separate proceedings before three trial court judges and the Court of Appeals, and multiple opinions from both this Court and the appellate court. To decide this dispute, the Court conducted a trial; — which included oral testimony from numerous live witnesses and thousands of exhibits — and carefully reviewed the entire record in this case, including the many Opinions issued by the two predecessor judges and the Court of Appeals.

While the procedural history and facts were extensively described by the D.C. Circuit in Mergentime Corp. v. WMATA, 166 F.3d 1257, 1260-61 (D.C.Cir.1999), the Court will detail the most relevant aspects fcir -the sake of context. As Judge Rever-comb succinctly stated, “[t]his case is about how not to. build a subway system” — the Shaw and U Street stops on Metro’s Green Line. Mergentime Corp. v. WMATA No. 89-1055, 1993 WL 328083, at *1 (D.D.C. July 30, 1993) (“Revercomb Op.”). In 1985 and 1986, WMATA awarded two separate contracts totaling $94 million to M/P to build the stops and associated tunnels. During the course of the construction, this Joint' Venture encountered various circumstances that caused delay. For example, M/P was faced with differing site conditions, including unanticipated boulders and the need for grouting. In addition, the District of Columbia Department of Public Works (“DPW”) rejected M/P’s traffic maintenance plan, which resulted in prolonged negotiations and reworking of the plans to handle street closings and traffic during the projects.

Among other things, M/P claimed it was owed reimbursement for additional costs incurred during construction as a result of these delays. Accordingly, M/P filed suit in this case on April 14, 1989 for breach of contract due to WMATA’s alleged failure to process claims submitted by M/P in a timely fashion. Mergentime Corp. v. McElhenny, Civ. No. 89-1055 (D.D.C. Apr. 14, 1989). Negotiations and subsequent agreements aimed at salvaging the projects followed; however, WMATA eventually terminated M/P for default on May 11, 1990. As a result, M/P amended its complaint and the litigation resumed.

M/P now seeks to collect on its reimbursement claims and subsequently added claims for breach of contract and wrongful *152 termination, while WMATA has counterclaimed to recover the costs it paid to other contractors to complete the work, credits owed to it by M/P, and other damages. 1 Following a 45-day bench trial, Judge Revercomb issued a 251-page opinion in July 1993 that found, among other things, that WMATA justifiably terminated M/P for default and was entitled to reprocurement costs, and that M/P established the merit of Shaw Street reimbursements but not an entitlement to the claims. Judge Revercomb was unable to quantify the claims and did not make any conclusions with respect to U Street claims before he passed away two days later. Judge Green, serving as the successor judge pursuant to Federal Rule of Civil Procedure 63, handled the post trial motions.

Upon both parties’ appeals, the Court of Appeals reversed the successor judge’s rulings for failing to comply with Federal Rule of Civil Procedure 63, and remanded the case back to this Court. 2 After additional briefing by parties regarding the remand procedures, this Court ruled that a new trial would be necessary in this case because it could not certify adequate familiarity with the record pursuant to Rule 63. Specifically, the Court determined that this case could not be completed in the absence of a new trial without prejudice to the parties. Thus, the Court conducted a 25-day bench trial, which was followed by closing arguments by counsel.

This opinion provides the Court’s findings of facts and conclusions of law, pursuant to Federal Rule of Civil Procedure 52(a). These findings of fact are based on a thorough evaluation of all the evidence and the parties’ proposed findings, and replies thereto. In making these findings, the Court relies in large part upon its determination of the credibility of those witnesses based on, among other things, its observation of their demeanor and the inherent probability of their testimony in light of the documentary evidence and other known facts. 3

FINDINGS OF FACT

Free access — add to your briefcase to read the full text and ask questions with AI

Related

College Point Boat Corp. v. United States
267 U.S. 12 (Supreme Court, 1925)
L. W. Foster Sportswear Co., Inc. v. The United States
405 F.2d 1285 (Court of Claims, 1969)
The United States v. Johnson Controls, Inc.
713 F.2d 1541 (Federal Circuit, 1983)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
In Re Nattrass (Peter J.)
950 F.2d 730 (Federal Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
400 F. Supp. 2d 145, 2005 U.S. Dist. LEXIS 38878, 2005 WL 3208227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mergentime-corp-v-washington-metropolitan-area-transportation-authority-dcd-2005.