Kings Electronics Co., Inc. v. The United States

341 F.2d 632, 169 Ct. Cl. 433, 1965 U.S. Ct. Cl. LEXIS 59
CourtUnited States Court of Claims
DecidedFebruary 19, 1965
Docket487-56
StatusPublished
Cited by17 cases

This text of 341 F.2d 632 (Kings Electronics Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kings Electronics Co., Inc. v. The United States, 341 F.2d 632, 169 Ct. Cl. 433, 1965 U.S. Ct. Cl. LEXIS 59 (cc 1965).

Opinion

COLLINS, Judge.

This action is based upon a contract entered into by plaintiff, Kings Electronics Co., Inc., and the Department of the Navy’s Bureau of Ships for the manufacture of 28-foot and 35-foot aluminum whip antennas. Plaintiff seeks damages for an alleged breach of the contract or, in the alternative, seeks an equitable adjustment of the contract price.

*634 After receipt, in September 1950, of an invitation to bid, Morton Weissman, president of plaintiff, prepared the bid for his company. In determining the amount and type of material required for each antenna, he used the drawings which were part of the invitation. Weissman assumed that standard commercial aluminum tubing could be used. The bid of plaintiff was submitted on October 13, 1950.

On November 17, 1950, the contract (No. NObsr-52087) was awarded to plaintiff; delivery was to begin within 90 days. Plaintiff received notice of the award no later than December 1, 1950, and began to process the contract on December 20th. Samuel II. Jackson, plaintiff’s project engineer, requested from the Navy Bureau of Ships the latest revision of specification 44T30, the specification (for aluminum tubing) referred to in the drawings. In response, the Navy, in January 1951, sent specification MIL-T-855, which included the statement that it superseded specification 44T30b insofar as purchases for the Bureau of Ships were concerned. Jackson proceeded under the assumption that MIL-T-855 was applicable to the contract.

Shortly after the engineering work began, Jackson encountered difficulty with regard to the tolerances pertaining to the aluminum tubing. Jackson believed that it would not be feasible to meet the dimensional requirements of the drawings with tubing ordered in accord with the specification. In an effort to resolve this matter, plaintiff conferred with Aluminum Company of America, its supplier. In January and in March of 1951, Alcoa submitted proposals to plaintiff, but plaintiff did not consider them to be acceptable. Finally, on April 4, 1951, Jackson wrote the contracting officer of the difficulty. Jackson’s letter described the dimensions of the tubing available from Alcoa which came closest to meeting the requirements of the contract and requested approval of changes in the tolerances for the inside and outside diameters.

On April 5, 1951, prior to receiving the letter from Jackson, the contracting officer wrote plaintiff that, due to its failure to make deliveries as required, plaintiff was in default. Plaintiff was directed to cure the default within 10-days or to show why the contract should not be terminated. 1 As a result of this correspondence, a meeting was held on April 26, 1951, between representatives-of plaintiff and of the Navy. The contract was not terminated, and plaintiff’s proposal with regard to tolerances was accepted by the contracting officer.

On May 3, 1951, plaintiff submitted to-the contracting officer its first progress report. 2 After obtaining the agreement, of Alcoa to an August delivery schedule, plaintiff placed its order for the aluminum tubing. On May 31, Alcoa returned the order to plaintiff because new directives regarding the allotment of strategic materials had been issued. The original, allocation to plaintiff had been made on the basis of regulations which would cease to be effective after July 1951. Plaintiff’s efforts to obtain aluminum from other sources were unsuccessful; however, in July plaintiff received a priority under the new regulations. Alcoa sent plaintiff formal acknowledgment of the purchase order; delivery was to be in November 1951.

In August 1951, Alcoa had called to plaintiff’s attention the need to alter the-elongation test provisions contained in specification MIL-T-855. 3 At a meeting on September 26, 1951, this matter was- *635 resolved when the contracting officer -orally accepted the proposed alteration.

On October 29, 1951, the Navy wrote plaintiff that a change from specification MIL-T-855 to specification WW-T-789 was contemplated. At a conference on October 31, Weissman told the contracting officer that the contemplated change would require plaintiff to “start from .scratch.” At that time, Weissman requested that the contract be terminated without cost to either party. The contracting officer did not terminate the •contract, and plaintiff, at the urging of the contracting officer, continued its performance.

In November 1951, when the aluminum •began to arrive, plaintiff’s facilities were •entirely occupied. Plaintiff then elected to perform by subcontracting the manufacture of the antennas.

The contract was completed in July 1953. At the suggestion of the contracting officer, plaintiff filed a request for a •contract price increase pursuant to Title II of the First War Powers Act of 1941. 4 •Subsequently, this claim was withdrawn •and resubmitted in the form of a claim for an equitable adjustment under the “Changes” article. On February 3, 1956, the contracting officer denied plaintiff’s •claim. An appeal to the Armed Services 'Board of Contract Appeals resulted (on March 27, 1958) in a decision adverse to plaintiff. In the present action, plaintiff seeks to recover $149,608.94, which represents its losses of $144,108.32 5 plus $5,500.62, the 5 percent profit which, according to plaintiff, was included in its hid.

Plaintiff asserts that, under either the "breach of contract or the equitable adjustment theory, the measure of damages should be the total amount of plaintiff’s losses, plus the 5 percent profit included in the bid. Defendant denies any liability to plaintiff. This court finds neither party’s position to be totally convincing. Although not persuaded that plaintiff should recover the entire amount claimed, we are of the opinion that defendant is liable for some of plaintiff’s losses.

The Matter of Delays

Plaintiff’s argument is based, to a considerable extent, upon the assumption that defendant must bear the responsibility for the delays which occurred during the performance of the contract and for losses allegedly caused by the delays. Completion of the contract, although originally scheduled for May 1951, did not occur until July 1953. Undoubtedly, certain of plaintiff’s losses resulted from the protraction of performance of the contract. The initial issue, then, is whether or not the various delays are attributable to the Government.

First, consideration must be given to the lapse of time which occurred between December 1, 1950, the date by which plaintiff had received notice of award of the contract, and April 4, 1951, when plaintiff wrote defendant regarding the problem of “tolerances.” This initial period of delay is important, for, according to plaintiff, the time consumed in dealing with the matter of “tolerances” had a causal relation with the subsequent delays.

For purposes of the immediate discussion, it is assumed that the drawings and specifications of the contract did contain a conflict with regard to dimensional tolerances.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferguson Propeller, Inc. v. United States
59 Fed. Cl. 51 (Federal Claims, 2003)
Tyger Construction Co. v. United States
39 Cont. Cas. Fed. 76,627 (Federal Claims, 1994)
Calfon Construction Inc. v. United States
35 Cont. Cas. Fed. 75,738 (Court of Claims, 1989)
Balboa Insurance v. United States
31 Cont. Cas. Fed. 71,682 (Court of Claims, 1983)
Kaminer Construction Corp. v. United States
488 F.2d 980 (Court of Claims, 1973)
Emerson-Sack-Warner Corporation v. The United States
416 F.2d 1335 (Court of Claims, 1969)
J. A. Jones Construction Company v. The United States
395 F.2d 783 (Court of Claims, 1968)
Lockheed Aircraft Corporation v. The United States
375 F.2d 786 (Court of Claims, 1967)
WRB Corp. v. United States
177 Ct. Cl. 909 (Court of Claims, 1966)
Thompson Ramo Wooldridge Inc. v. The United States
361 F.2d 222 (Court of Claims, 1966)
Terminal Construction Corp. v. United States
171 Ct. Cl. 1 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
341 F.2d 632, 169 Ct. Cl. 433, 1965 U.S. Ct. Cl. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kings-electronics-co-inc-v-the-united-states-cc-1965.