Tufano Contracting Corporation and Anthony Grace & Sons, Inc., Joint Venture v. The United States

356 F.2d 535, 174 Ct. Cl. 398, 1966 U.S. Ct. Cl. LEXIS 159
CourtUnited States Court of Claims
DecidedFebruary 18, 1966
Docket53-61
StatusPublished
Cited by16 cases

This text of 356 F.2d 535 (Tufano Contracting Corporation and Anthony Grace & Sons, Inc., Joint Venture v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tufano Contracting Corporation and Anthony Grace & Sons, Inc., Joint Venture v. The United States, 356 F.2d 535, 174 Ct. Cl. 398, 1966 U.S. Ct. Cl. LEXIS 159 (cc 1966).

Opinion

COLLINS, Judge.

This action is based upon a contract entered into by plaintiffs, acting as a joint venture, and the Department of the Air Force. Plaintiffs agreed to build a 222-unit Capehart housing project at Suffolk County Air Force Base, Long Island, New York. 1 Although the Air Force had primary responsibility for the project, the Federal Housing Administration, which had insured the mortgages, also had some supervisory authority.

After construction had commenced, a dispute arose as to the necessity of installing certain “blocking.” 2 Government representatives insisted that the blocking in question was required by the contract; plaintiffs asserted the contrary. Ultimately, proceeding under protest, plaintiffs complied with the demands of the Government. The present suit is for recovery of the resulting expenses. 3

The facts can be summarized as follows: 4 The contract drawings and specifications were prepared for the Air Force by an architectural firm. The invitation for bids, issued in March 1958, had attached the contract form, including the drawings and specifications. The persons who prepared plaintiffs’ bid made a study of the various documents, but none of them read the plans or specifications as requiring the blocking now in dispute. Accordingly, they gave no consideration to the possibility of installing such blocking. Plaintiffs’ personnel did recognize that, in many respects, the contract called for construction which sur *537 passed the minimum standards of the FHA. 5

Plaintiffs’ bid was accepted, and the contract was executed in June 1958. Construction began on June 28,1958. It had been agreed that plaintiffs would first complete three houses which would serve as models and which would permit the identification and elimination of problems that might appear. Numerous representatives of the Government were present at the worksite on a regular basis; these included Col. Kenneth Ozment, the project officer; James J. Shields of the architectural firm; and approximately 30 inspectors, largely military personnel, who were present daily to inspect the work.

Throughout July 1958, plaintiffs made rapid progress. By the early part of August, the three model houses had been framed, were being covered with plywood sheathing, and were almost ready to receive wallboard and shingles. On August 12th, Mr. Shields called to the attention of plaintiffs’ superintendent the fact that the model houses did not have blocking between the rafters. Shields stated that such blocking was required and that installation of it after the sheathing had been applied would be more difficult. Plaintiffs’ superintendent replied that Shields had no authority to require such blocking.

On August 13, 1958, plaintiffs wrote defendant that they did not intend to install the disputed blocking. The Air Force contracting officer responded by quoting provisions of the specifications which, according to him, required the blocking for the attaching of (1) roof sheathing and (2) ceiling wallboard. 6 The position taken by the Government caused serious concern among plaintiffs’ employees and subcontractors. Thus, plaintiffs sought either to negotiate a compromise or to obtain reversal of the decision of the contracting officer. Plaintiffs’ efforts were unsuccessful.

On August 20, 1958, the contracting officer notified plaintiffs that he would not approve for payment any wallboard placed on ceilings without blocking. The prospect of a suspension of payments caused plaintiffs to begin installing the blocking. However, in a letter dated September 4, 1958, plaintiffs made clear that their compliance with the Government’s instruction was being done under protest. Also, plaintiffs requested the contracting officer to rescind his prior decision. This request was denied on October 13th, and plaintiffs were told that they could appeal to the head of the department. After denying the claim of plaintiffs, the contracting officer informed the FHA of the dispute. The FHA replied, on December 29, 1958, that the contracting officer’s interpretation of the specifications appeared to be “logical and reasonable.”

In November 1958, pursuant to the disputes clause of the contract, plaintiffs submitted a formal appeal to the Air Force. Subsequently, a hearing was conducted before the Armed Services Board of Contract Appeals. Having determined, in essence, that it lacked jurisdiction over the matter, the Board dismissed plaintiffs’ appeal. 7

*538 Work under the contract was completed by February 15, 1960. As indicated above, plaintiffs now seek to recover the extra costs resulting from installation of the disputed blocking.

It should be noted, at the outset, that there was no general practice, among builders in the Long Island area, of utilizing blocking of the type in question. That is, absent an express direction to do so, such blocking would not be used. Defendant’s contention that plaintiffs were directed to install the blocking rests solely upon the contract specifications, for it was not shown in the drawings. 8 Our primary task, therefore, is to interpret the specifications. 9 The basic issues are (1) whether the specifications did require plaintiffs to install the disputed blocking or (2) whether there was at least a sufficient indication of it so that plaintiffs were obligated, before bidding, to inquire as to the meaning of the specifications. 10 We conclude, for reasons to be explained, that both questions must be answered in the negative.

The arguments of defendant as to the ceilings and as to the roofs are based upon different contractual provisions. 11 With respect to the ceilings, defendant relies upon the following portion of section 13-15(C) of the specifications: “* * * All ends and edges of wallboard shall be placed only over structural members or where none exist, rigid blocking shall be installed. * * * ” According to defendant, this is a clear direction to use blocking of the type which plaintiffs ultimately installed.

The wallboard was in the form of sheets measuring 4 feet by 12 feet. The term “end” refers to the short side; the term “edge,” to the long. Under defendant’s interpretation of section 13-15 (C), the entire length of each end or edge had to be attached either to a structural member (i. e., a joist) or to blocking (which ran between joists at right angles). The ends of the sheets of ceiling wallboard were nailed to joists (which were located at 2-foot intervals), but, unless blocking were installed, there would not be a continuous surface to which to nail the edges. Defendant asserts that the persons responsible for plaintiffs’ bid relied not upon the specification, but upon the recommendation of the manufacturer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United International Investigative Services v. United States
40 Cont. Cas. Fed. 76,767 (Federal Claims, 1995)
James A. Mann, Inc. v. United States
535 F.2d 51 (Court of Claims, 1976)
Kenneth Reed Construction Corp. v. United States
475 F.2d 583 (Court of Claims, 1973)
Chris Berg, Inc. v. United States
455 F.2d 1037 (Court of Claims, 1972)
J. W. Bateson Co. v. United States
450 F.2d 896 (Court of Claims, 1971)
Air-A-Plane Corporation v. The United States
408 F.2d 1030 (Court of Claims, 1969)
J. A. Jones Construction Company v. The United States
395 F.2d 783 (Court of Claims, 1968)
L. Rosenman Corporation v. The United States
390 F.2d 711 (Court of Claims, 1968)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Tufano Contracting Corp. v. United States
191 Ct. Cl. 814 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
356 F.2d 535, 174 Ct. Cl. 398, 1966 U.S. Ct. Cl. LEXIS 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tufano-contracting-corporation-and-anthony-grace-sons-inc-joint-cc-1966.