In Re Boston Shipyard Corp., Debtor. Appeal of Boston Shipyard Corp

886 F.2d 451, 1989 WL 110791
CourtCourt of Appeals for the First Circuit
DecidedSeptember 27, 1989
Docket89-1144
StatusPublished
Cited by53 cases

This text of 886 F.2d 451 (In Re Boston Shipyard Corp., Debtor. Appeal of Boston Shipyard Corp) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Boston Shipyard Corp., Debtor. Appeal of Boston Shipyard Corp, 886 F.2d 451, 1989 WL 110791 (1st Cir. 1989).

Opinion

TORRUELLA, Circuit Judge.

Boston Shipyard Corporation (“BSC”) appeals from the decision of the district court, which affirmed the bankruptcy court’s grant of summary judgment in favor of appellee, the United States Military Sealift Command (“MSC”).

I. Background

BSC entered into a contract with MSC to overhaul the USNS Mississinewa. This contract was awarded even though BSC was in the midst of a Chapter 11 reorganization in the bankruptcy court. The original contract called for a 100 day performance period and for BSC to be paid $4,997,-925.

As often happens, the contract proved to require much more time and expense than was originally anticipated. Each point that BSC realized a change in the contract specifications would be required, it filed a condition report or change order requesting authorization for the necessary changes so that the work could be done. Hundreds of these change orders were submitted and BSC claims that the delay in their resolution led to increased financial burdens on BSC, as well as to greatly hindered progress, causing the work to fall far behind schedule.

By the end of August 1985, BSC’s financial condition had worsened and MSC payments were necessary for the company’s continued ability to perform on the contract. BSC filed a claim seeking $536,-132.31 in costs caused by alleged delays and disruption by MSC. Work had significantly slowed down due to a work stoppage by BSC’s sub-contractors after payments to them were not made. MSC issued a cure notice to BSC advising it that the contract would be terminated within ten days unless BSC’s subcontractors resumed work.

On Friday, August 30, BSC’s president, Kenney, met to negotiate this dispute with MSC’s deputy contracting officer, Rapka. Kenney hoped to receive progress payments for that week, negotiate a settlement of claimed costs due to delay and disruption, and to obtain a final determination of BSC’s request for “advance payments.” At this meeting, Rapka offered Kenney approximately $500,000 for monies owed up to that date and as settlement for all claimed delay and disruption costs *453 through August 30. Also, MSC asked Ken-ney to withdraw his request for advance payments. This settlement was written up as Modification 14 to the contract.

Although Kenney did not want to sign the modification, and stated that he thought it was “ambiguous” and “inconsistent with the oral agreement,” he did sign after being told that he would then immediately be given a check for the $500,-000. Two hundred payroll checks had to be distributed that day to BSC employees. Kenney, in an affidavit, stated that they could not have been paid unless he had received the money from MSC and, therefore, he concluded that he had no choice but to agree to the modification. He signed the modification and MSC then paid the full amount agreed upon.

On September 6, Kenney and Rapka met again. Rapka asked Kenney to sign a “receipt” stating that the money received on August 30 had been primarily for certain progress payments. 1 Although Kenney disagreed with the wording of the receipt, he signed the document after being told that he would receive no progress payment that day unless he did.

BSC curtailed its operations on the contract effective October 17, due, it claims, to the “effect of MSC’s delays, disruption and failure to compensate BSC.” Brief of Appellant at 24. A press release issued on that day stated that “[t]oday Boston Shipyard Corp. is forced to cease operations.” On November 15, MSC terminated the contract because of this default by BSC.

The government filed a Proof of Claim in the United States Bankruptcy Court on February 25, 1986 seeking $9.2 million in reprocurement costs. BSC objected to the Proof of Claim and filed a counterclaim seeking to convert the default termination into a termination for the convenience of the government.

The government filed a motion for partial summary judgment, arguing that Modification 14 settled and released all claims against MSC up to and including August 30. The bankruptcy court granted this motion. Six months later, after full briefing and a hearing on the issues, the bankruptcy court entered summary judgment in favor of the government on the remainder of the case, based on its conclusion that BSC had inexcusably abandoned the contract. Upon appeal, the district court affirmed both summary judgment orders and BSC now appeals this decision.

II. Standards for Review of Summary Judgments

Summary judgment is appropriate under Rule 56(c) of the Federal Rules of Civil Procedure when there exists no genuine issue of material fact and, as a matter of law, the movant is entitled to a judgment. Oliver v. Digital Equipment Corp., 846 F.2d 103,105 (1st Cir.1988). Although “the mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment,” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 2509-10, 91 L.Ed.2d 202 (1986) (emphasis in original), we will review the record in the light most favorable to the non-movant and will, of course, indulge all inferences favorable to that party. Oliver, 846 F.2d at 105.

III. The Partial Summary Judgment

BSC asserts that Modification 14 is void and therefore should not have controlled the bankruptcy court’s partial summary judgment decision. It bases this argument on two grounds.

A. Lack of Consideration

First, BSC argues that Modification 14 was not supported by proper considera *454 tion. It claims that the $500,000 payment was a progress payment, already due to it, and was not a settlement of the costs for delay and disruption. It relies on an internal memorandum of MSC which stated, in regard to the August 30 payment, that “this payment is being made as progress for the following....” The memo then broke down the figure into the same components as were later inscribed on the receipt of September 6. See footnote 1, supra. Also, another MSC memo stated “I asked [Kenney] to sign a breakdown of the progress payments for 30 Aug 85.... This breakdown specifically states the payments are progress payments and not delayed (sic) or disruption.”

The district court and the bankruptcy court both agreed with the government that, as a matter of law, there was ample consideration to support this modification. The district court found that, accepting all of BSC’s allegations as true, the amount paid on that day was at least in part to settle BSC’s disputed claim to delay and disruption costs and to release MSC from these claims. Therefore, because the money was not given solely to satisfy an acknowledged debt, there was good consideration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Maine, 2026
Bennigson v. Solomon R. Guggenheim Found.
2024 NY Slip Op 24164 (New York Supreme Court, New York County, 2024)
Zanoli v. Keurig Dr. Pepper
D. Massachusetts, 2020
Smith v. Zipcar, Inc.
125 F. Supp. 3d 340 (D. Massachusetts, 2015)
Oquendo v. CCC Terek
111 F. Supp. 3d 389 (S.D. New York, 2015)
Pilalas v. The Cadle Co
695 F.3d 12 (First Circuit, 2012)
Donald Dean & Sons, Inc. v. Xonitek Systems Corp.
656 F. Supp. 2d 314 (N.D. New York, 2009)
Cabot Corp. v. AVX Corp.
863 N.E.2d 503 (Massachusetts Supreme Judicial Court, 2007)
Wright v. Eastman Kodak Co.
445 F. Supp. 2d 314 (W.D. New York, 2006)
Bard v. Mark Steven CVS, Inc.
378 F. Supp. 2d 33 (D. Rhode Island, 2005)
Cabot Corp. v. AVX Corp.
18 Mass. L. Rptr. 36 (Massachusetts Superior Court, 2004)
General Motors Corp. v. Firepond, Inc.
16 Mass. L. Rptr. 528 (Massachusetts Superior Court, 2003)
Fe-Ri Construction Inc. v. Intelligroup, Inc.
218 F. Supp. 2d 168 (D. Puerto Rico, 2002)
Hogan v. Eastern Enterprises/Boston Gas
165 F. Supp. 2d 55 (D. Massachusetts, 2001)
Morganti National, Inc. v. United States
49 Fed. Cl. 110 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
886 F.2d 451, 1989 WL 110791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-boston-shipyard-corp-debtor-appeal-of-boston-shipyard-corp-ca1-1989.