Al Johnson Construction Co. v. United States

19 Cl. Ct. 732, 1990 U.S. Claims LEXIS 85, 1990 WL 35020
CourtUnited States Court of Claims
DecidedFebruary 21, 1990
DocketNo. 204-89C
StatusPublished
Cited by22 cases

This text of 19 Cl. Ct. 732 (Al Johnson Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al Johnson Construction Co. v. United States, 19 Cl. Ct. 732, 1990 U.S. Claims LEXIS 85, 1990 WL 35020 (cc 1990).

Opinion

OPINION

BRUGGINK, Judge.

This is a contract action brought pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-13 (1982) (“the Act”). Defendant has moved to dismiss the action under RUSCC 12(b)(1) (lack of jurisdiction). It contends that the attempted certification of plaintiff’s claim was ineffective. The issue is whether, in the circumstances of this case, certification of the claim by the Project Manager constitutes certification by “a senior company official in charge at the Contractor’s plant or location involved.” Defense Acquisition Regulation (“DAR”) 7-103.12(a), 32 C.F.R. § 7-103.12(a) (1982). After considering the parties’ written and oral arguments, the court concludes that the certification was inadequate, and that the action must be dismissed without prejudice.

BACKGROUND FACTS

Plaintiff is a joint venture consisting of A1 Johnson Construction Co. (“Johnson”) and Massman Construction Co. (the venture will be referred to as “Johnson Mass-man”). On September 30, 1982, Johnson Massman and the United States Corps of Engineers (“Corps”) entered into a contract. The contract was signed for the joint venture by the President of Massman Construction Co. and by the President of [733]*733the Construction Division of Johnson. By the terms of the contract, Johnson Mass-man was to construct Phase II of the Old River Control Auxiliary Structure (“OR-CAS”) on the Mississippi River in Louisiana. The total price was $135,264,995.00. The work required under the contract included the construction of a six-gated dam, channel excavation and construction of inflow and outflow channels to convey water to and from the auxiliary structure.

During construction, the parties apparently had disagreements concerning defendant’s contract responsibility to design suitable concrete mixes for use by plaintiff. In its complaint, Johnson Massman alleges that it incurred additional direct and indirect costs due to defendant’s poor handling of the design for the mix. On September 2,1986, Johnson Massman submitted a certified claim in the amount of $1,087,213.62. The claim was signed by Brian Kaub, the “Project Manager.” After extensive review, the Contracting Officer (“CO”) denied the claim on April 15, 1988. Suit was subsequently brought in this court.

DISCUSSION

The Act requires that, for claims in excess of $50,000.00, the contractor must certify that the claim is made in good faith, and, to the best of the contractor’s knowledge, is supported by accurate and complete data. 41 U.S.C. § 605(c)(1). The filing of a properly certified claim with the CO is a jurisdictional prerequisite to asserting a claim under the Act. Ball, Ball & Brosamer, Inc. v. United States, 878 F.2d 1426, 1428 (Fed.Cir.1989); Thoen v. United States, 765 F.2d 1110, 1116 (Fed.Cir.1985).

The disputes clause of the contract incorporates a regulatory provision found at DAR 7-103.12(a), 32 C.F.R. § 7-103.12(a).1 In relevant part, the regulation provides:

The certification shall be executed by the Contractor if an individual. When the Contractor is not an individual, the certification shall be executed by a senior company official in charge at the Contractor’s plant or location involved, or by an officer or general partner of the Contractor having overall responsibility for the conduct of the Contractor's affairs.

32 C.F.R. § 7-103.12(a) (emphasis added). Because Kaub is not an officer in either company, the parties agree that the relevant inquiry is whether he is a “senior company official in charge at the ... location involved.”

The parties have submitted affidavits and documents in support of their respective positions. Because the motion is brought pursuant to RUSCC 12(b)(1) and raises jurisdictional issues, the filing of materials outside the pleadings does not call for consideration of the motion as one for summary judgment. See RUSCC 12(b). While the unchallenged allegations of the complaint are taken as true for purposes of ruling on the motion, Sckeuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974), the court may inquire, by affidavits or otherwise, into facts necessary to support jurisdiction, and may resolve disputed facts. Western Transp. Co. v. Couzens Warehouse & Distributors, Inc., 695 F.2d 1033 (7th Cir.1982) (in determining whether it has subject matter jurisdiction, a court may review any available evidence); Eaton v. Dorchester Development, Inc., 692 F.2d 727 (11th Cir.1982) (court may, in resolving 12(b)(1) motion, make factual determinations); Williamson v. Tucker, 632 F.2d 579 (5th Cir.1980) (in resolving jurisdictional question, court may make factual findings); see Gibbs v. Buck, 307 U.S. 66, 71-72, 59 S.Ct. 725, 728-29, 83 L.Ed. 1111 (1939) (“[a]s there is no statutory direction for procedure upon an issue of jurisdiction, the mode of its determination is left to the trial court.”)

Defendant attaches to its motion a letter dated May 30, 1985, written by D.A. Johnson, President of Johnson’s Construction Division, to the Corps’ Resident Officer for the ORCAS project, authorizing Kaub to do certain things in connection with the per[734]*734forcnance of the contract. The authorization is quoted in full below:

As President of the Construction Division of A1 Johnson Construction Co., I hereby authorize and appoint Brian C. Kaub as Project Manager of the ORCAS project, to do and perform the following acts and things in connection with the performance of said Contract: to sign and execute (a) progress payment estimates, (b) vouchers, (c) change orders, if the increase or decrease in the Contract does not exceed Fifty Thousand Dollars ($50,000.00), (d) subcontracts, and (e) payroll transcripts and affidavits. Mr. Joseph E. McGowan will remain associated with the Project as Project Sponsor, and will also retain the above authorities.

Attached to the letter was a corporate resolution, dated May 30, 1985, which declared that the president or any vice president was authorized to issue a power of attorney appointing Kaub as “Attorney-in-Fact” for the corporation to perform the functions set out in the letter above. This appointment occurred toward the end of the contract period. Work had commenced on November 5, 1982, and the finished project was accepted on September 5, 1986. Prior to his appointment as Project Manager, Kaub had been Project Engineer.

Defendant also submits the affidavit of Donald Hull, Chief, Construction Division for the New Orleans District Corps.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greene v. United States
Federal Claims, 2023
Reid v. United States
Federal Claims, 2022
First Annapolis Bancorp, Inc. v. United States
72 Fed. Cl. 369 (Federal Claims, 2006)
Riviera Drilling & Exploration Co. v. United States
61 Fed. Cl. 395 (Federal Claims, 2004)
Hoskins v. United States
61 Fed. Cl. 209 (Federal Claims, 2004)
Lynn v. United States
58 Fed. Cl. 797 (Federal Claims, 2003)
Moyer v. United States
41 Fed. Cl. 324 (Federal Claims, 1998)
Kiewit/Tulsa-Houston v. United States
37 Cont. Cas. Fed. 76,255 (Court of Claims, 1992)
Choggiung Ltd. v. United States
37 Cont. Cas. Fed. 76,200 (Court of Claims, 1991)
Shirley Construction Corp. v. United States
37 Cont. Cas. Fed. 76,155 (Court of Claims, 1991)
Reliance Insurance v. United States
37 Cont. Cas. Fed. 76,090 (Court of Claims, 1991)
KDH Corp. v. United States
37 Cont. Cas. Fed. 76,087 (Court of Claims, 1991)
The United States v. Grumman Aerospace Corporation
927 F.2d 575 (Federal Circuit, 1991)
Manning Electric & Repair Co. v. United States
36 Cont. Cas. Fed. 75,993 (Court of Claims, 1991)
Cox Construction Co. v. United States
36 Cont. Cas. Fed. 75,919 (Court of Claims, 1990)
Triax Co. v. United States
36 Cont. Cas. Fed. 75,869 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
19 Cl. Ct. 732, 1990 U.S. Claims LEXIS 85, 1990 WL 35020, Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-johnson-construction-co-v-united-states-cc-1990.