General Metals, Inc. v. Green Fuel Economizer Co.

213 F. Supp. 641, 1963 U.S. Dist. LEXIS 7746
CourtDistrict Court, D. Maryland
DecidedJanuary 28, 1963
DocketCiv. No. 11846
StatusPublished
Cited by4 cases

This text of 213 F. Supp. 641 (General Metals, Inc. v. Green Fuel Economizer Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
General Metals, Inc. v. Green Fuel Economizer Co., 213 F. Supp. 641, 1963 U.S. Dist. LEXIS 7746 (D. Md. 1963).

Opinion

THOMSEN, Chief Judge.

This is an action by a second-tier subcontractor, General Metals (plaintiff), against the first-tier subcontractor, Green Fuel (defendant), in which plaintiff claims that defendant unjustifiably terminated the contract between them, thus [643]*643entitling plaintiff to its costs incurred, which, amount to more than $200,000. Defendant has filed a counterclaim against plaintiff and a third-party claim against its surety, Seaboard, based upon the failure of plaintiff to complete the contract. Defendant claims that as a result of that failure the principal contractor, Blount Brothers Construction Co. (Blount), terminated defendant’s subcontract and defendant paid Blount $250,000 in settlement of Blount’s suit against defendant.

The parties have agreed that the question of liability should be tried first before the Court without a jury, and that the exact amount of any damages either side might be entitled to collect from the other shall be determined later.

The Contract

On December 15, 1955, the United States and Blount entered into a contract under which Blount undertook to furnish all labor and materials and perform all work required for the construction of a 36-inch variable pressure water tunnel, at the David W. Taylor Model Basin, Carderock, Maryland, in accordance with the specifications, schedules and drawings prepared by the Department of the Navy, which was designated as architect and engineer. On the same day Blount subcontracted to defendant that part of the general contract dealing with the resorber pit lining and tunnel shell, the latter term includes all the work covered by the subcontract between defendant and plaintiff. The original date for completion of the principal contract was March 1, 1957, but the time was extended by Blount. Defendant itself performed all the work connected with the resorber pit,1 2*but by the fall of 1956 had been unable to fabricate the tunnel shell through its own efforts or those of the second-tier subcontractors theretofore employed.

On September 24, 1956, defendant issued a purchase order to plaintiff for that part of the tunnel shell known as the contraction assembly. Plaintiff was not equipped to handle such heavy work; so, immediately after receiving the purchase order from defendant, plaintiff issued a purchase order for the contraction assembly to Truitt Manufacturing Company (Truitt), which thus became a third-tier subcontractor. The purchase orders required that the work be completed by December 30,1956.

In November 1956 defendant asked plaintiff to bid on the entire tunnel shell and supports, except the test section, which was being constructed by others.2 The contract which is the subject of the instant case was dated December 27, 1956, and was executed by both parties within a day or two thereafter.

The work which plaintiff undertook under that contract included the fabrication of: the contraction assembly, which carried the water into the test section, the previous purchase order being superseded by the contract; three diffuser section assemblies; three cylindrical section assemblies; four elbow assemblies, including numerous guide vanes (turning vanes) assembled in elliptical rings, the purpose of which was to eliminate or minimize the turbulence of the water flowing through the tunnel; eighteen flanges, to be welded onto various assemblies; and various minor items not material in this case.

Delivery under the contract of December 27, 1956, was to be made so that erection could start on March 5,1957, and be completed on June 1, 1957. The contract price was $233,500. The contract contained most of the provisions usually found in construction subcontracts, of [644]*644which those set out in the margin3 are material in this case.

The fabrication of the contraction section, which tapered in a reverse curve, [645]*645would have been very difficult at best; it was rendered nearly if not absolutely impossible by the close tolerance of two hundredths of an inch (.020") required for the inside surface.4 The fabrication of the elliptical rings, into which the turning vanes were welded, was rendered absolutely impossible by the unreasonable tolerance of .010".5 This tolerance was later relaxed by the Navy to .125", but too late to benefit either plaintiff or defendant.6

A rider attached to the contract of December 27, 1956, contained a list of “raw materials to be furnished by [defendant] to [plaintiff] for fabrication.”7 Plaintiff claims that its performance of the contract was delayed and prevented by the failure of defendant to deliver those materials promptly, and, more importantly) by the unsuitability of those materials for the work to be done.

Plaintiff also contends that Gordon, who negotiated the contract for defendant, falsely represented to plaintiff before the contract was executed, that the tolerances would be relaxed and that the materials to be supplied by defendant would be suitable for the work. Defendant objected to the testimony offered by plaintiff to that effect, as a violation of the parol evidence rule. The Court has admitted the testimony, not to vary the terms of the written contract, but as evidence in support of plaintiff’s contention that defendant’s counterclaim should be disallowed because the contract was obtained by false representations and concealment amounting to fraud.

Chronological Statement

Plaintiff did not intend to perform in its own shop any part of the work covered by the contract of December 27, 1956. On February 22,1957, it gave a purchase order to Truitt for all the work covered by that contract, including fabrication of the contraction assembly, which had been the subject of plaintiff’s September 1956 purchase order to Truitt. Delivery under the new purchase order was to be made in May 1957.

The material necessary for the contraction assembly had been ordered by plaintiff in November 1956 and was received by Truitt late in December 1956. A few days later Truitt started work on the contraction section. The other material required to perform plaintiff’s contract, except that to be furnished by defendant under the rider, was purchased by plaintiff as needed.

Immediately after the February 1957 purchase order to Truitt was issued, plaintiff notified defendant to ship to Truitt the material which defendant was obligated to supply under the rider. That material was delivered over a period of about a month. It included the carbon steel for the flanges, and the %" stainless steel plates from which the turning vanes were to be fabricated. Plaintiff’s claims that both items were unsuitable will be discussed separately below. Truitt began to work on the flanges early in April; shortly thereafter it began work on the turning vanes, in each instance using the material supplied by defendant. Neither Truitt nor plaintiff was delayed in the [646]*646performance of the work becáuse defendant did not deliver the materials sooner, but they were delayed because of the unsuitability of the material supplied by defendant for the flanges and for the turning vanes. Truitt found it impossible to fabricate the %" turning vanes from the %" steel plates, because the necessary machining reduced the thickness thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
213 F. Supp. 641, 1963 U.S. Dist. LEXIS 7746, Counsel Stack Legal Research, https://law.counselstack.com/opinion/general-metals-inc-v-green-fuel-economizer-co-mdd-1963.