Anderson Construction Company, Inc. And Montin-Benson Corporation, Joint Venturers v. United States

289 F.2d 809, 153 Ct. Cl. 475, 1961 U.S. Ct. Cl. LEXIS 90
CourtUnited States Court of Claims
DecidedMay 3, 1961
Docket257-58
StatusPublished
Cited by5 cases

This text of 289 F.2d 809 (Anderson Construction Company, Inc. And Montin-Benson Corporation, Joint Venturers v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson Construction Company, Inc. And Montin-Benson Corporation, Joint Venturers v. United States, 289 F.2d 809, 153 Ct. Cl. 475, 1961 U.S. Ct. Cl. LEXIS 90 (cc 1961).

Opinion

LARAMORE, Judge.

This is an action for an equitable adjustment of the contract price for alleged extra work required by defendant. This claim arises out of a contract entered into between plaintiffs and the United States through the Corps of Engineers, Department of the Army, for the construction of a large fieldhouse at Eielson Air Force Base near Fairbanks, Alaska. Plaintiffs seek reimbursement for the additional cost of the alleged extra work performed by them together with a reasonable allowance for overhead and profit.

This contract was entered into pursuant to appropriate regulations pertaining to the letting of Government contracts. On February 13, 1952, invitations for bids were issued. Attached to the invitation for bids at the time of issuance were (1) the specifications; (2) 52 drawings; and (3) Addendum No. 1, listing certain changes in the specifications. Relying on the information supplied in the invitation to bid, the plaintiffs, in the person of Mr. Anderson, prepared their bid. The opening paragraph of the specifications stated that “the site of the proposed work is at Eielson Air Force Base,approximately 26 miles from Fairbanks, Alaska, as shown on the Plot Plan.” However, the plot plan was not among the drawings furnished but was “to be furnished by addendum,” along with the grading plan. ■ •

*810 The 52 drawings which accompanied the specifications at the time of the issuance of the invitation for bids covered four features: architectural, structural, mechanical, and electrical. Four of the drawings depicting the basement plan showed the area underneath the floor slab as “unexcavated.” Four of the drawings depicting elevation showed the top of the finish ground floor as being at elevation 0.00. The “finish grade” below the floor slab was at elevation —1.19. The existing or present grade was at elevation -4.19. Tops of footings were at elevations -6.19; bottoms at -8.19.

Upon receipt of the drawings and specifications, about the middle of February 1952, Mr. Anderson made preliminary computations in contemplation of preparing a bid for the joint venturers. He interpreted the “unexcavated” legends to mean that the contractor would not be required to excavate under the floor slab areas, except for footings and utility trenches. He understood the “existing” or “present” grade at elevation -4.19 to indicate the necessity for fill to finish grade at —1.19. His computations for excavation were therefore limited to the requirements for footings and other subsurface elements.

Addendum No. 2 was issued on February 29, 1952. It contained the drawings pertaining to the plot plan and grading plan. The printed portion of Addendum No. 2 reached Mr. Anderson during the early days of March. The drawings were somehow delayed for a few days. When he received them, less than a week remained before the bid-opening date of March 12, 1952.

The grading plan traced the outline of the building in a field of contour elevations. The highest elevation in the vicinity of the building was 544 feet, while the lowest was 530 feet. Within the perimeter of the building’s outlines the highest elevation was 536 feet and the lowest 530 feet. The grading plan further showed the bottom of the floor slab as being at elevation 542.08, with the finish grade outside the perimeter beginning at elevation 541.88.

At the bottom of the grading plan a section of floor was depicted. This diagram showed the finish floor at elevation 543.27 feet, the finish grade beneath the floor at elevation 542.08, the finish grade outside at elevation 541.88, the “bottom of footing” at elevation 535.10, and the “excavation line” at elevation 526.0, which line was marked “Top of non-frost susceptible material.” Between the excavation line and the underside of the finish floor there had been traced the “existing ground line” showing its variants in elevation. The cross-section area between the excavation line and the underside of the finish floor was hatched. A note explained that the hatching denoted structural fill. It is this section of Addendum No. 2 that gives rise to the present controversy. The Government interpreted the provisions one way and the plaintiffs interpreted them another way. Hence, the issue of liability turns upon the reasonableness of the construction which plaintiffs, in the preparation of their bid, placed upon the contract specifications and drawings relating to excavation requirements.

Plaintiffs’ bid was mailed from Seattle by Mr. Anderson several days before the bid-opening date. The bid as prepared and mailed was in the amount of $2,250,-000. It was so submitted, however, with the intention of modifying it by telegram. This was done. Just before the bid-opening date, Mr. Anderson telegraphed a reduction of $273,000, making the final bid $1,977,000. The Government’s estimate of the cost of the contract work was in the amount of $2,600,927. Nine bids were submitted, all of which were lower than the Government’s estimate.

On July 3, 1952, plaintiffs wrote to defendant’s resident engineer, explaining that they were starting to excavate but that there appeared to- be a conflict in the requirements. On July 14, 1952, plaintiff actually began excavating. Cüi July 18, 1952, the defendant’s resident engineer advised plaintiffs that they were required to excavate the entire area within contract lines to the depth indicated as the excavation line on the section *811 showing on the grading plan. The plaintiffs proceeded with the excavation as directed. As a result, the cost of performance as required by the contracting officer was greater than the cost that would have been incurred in performance of the limited excavation contemplated by the plaintiffs. It is for the difference in cost of performance as required by the contracting officer and the cost of performance as anticipated by the plaintiffs that this action is brought.

There is no question whether the work involved in the present controversy was performed satisfactorily or not. Defendant makes no issue as to that. The only question is whether plaintiffs were required to perform the work under the terms of the contract or whether it was a determination by the contracting officer that additional work was required for which an equitable adjustment should be made.

When a contractor is requested to bid on a project, he must of necessity have adequate information from which to base an intelligent estimate. In this instance the information was supplied by the defendant. At the time request for bids were sent out the defendant sent along specifications, drawings, and changes. This was intended to inform prospective bidders what the project was about, what work would be required, and the necessary details from which a prospective bidder could submit an estimate. Significantly, the plot plan and the grading plan were not included with the other drawings at this time, but were to be furnished by addendum at a later date. A plot plan locates a given structure with respect to longitude and latitude. It shows where a given thing fits in with the surrounding area. A grading plan, on the other hand, raises and lowers an object according to elevation. Therefore, it is quite possible for an architect or engineer to design a structure in minute detail without regard for location or elevation. In the instant case, an arbitrary elevation of 0.00 was designated for the finish ground floor and other elevations were calculated in relation to this figure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
289 F.2d 809, 153 Ct. Cl. 475, 1961 U.S. Ct. Cl. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-construction-company-inc-and-montin-benson-corporation-joint-cc-1961.