Petrochem Services, Inc. v. The United States

837 F.2d 1076, 34 Cont. Cas. Fed. 75,427, 56 U.S.L.W. 2512, 1988 U.S. App. LEXIS 683
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 26, 1988
Docket87-1382
StatusPublished
Cited by30 cases

This text of 837 F.2d 1076 (Petrochem Services, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Petrochem Services, Inc. v. The United States, 837 F.2d 1076, 34 Cont. Cas. Fed. 75,427, 56 U.S.L.W. 2512, 1988 U.S. App. LEXIS 683 (Fed. Cir. 1988).

Opinion

NICHOLS, Senior Circuit Judge.

Petrochem Services, Inc. appeals the decision of the Armed Services Board of Contract Appeals [ASBCA or board], ASBCA No. 33105, 87-1 BCA (CCH) 1119,597 (1987), holding that the government discharged its duty to disclose superior knowledge through oral representations made to appellant at the time of on-site inspection. We vacate the ASBCA’s judgment denying Petrochem’s appeal and remand.

Issues

The issues raised by the parties are twofold. First, was the government’s duty to disclose superior knowledge legally discharged by the government’s oral representations to Petrochem? Second, was the ASBCA’s decision arbitrary, capricious, so grossly erroneous as to imply bad faith, or not supported by substantial evidence so as to require reversal and remand?

Background

On January 29, 1982, oil spilled from a storage tank being filled at the Great Lakes, Illinois Naval Base. The tank:

is a part of the facility’s steam generation capability and provides back-up fuel * * *. The tank is constructed of steel and is approximately 60 to 70 feet in diameter, 40 feet high and contains perhaps as much as a half million gallons of fuel oil. The tank sits in the middle of a rectangular containment area approximately 80 X 100 feet in size. The floor *1078 of the containment area is covered with about a one foot thickness of pea gravel. The containment area is * * * sized to contain all of the oil which might be in the storage tank at any given time in the event of a catastrophic rupture.

(Appellant’s App. at 3.)

The Navy determined that the oil had to be removed and that bids should be taken from contractors to perform the operation. In order to assist those contractors interested in bidding, Mr. Gary Smith, Supervisor of Steam Production at the Navy’s Public Works Center, drafted technical specifications for the cleanup. The government’s engineering department ascertained that 21,076 gallons had spilled, but Mr. Smith did not mention this figure in the technical specifications.

The contract, No. N62472-82-C-6147, was awarded to Petrochem on May 18, 1982. Prior to the contract award, Petro-chem sent a representative, Mr. Edward Vehrs, to the facility to gauge how much oil spilled and required removal. A visual inspection around the tank revealed water and oil floating in varying degrees upon the surface of the water. The pea gravel bottom of the tank was not visible to anyone simply looking at the tank.

At the on-site inspection, Mr. Vehrs estimated that roughly 6,000 gallons of oil had to be removed. The level of water within the concrete barrier and the weather conditions in March prevented anyone from seeing exactly how much oil had spilled. Mr. Smith testified, however, that in a brief exchange, he said to Mr. Vehrs that the actual amount spilled was closer to 21,000 gallons. The government well knew this by the amount that had disappeared from its inventory. It was not found, and is not clear, that the statement was made in such a way that Vehrs knew or could be charged with knowledge that it was an official, definitive disclosure of superior knowledge rather than an off-hand (or even considered) estimate by a government employee who, for all Vehrs knew, may have been no better qualified to estimate than Vehrs. It is not clear how well Smith communicated. Vehrs either did not hear it, heard it but thought Smith was guessing, or heard it but did not understand. Regardless of the disparity in numbers, neither party subsequently communicated with the other in writing to verify the exact amount of oil in question. At trial, Mr. Vehrs was unavailable to testify regarding his conversation with Mr. Smith and the board relied on Mr. Smith’s testimony.

When Petrochem attempted to perform the contract, it discovered that its estimate was off by roughly 15,000 gallons; a material difference which would have been reflected in Petrochem’s bid, if it had known the correct amount of oil to be removed. The removal process occurred during June-August, 1982. The warmer weather caused the oil in the pea gravel to seep out and float up to the surface, something which did not occur on March 22, 1982, when Mr. Vehrs made his on-site inspection. Petrochem performed the contract, ultimately removing 21,401 gallons of oil from the tank.

After the cleanup, Petrochem submitted a claim to the contracting officer for an equitable adjustment in the amount of $27,-421.13, based on the government’s failure to disclose superior knowledge. The contracting officer denied Petrochem’s request and Petrochem filed an appeal with the ASBCA pursuant to 41 U.S.C. § 605(c)(5). On January 5, 1987, ASBCA upheld the contracting officer’s denial of an equitable adjustment. After reconsideration, the ASBCA affirmed the January 5, 1987, decision on May 14, 1987. This appeal ensued raising questions of failure to disclose material superior knowledge and changed conditions.

Opinion

I. Duty to Disclose Superior Knowledge

A veritable gold mine of circuit caselaw exists defining the government’s duty to disclose superior knowledge on contracts ’ when equitable adjustment claims under contract clauses or breach of contract claims are raised. In either type of claim, the doctrine of superior knowledge requires approximately the same elements *1079 to be satisfied. See, e.g., Petrofsky v. United States, 616 F.2d 494, 222 Ct.Cl. 450 (1980), cert. denied, 450 U.S. 968, 101 S.Ct. 1488, 67 L.Ed.2d 618 (1981) (breach of contract); Hardeman-Monier-Hutcherson v. United States, 458 F.2d 1364, 198 Ct.Cl. 472 (1972) (equitable adjustment); H.N. Bailey & Associates v. United States, 449 F.2d 376 (Ct.Cl.1971) (equitable adjustment); Wm. A. Smith Contracting Co. v. United States, 412 F.2d 1325, 188 Ct.Cl. 1062 (1969) (equitable adjustment); Helene Curtis Industries, Inc. v. United States, 312 F.2d 774, 160 Ct.Cl. 437 (1963) (breach of contract). The disclosure of superior knowledge doctrine applies in situations where:

(1) a contractor undertakes to perform without vital knowledge of a fact that affects performance costs or duration;
(2) the government was aware the contractor had no knowledge of and had no reason to obtain such information; (3) any contract specification supplied misled the contractor, or did not put it on notice to inquire; and (4) the government failed to provide the relevant information.

American Shipbuilding Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bannum, Inc. v. United States
80 Fed. Cl. 239 (Federal Claims, 2008)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Federal Group, Inc. v. United States
67 Fed. Cl. 87 (Federal Claims, 2005)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
Southern California Edison v. United States
58 Fed. Cl. 313 (Federal Claims, 2003)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
CTA Inc. v. United States
44 Fed. Cl. 684 (Federal Claims, 1999)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Morris v. United States
40 Cont. Cas. Fed. 76,832 (Federal Claims, 1995)
Howard v. United States
31 Fed. Cl. 297 (Federal Claims, 1994)
Bradley Construction Inc. v. United States
39 Cont. Cas. Fed. 76,629 (Federal Claims, 1994)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Gould, Inc. v. United States
39 Cont. Cas. Fed. 76,587 (Federal Claims, 1993)
Solar Turbines, Inc. v. United States
38 Cont. Cas. Fed. 76,409 (Court of Claims, 1992)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,240 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
837 F.2d 1076, 34 Cont. Cas. Fed. 75,427, 56 U.S.L.W. 2512, 1988 U.S. App. LEXIS 683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/petrochem-services-inc-v-the-united-states-cafc-1988.