Topkis Brothers Company v. The United States

297 F.2d 536, 155 Ct. Cl. 648, 1961 U.S. Ct. Cl. LEXIS 192
CourtUnited States Court of Claims
DecidedDecember 6, 1961
Docket391-57
StatusPublished
Cited by11 cases

This text of 297 F.2d 536 (Topkis Brothers Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Topkis Brothers Company v. The United States, 297 F.2d 536, 155 Ct. Cl. 648, 1961 U.S. Ct. Cl. LEXIS 192 (cc 1961).

Opinion

JONES, Chief Judge.

Plaintiff Topkis Brothers Company, a. clothing manufacturer, seeks reimbursement by way of an equitable adjustment, in the contract price for increased costs of production and loss of profit because-of defendant’s alleged failure to supply suitable Government-furnished property. Defendant counterclaims for savings allegedly realized by plaintiff in-the performance of its agreement.

On November 9, 1951, defendant’s. New York Quartermaster Procurement Agency issued an invitation for bids pursuant to which the Government sought to procure 3,802,980 field jackets,, sateen, OD-7. On the basis of its responsive bid to defendant’s invitation, plaintiff was awarded two contracts on December 21, 1951, numbered DA-30-280-QM-22839 and DA-30-280-QM-22848. The former contract called for delivery of 700,000 jackets at unit prices ranging from $0.545 to $0.599, for a. total contract price of $398,900, while the latter called for delivery of 300,000 jackets at unit prices of from $0.519 to $0.535, for a total contract price of' $157,300. Deliveries under both contracts were to be made in designated' monthly quantities, with performance- *537 under both to be completed by August of 1952.

Except for the unit prices and quantities involved, the terms and conditions of each contract were identical in all material respects. The jackets were to be manufactured by plaintiff in strict compliance with defendant’s specification MIL-J-3001A, which is fully set forth in finding 10. Defendant undertook to furnish plaintiff with the requisite cloth for the manufacture of the jackets, the government-furnished cloth being described in defendant’s invitation for bids as “Cloth, Cotton, Sateen, 8.5 oz., OD — 7.”

Although no specification concerning the manufacture of the sateen cloth was mentioned in the contracts, there was in existence at the time of the issuance of defendant’s invitation for bids a Government military specification controlling the manufacture of cotton, sateen cloth. This specification, which by its terms superseded MIL-C-10296, dated May 9, 1950, was MIL-C-10296A, dated May 10, 1951, covering “Cloth, Cotton, Sateen, Carded.” The pertinent provisions of each of the above specifications are fully set forth in finding ■8.

In connection with defendant’s undertaking to supply plaintiff with the necessary “Cloth, Cotton, Sateen, 8.5 oz., OD-7” for the manufacture of the field jackets, each of the contracts provided in pertinent part as follows:

“29. Government-Furnished Property. — (a) The Government shall deliver to the Contractor, for use in connection with and under the terms of this contract, the property which the schedule or the specifications state the Government will furnish (hereinafter referred to as “Government-Furnished property”). The delivery or performance dates for the supplies or services to be furnished by the Contractor under this contract are based upon the expectation that Government-Furnished property of a type suitable for use will be delivered to the Contractor at the times stated in the schedule or if not so stated in sufficient time to enable the Contractor to meet such delivery or performance dates. * * * The Government shall not be liable to the Contractor for damages or loss of profit by reason of any delay in delivery of or failure to deliver any or all of the Government-Furnished property, except that in case of such delay or failure upon the written request of the Contractor, an equitable adjustment shall be made in the delivery or performance dates, or price, or both, and in any other contractual provision affected thereby, in accordance with the procedures provided for in the clause of this contract entitled “Changes.”
* * * -x- * *
“2. Changes. — The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following: (i) drawings, designs, or specifications, where the supplies to be furnished are to be specially manufactured for the Government in accordance therewith; (ii) method of shipment or packing; and (iii) place of delivery. If any such change causes an increase or decrease in the cost of, or the time required for, performance of this contract, an equitable adjustment shall be made in the contract price or delivery schedule, or both, and the contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under *538 this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled ‘Disputes.’ However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.
******
“12. Disputes.- — Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the Secretary, and the decision of the Secretary or his duly authorized representative for the hearing of such appeals shall be final and conclusive: Provided, That if no such appeal is taken, the decision of the Contracting Officer shall be final. and conclusive. In connection with any appeal proceeding under this clause, the Contract- or shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the Contracting Officer’s decision.”

Plaintiff received its first shipment of the Government-furnished sateen cloth under these contracts on February 9, 1952. Upon commencing production in accord with the method specified in the invitation for bids, i. e., specification MIL-J-3001A, plaintiff immediately experienced sewing difficulties. Although there is no doubt that the cloth conformed to the applicable specifications controlling its manufacture, nonetheless its finish was so “hard” and lacking in flexibility that it resisted adjusting to the shape to be provided by the %3-ineh folders with which plaintiff’s machines were equipped. As a result, the cloth was not adequately folded together on the requisite double stitching operations, thereby causing raw edges of the cloth to remain exposed after such operations. Similarly, on both single and double stitching operations, the stiffness of the cloth resulted in cloth fracture, needle burning, thread breakage, and malformed stitching.

Plaintiff’s machinists endeavored to solve the problems thus encountered but without success, and plaintiff finally found it necessary to call upon the Singer Sewing Machine Company for advice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
Cubic Corp. v. United States
36 Cont. Cas. Fed. 75,972 (Court of Claims, 1990)
Fruehauf Corp. v. United States
587 F.2d 486 (Court of Claims, 1978)
Whittaker Corporation v. The United States
443 F.2d 1373 (Court of Claims, 1971)
Thompson Ramo Wooldridge Inc. v. The United States
361 F.2d 222 (Court of Claims, 1966)
Acme Process Equipment Co. v. United States
171 Ct. Cl. 324 (Court of Claims, 1965)
Acme Process Equipment Co. v. United States
347 F.2d 509 (First Circuit, 1965)
General Metals, Inc. v. Green Fuel Economizer Co.
213 F. Supp. 641 (D. Maryland, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
297 F.2d 536, 155 Ct. Cl. 648, 1961 U.S. Ct. Cl. LEXIS 192, Counsel Stack Legal Research, https://law.counselstack.com/opinion/topkis-brothers-company-v-the-united-states-cc-1961.