Adler Construction Co. v. United States

423 F.2d 1362, 191 Ct. Cl. 607
CourtUnited States Court of Claims
DecidedApril 17, 1970
DocketCong. No. 10-60
StatusPublished
Cited by6 cases

This text of 423 F.2d 1362 (Adler Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adler Construction Co. v. United States, 423 F.2d 1362, 191 Ct. Cl. 607 (cc 1970).

Opinion

Per Curiam :

This case was referred to Trial Commissioner C. Murray Bernhardt with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a) [since September 1, 1969, Rule 134(h)]. The commissioner has done so in an opinion and report filed on June 11,1969. Exceptions to the commissioner’s opinion, findings and recommended conclusion of law were filed by plaintiff. Defendant urged the court to adopt the commissioner’s opinion as its decision in this case. The case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the opinion, findings and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, plaintiff is not entitled to recover and the petition is dismissed.

OEINION OE COMMISSIONER

Bernhardt, Commissioner: The issue of dispositive stature in this unduly protracted Government contract case is the validity of a release containing express reservations executed by plaintiff contractor in November 1956 following completion in August 1956 of a dam he built for the Bureau of Reclamation. The finality of the release is so apparent as to obviate a more than cursory recital of the issue-related facts so prolixly established in the accompanying findings, and to permit the omission entirely from such findings of those facts relating to the damage issue despite the wealth of record thereon.1

[610]*610If valid and not waived, the release extinguishes all of plaintiff’s present claims sounding in changed conditions, cardinal change, misrepresentation, erroneous classification of excavated materials, and errors in bid, since none of these are preserved, specifically or inferentially, by the 13 enumerated exceptions to the release. See H.L.C. & Associates, 176 Ct. Cl. 285, 376 F. 2d 586 (1966) and cases cited therein.

After partial correction of obvious errors in plaintiff’s improvidently low bid (findings 5-25), the plaintiff was given notice to proceed in November 1952, reaching substantial completion on August 15,1956, instead of the original completion date of June 25, 1955 (finding 26), the delays being covered by time extensions (finding 64). Radically changed conditions were encountered (findings 28-38), involving not only excessive overruns of excavation and fill material at the main damsite (findings 39-41), but also extraordinarily rough foundation terrain (findings 37-38), which completely disrupted and slowed down plaintiff’s planned work sequence and increased his costs commensurately (findings 50-52), as well as occasioning demands by the contracting officer for acceleration of the work (findings 53-57), including working through the markedly severe winter of 1955-56 at a loss of 45 percent efficiency (findings 58-60). The circumstances were ideal as the basis of a claim under the changed conditions clause of the contract, but such a claim was not presented in season.

On July 6, 1956, the plaintiff, in consideration of the payment of $43,314.39 for certain changes, agreed in writing to withdraw all then pending claims for compensation and to make no new claims for additional compensation on the basis of anything occurring prior to that date (findings 62-64). If this were regarded as a release it could be considered as waived by subsequent conduct of the Government in the release of November 20,1956, which by permitting the noting of extensive exceptions impliedly waived the finality of the July 6 concession by plaintiff. See Winn-Senter Constr. Co. v. United States, 110 Ct. Cl. 34, 65-66, 75 F. Supp. 255, 260 (1948).

On November 20, 1956, the plaintiff, in consideration of the payment of $213,562.60 ($212,319 of which represented [611]*61110 percent withholdings from progress payments through August 1954 pursuant to Article 16 of the contract), signed an official release form in which he—

* * * remises, releases, and forever discharges the United States of and from all manner of debts, dues, sum or sums of money, accounts, claims, and demands whatsoever, in law or in equity, under or by virtue of the said contract, except contract items and quantities as listed on the reverse side hereof.

The reverse side of the release summarized 13 exceptions totaling $198,633.20, consisting almost entirely of disagreements on specific quantities of excavation and fill identified to specific item numbers in the contract specifications.

It is noteworthy that none of the claims constituting the present action were excepted from the foregoing release. No matter how meritorious may be the claims not excepted by a contractor from the operation of a full, valid release under a Government contract (and we might well feel that certain of plaintiff’s non-excepted claims made here were of intrinsic merit had they been kept alive), they may not be judicially entertained later unless the release be found invalid or waived by subsequent conduct of the Government, both of which grounds plaintiff advances. See J. G. Watts Constr. Co. v. United States, 161 Ct. Cl. 801 (1963). The claim of invalidity of the release is based on alleged economic duress, and on the further ground that since the release was signed pursuant to Article 16 of what the plaintiff considers to be a contract void ab initio, the release itself is ineffectual. Neither argument convinces.

Irrespective of plaintiff’s dire financial predicament (findings 61 and 80), no conceivable economic coercion could invalidate a release where, as here, there is no evidence that plaintiff was restricted in the scope of his exceptions to the release. Cf. Harvey-Whiffle, Inc., v. United States, 169 Ct. Cl. 689, 697-99, 342 F. 2d 48, 53 (1965). For all the record shows the 13 exceptions listed by plaintiff in the November 20, 1956 release which he signed were of his own free choice and represented all of the claims he then considered due him from the Government, even though he may have previously announced his intention to make an extensive claim for his [612]*612damages due to changed conditions and related delays (finding 61). The time to have reserved such claims was upon the execution of the release, and we cannot passively assume that their reservation in the release would have caused [the Government to deny him the final payment of withheld percentages. Plaintiff’s contentions now urged that he lacked sufficient information at the [time of the release to frame proper exceptions to reserve his present claims, and that he obtained the necessary data only in the course of discovery proceedings in this action, do not excuse his failure to state his exceptions covering his present claims in general terms which would have sufficed the purpose of preserving his right to pursue them. See Ft. Sill Associates, asbca No. 7482, 1963 bca ¶ 3869.

Nor does it appear that any conduct of the Government subsequent to the release constituted a waiver thereof. On August 23, 1957, the Bureau of -Reclamation wrote plaintiff to inquire when he would supply additional data with respect to the items excepted from the release, advising that findings of fact would be issued within 60 days on the basis of available information concerning the excepted claims unless plaintiff filed additional data in the meantime (finding 70).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garrett v. United States
15 Cl. Ct. 204 (Court of Claims, 1988)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Westinghouse Electric Corp. v. Garrett Corp.
437 F. Supp. 1301 (D. Maryland, 1977)
Robert E. McKee, Inc. v. City of Atlanta
431 F. Supp. 1198 (N.D. Georgia, 1977)
Johnson, Drake & Piper, Inc. v. United States
531 F.2d 1037 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
423 F.2d 1362, 191 Ct. Cl. 607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adler-construction-co-v-united-states-cc-1970.