H&M Associates, LLC. v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 31, 2023
Docket22-110
StatusPublished

This text of H&M Associates, LLC. v. United States (H&M Associates, LLC. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H&M Associates, LLC. v. United States, (uscfc 2023).

Opinion

IN THE UNITED STATES COURT OF FEDERAL CLAIMS ______________________________________ ) H&M ASSOCIATES, LLC, ) ) Plaintiff, ) No. 22-110C ) v. ) Filed: March 31, 2023 ) THE UNITED STATES, ) ) Defendant. ) ______________________________________ )

OPINION AND ORDER

Plaintiff H&M Associates, LLC filed this action against the United States alleging that the

United States Air Force (“USAF”) improperly terminated for default its contract to replace a

centrifugal Trane chiller at Joint Base San Antonio-Lackland. Before the Court is Defendant’s

Motion to Dismiss pursuant to Rule 12(b)(1) of the Rules of the United States Court of Federal

Claims (“RCFC”), for failure to establish subject-matter jurisdiction, and Rule 12(b)(6), for failure

to state a claim upon which relief may be granted.

For the reasons discussed below, the Court finds that it lacks subject-matter jurisdiction as

to any claim premised on a contractual modification or an equitable adjustment (whether raised

affirmatively or defensively) because no claim was submitted to the contracting officer for final

decision or certified in accordance with the Contract Disputes Act (“CDA”), 41 U.S.C. §§

7103(a)–(b). However, the challenge to the default termination falls within the Court’s

jurisdiction, and Plaintiff has at the pleadings stage sufficiently stated a claim upon which relief

may be granted. Accordingly, Defendant’s Motion to Dismiss is GRANTED in part and

DENIED in part. I. BACKGROUND

A. Factual Background 1

On August 13, 2020, the USAF issued a solicitation to replace a chiller at Joint Base San

Antonio-Lackland in San Antonio, Texas. Pl.’s Compl. ¶ 7, ECF No. 1. The project was 100%

set aside for Women Owned Small Businesses. Id. ¶ 8. The solicitation required “demolition and

replacement of the [c]entrifugal chiller, DDC EMCS, pumps, and of limited piping, hangers,

electrical circuits and components, appurtenances and incidental related work.” Id. ¶ 11. The

solicitation indicated that Defendant would provide the awardee with one set of contract drawings

and specifications and a virtual site visit. Id. ¶¶ 16–17.

On September 30, 2020, the USAF awarded a fixed price contract to Plaintiff. Id. ¶ 12.

“The contract required Plaintiff to deliver to Defendant all labor, equipment and materials to

demolish and replace a [c]entrifugal Trane [c]hiller along with various components and

appurtenances[.]” Id. ¶ 13. Additionally, the contract delivery schedule required “delivery of

design and submittal of long lead items on or before 100 days after receipt of the Notice to

Proceed” (“NTP”); “the installation of the replacement Trane [c]hiller on or before 120 days after

receipt of the NTP”; and “completion of all [c]lose out [a]ctivities on or before 30 days after receipt

of [the] NTP as set forth in FAR [Federal Acquisition Regulation] 52.211-10 ‘Commencement,

Prosecution, and Completion of Work.’” Id. ¶ 14.

1 The following background facts are compiled from Plaintiff’s Complaint and supplemented in part by materials in the appendix to Defendant’s Motion. See Pl.’s Compl., ECF No. 1; App. to Def.’s Mot. to Dismiss Pl.’s Compl., ECF No. 6-1. Each of those materials are referenced in or integral to the Complaint, and Plaintiff does not dispute their authenticity. Bell/Heery v. United States, 106 Fed. Cl. 300, 307–08 (2012), aff’d, 739 F.3d 1324 (Fed. Cir. 2014) (holding that a court may consider materials specifically referenced in the complaint or integral to it without converting a motion to dismiss into a motion for summary judgment). 2 On October 7, 2020, Plaintiff, a San-Antonio Trane representative, local installers,

electricians, and other service providers participated in a site visit. Id. ¶ 19. On October 9, 2020,

the USAF contracting officer (“CO”), issued a Partial NTP for the design and submittal activities

and set the 100-calendar-day period of performance as October 13, 2020, to January 20, 2021. Id.

¶¶ 9, 21–22, 26.

Soon thereafter, from October 18 to November 18, 2020, Plaintiff’s owner (and

representative), Ms. Maumita Mandal, traveled to India because her mother suffered a head injury

and later passed away. Id. ¶ 24. After Ms. Mandal’s return from India, Plaintiff called the contract

specialist and the CO several times between November 18 and December 1, 2020, but was unable

to reach them because their voicemail boxes were full. Id. ¶ 25; ECF No. 6-1 at 4, 42. Between

December 2, 2020, and January 7, 2021, Plaintiff submitted four requests for information (“RFI”):

RFI 1 sought information on certain technical requirements and the requested configuration for the

chiller; RFI 2 asked for make and model numbers for motors that needed replacement; RFI 3

sought confirmation on licensing; and RFI 4 followed up on questions in RFI 2 that were not

adequately answered. ECF No. 1 ¶ 31. During the same period, Plaintiff also sent “various emails

to Defendant asking . . . for responses” to its RFIs. Id. ¶ 32. On December 10, 2020, Plaintiff

submitted its first set of submittals (“Submittal 0001”) for the chiller and provided the variable

frequency drive (“VFD”), although Plaintiff had not received a response to RFI 1 yet. Id. ¶ 33.

On January 8, 2021, Plaintiff emailed the Government with its concerns about the lack of

responses to its four RFIs. Id. ¶ 34. In particular, the email stated that Plaintiff could not “place a

purchase order with . . . T[rane] unless the submittals are approved” by the Government. Id. ¶ 35.

It added that “the Scope of Work [did] not provide any specifications for the chiller equipment to

know what exactly the [G]overnment wants;” and thus, Plaintiff could not confidently place the

3 purchase order. Id. It further advised that the Trane representative, who also was copied on the

email, had notified Plaintiff that Trane prices would increase the following week; and therefore,

Plaintiff requested that the approvals for the chiller and VFD as well as responses to the four RFIs

be expedited. Id. The same day, the Government responded to RFIs 1, 2, and 3; however,

Plaintiff’s Submittal 0001 was not yet approved. Id. ¶ 36.

On January 11, 2021, the CO issued a cure notice to Plaintiff. Id. ¶ 37. Plaintiff responded

via email the same day, providing three dates to discuss the issues and pointing out that many

emails and calls from Plaintiff to the Government had “never received any responses.” Id. ¶¶ 39–

40. Plaintiff highlighted that prior emails from Plaintiff to the Government between January 6 and

January 8 raised concerns “that responses to RFIs and submittals [were] not being provided from

the [G]overnment, and that as a result[,] timely delivery of this project will be difficult.” Id. ¶ 39.

Plaintiff also complained that the contract did not offer product specifications for heavy ticket

items and that it was too risky for Plaintiff “to proceed with a half a million dollar purchase from

T[rane] for just one item – the [c]hiller” without first receiving approvals or responses to the RFIs.

Id. ¶ 41. That day and the following day, when Plaintiff reached out to local installers about the

project, they were already aware of the January 11, 2021, cure notice. Id. ¶ 42.

On January 13, 2021, a cure meeting was held. Id. ¶ 44. The next day, the Government

responded to RFI 4 and approved Submittal 0001. Id. ¶¶ 31, 51. On January 19, 2021, Plaintiff

requested an updated submittal list via email, noting that she was uncertain what submittals would

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Papasan v. Allain
478 U.S. 265 (Supreme Court, 1986)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Indium Corporation of America v. Semi-Alloys, Inc.
781 F.2d 879 (Federal Circuit, 1985)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Donald A. Henke v. United States
60 F.3d 795 (Federal Circuit, 1995)
Dcx, Inc. v. William J. Perry, Secretary of Defense
79 F.3d 132 (Federal Circuit, 1996)
Inter-Coastal Xpress, Inc. v. United States
296 F.3d 1357 (Federal Circuit, 2002)
Steel Co. v. Citizens for a Better Environment
523 U.S. 83 (Supreme Court, 1998)
Estes Express Lines v. United States
739 F.3d 689 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
H&M Associates, LLC. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hm-associates-llc-v-united-states-uscfc-2023.