Turnbull, Inc., Individually and Turnbull, Inc., and A. & H., Inc., Co-Venturers v. The United States

389 F.2d 1007, 180 Ct. Cl. 1010, 1967 U.S. Ct. Cl. LEXIS 108
CourtUnited States Court of Claims
DecidedJuly 20, 1967
Docket319-60
StatusPublished
Cited by22 cases

This text of 389 F.2d 1007 (Turnbull, Inc., Individually and Turnbull, Inc., and A. & H., Inc., Co-Venturers v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turnbull, Inc., Individually and Turnbull, Inc., and A. & H., Inc., Co-Venturers v. The United States, 389 F.2d 1007, 180 Ct. Cl. 1010, 1967 U.S. Ct. Cl. LEXIS 108 (cc 1967).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner Mastín G. White with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in a report and opinion filed on November 21, 1966. Exceptions to the commissioner’s findings and recommended conclusion of law were filed by plaintiffs, defendant urged adoption of the commissioner’s report, and the case has been submitted to the court on oral argument of counsel and briefs of the parties. Since the court is in agreement with the trial commissioner’s opinion and recommendation, with modifications, it hereby adopts the same, as modified, as the basis for its judgment in this case, as hereinafter set forth. Plaintiffs are, therefore, not entitled to recover and the petition is dismissed.

Commissioner White’s opinion, * as modified by the court, is as follows:

In this case, Turnbull, Inc., and A. & H. , Inc., two corporations that acted as co-venturers in the construction of buildings at the Longhorn Ordnance Works in Texas under a contract with the defendant, sue for $892,787.20 because it was necessary under an oral directive from personnel of the defendant to change the construction sequence provided for in the contract. 1 (For the sake of convenience, the two corporations, in their relationship as co-venturers, will usually be referred to hereafter in the opinion as “the prime contractor.” 2 )

The defendant has consistently conceded throughout the present action that the prime contractor is entitled to compensation for its extra costs growing out of the change in the construction sequence ordered by personnel of the defendant after the prime contractor had begun the performance of the contract at the Longhorn Ordnance Works. Hence, the controversy between the parties relates to the proper amount of such compensation.

The contract involved in the present case was entered into on May 26, 1954 between the prime contractor and a contracting officer of the Corps of Engineers, Department of the Army; it was numbered DA-34-066-eng-4150; and it provided for the payment of $2,480,-479.76 to the prime contractor for the furnishing of all labor, equipment, and materials (with exceptions not pertinent to this litigation) and the performance of the work involved in the construction of buildings at the Longhorn Ordnance Works, located in Harrison County, Texas. (This contract will usually be referred to hereafter in the opinion as “the contract.”)

*1009 The contract contained “Changes” and “Disputes” provisions similar to those customarily inserted in Government construction contracts administered by the Corps of Engineers.

A notice to proceed under the contract was given to the prime contractor by the defendant on June 11, 1954.

The original date for the completion of the contract was January 10, 1955. However, as a result of the issuance of 34 change orders by the contracting officer (not including the transaction that is involved in the present litigation), the time for the completion of the contract was extended to May 1, 1955. The change orders referred to in the preceding sentence required the performance of numerous items of work that were not required under the provisions of the original contract, and deleted some items of work that were required under the provisions of the original contract. These change orders provided for a total net increase of approximately $500,000 in the contract price.

Fairly soon after work was begun under the contract, a dispute arose between the prime contractor and personnel of the defendant with respect to whether, in connection with the erection of the buildings, the contract should be interpreted as providing that the walls and roofs would be constructed before the concrete floor slabs were placed, or as providing that the concrete floor slabs would be placed before the walls and roofs were constructed. The dispute grew out of a discrepancy between the drawings and the specifications that were attached to and formed part of the contract. The prime contractor argued that the first of the two interpretations previously mentioned was the correct one. This dispute was finally resolved by a representative of the contracting officer in favor of the “walls and roofs first” plan of construction for which the prime contractor had contended. The administrative decision was incorporated in a letter dated August 5, 1954 and addressed to the prime contractor.

Notwithstanding the administrative decision referred to in the preceding paragraph, a representative of the contracting officer on August 24, 1954 issued an oral directive to the prime contractor, requiring that the sequence of construction previously agreed upon be reversed and that the prime contractor adopt a plan of construction whereby the concrete floor slabs would be poured before the walls and roofs of the buildings were constructed. Thereafter, the prime contractor, under protest but with vigor, launched into and carried out a “floors first” method of construction. The work force was operated on a 2-shift, overtime basis to achieve progress.

Because of the disruption of the work sequence resulting from the oral directive of August 24, 1954, it was necessary for the prime contractor to reschedule the job and to take steps to have the prime contractor’s suppliers reschedule their operations. These circumstances changed the contract work from a smooth operation to one where it was necessary for the prime contractor to proceed on a makeshift basis and switch from one place to another, building as far as it could on one structure and then transferring the work force to another structure and a different type of work. Such factors, coupled with the geographical size of the project and the necessity of “hedgehopping” from area to area with no well-established plan of operation, increased the cost of the job.

More than nine months after the contracting officer’s representative required the prime contractor to reverse the construction sequence, the prime contractor on June 11, 1955 demanded that a change order be issued to compensate the prime contractor for losses allegedly resulting from the reversal in the construction sequence. The prime contractor asked for an adjustment upward of $474,243.89 in the contract price on the claim arising out of the change in the construction sequence and on another claim (which is not involved in the present litigation) based upon alleged delay by personnel of the defendant in approving certain shop drawings.

*1010 On September 15,1955, the contracting officer denied the June 1955 claims of the prime contractor in their entirety.

On October 5, 1955, the prime contractor appealed to the Chief of Engineers from the contracting officer’s action of September 15, 1955 in denying the claim based upon the change in the construction sequence. The prime contractor’s appeal was referred to the Corps of Engineers Claims and Appeals Board (as the representative of the Chief of Engineers) for determination. The subsequent proceedings before the board were assigned the number 938.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
State Highway Commission v. Brasel & Sims Construction Co.
688 P.2d 871 (Wyoming Supreme Court, 1984)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
St. James Hospital v. Harris
535 F. Supp. 751 (N.D. Illinois, 1981)
Jo-Bar Manufacturing Corp. v. United States
535 F.2d 62 (Court of Claims, 1976)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
Lockheed Aircraft Corp. v. United States
485 F.2d 584 (Court of Claims, 1973)
Air-A-Plane Corporation v. The United States
408 F.2d 1030 (Court of Claims, 1969)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Fort Sill Associates v. United States
183 Ct. Cl. 301 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
389 F.2d 1007, 180 Ct. Cl. 1010, 1967 U.S. Ct. Cl. LEXIS 108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turnbull-inc-individually-and-turnbull-inc-and-a-h-inc-cc-1967.