L. Rosenman Corporation v. The United States

390 F.2d 711, 182 Ct. Cl. 586, 1968 U.S. Ct. Cl. LEXIS 57
CourtUnited States Court of Claims
DecidedFebruary 16, 1968
Docket211-65
StatusPublished
Cited by44 cases

This text of 390 F.2d 711 (L. Rosenman Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. Rosenman Corporation v. The United States, 390 F.2d 711, 182 Ct. Cl. 586, 1968 U.S. Ct. Cl. LEXIS 57 (cc 1968).

Opinion

ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

DURFEE, Judge.

This action arises out of a Government contract between plaintiff, L. Ro-senman Corporation (hereafter referred to as “Rosenman”) and General Services Administration (hereafter referred as as “GSA”) for “Air Conditioning Phase II” of a Federal Office Building located at Vesey and Church Streets in New York City.

The controversy here involves the interpretation of the contract. Specifically, the dispute involves the contracting officer’s direction to furnish approximately 900 automatic steam radiator valves for those radiators located on the 8th through the 15th floors of the subject building. Plaintiff contends that the contract did not require installation of radiator valves on these floors and as a consequence, the contracting officer’s order to install such valves represents a change in the contract for which plaintiff is entitled to an equitable adjustment. The contracting officer denied plaintiff’s claim for an equitable adjustment.

Upon appeal, the General Services Administration Board of Contract Appeals (hereafter referred to as the “Board”) divided evenly on the question of liability. 1 Nevertheless, the members of the Board unanimously agreed that in cases of a tie the decision of the contracting officer should prevail. 2 Hence, plaintiff’s appeal was dismissed. We conclude, however, that plaintiff is entitled to an equitable adjustment for performance beyond that required by the contract.

The disagreement between plaintiff and defendant centers around the technical drawings (floor-plans) for the individual floors of the building. The floor plans for the first five floors show a broken line running from the thermostats to the radiators. The drawing for floor six contains a similar representation. The plans for floors 8 through 15 do not contain the broken line running from thermostats to radiators. It was understood by both parties that automatic radiator valves would be installed only where the radiator was to be connected to a thermostat. A radiator not so connected would not have any need for an automatic valve, but would be regulated solely by the existing automatic zone-controlled system. Since the *713 drawings for floors 8 through 15 did not indicate any connection between the thermostats and radiators whereas the drawings for the first five floors plus floor six 3 did so indicate, plaintiff reasonably assumed from the beginning that the contract did not intend valves for floors 8 through 15. Defendant, however, contends that the omission of the connecting lines does not negate the clear directions of the specifications 4 and the detail drawing 5 to install automatic radiator valves throughout the entire building including floors 8 through 15. The omission of the connecting lines, at best, argues defendant, creates a patent discrepancy with the contract specifications and detail drawings which gives rise to an affirmative duty upon plaintiff to seek clarification.

Defendant’s arguments must be answered in two parts to correspond to the two legal issues raised. The first issue is whether the contract was so clear as to make the omission of the broken lines a patent and glaring error. Since we answer this in the negative, the second issue must also be reached, viz., whether plaintiff’s interpretation of the contract was reasonable and justifiable.

Regarding the first issue, we agree with defendant that the burden is on a contractor to seek clarification in cases of patent discrepancy (See, Ring Constr. Corp. v. United States, 162 F. Supp. 190, 192, 142 Ct.Cl. 731, 734 (1958); Consolidated Engineering Co. for Use of Fulton Nat. Bank v. United States, 98 Ct.Cl. 256, 280 (1943), but such is not the case here.

What constitutes a patent and glaring omission cannot, of course, be defined generally but only on an ad hoc basis by looking to what a reasonable man would find to be patent and glaring. In this case, three members of the GSA Board of Contract Appeals did not think the valves were clearly required. (In fact, they thought the valves were clearly not required). Plaintiff’s temperature control sub-contractor, who had some expertise in the air-conditioning system of this specific building, 6 did not consider the valves to be clearly required by the contract. It, too, believed the valves were clearly not required from the very beginning when it first submitted its bid to plaintiff. 7 Nor do we think the contract specifications and detail draw *714 ings were so clear as to create a duty to seek clarification of the omission of the broken lines. Although the specifications and drawings may have been clear as a bell in the mind of defendant’s architect, it is not the subjective intent that is the legal determinant. National Movers Co., Inc. v. United States, Ct.Cl., 386 F.2d 999 p. 1001 decided November 9, 1967. Rather, it is the representations of the specifications and drawings themselves which represent defendant’s intent. And these were not so clear as to compel plaintiff to seek clarification, or as to make defendant’s interpretation binding upon plaintiff. See, Tufano Contracting Corp. and Anthony Grace & Sons, Inc., Joint Venture v. United States, 356 F.2d 535, 539, 174 Ct.Cl. 398, 405 (1966). “The Government, as the author [of the contract] has to shoulder the major task of seeing that within the zone of reasonableness the words of the agreement communicate the proper notions — as well as the main risk of a failure to carry that responsibility.” WPC Enterprises, Inc. v. United States, 323 F.2d 874, 877, 163 Ct.Cl. 1, 6 (1963). Here defendant did not meet its burden. If it had wanted automatic radiator valves on all 15 floors, it should have said so explicitly. Even the Government witness conceded that there was no way of telling from the floor plans that automatic valves were intended for the 8th through the 15th floors.

Since we find that defendant’s plans and specifications were not so clear as to make its intepretation binding on plaintiff, we must next proceed to the second issue, the formulation of which is based on the well-defined principle that “when the Government draws specifications which are fairly susceptible of a certain construction and the contractor actually and reasonably so construes them, justice and equity require that construction be adopted.” Peter Kiewit Sons’ Co., et al. v. United States, 109 Ct. Cl. 390, 418 (1947) cited with approval in WPC Enterprises, Inc. (supra); cf., Maxwell Dynamometer Co. et al. v. United States, Ct.Cl., 386 F.2d 855 p. 867, decided November 9, 1967.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaw v. United States
131 Fed. Cl. 181 (Federal Claims, 2017)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)
Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)
Jaynes v. United States
75 Fed. Cl. 218 (Federal Claims, 2007)
Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Wilner v. United States
28 Fed. Cl. 783 (Federal Circuit, 1993)
Bayou Land & Marine Contractors, Inc. v. United States
37 Cont. Cas. Fed. 76,153 (Court of Claims, 1991)
Cherry Hill Sand & Gravel Co. v. United States
33 Cont. Cas. Fed. 74,030 (Court of Claims, 1985)
Salem Engineering & Construction Corp. v. United States
31 Cont. Cas. Fed. 71,312 (Court of Claims, 1983)
Sofarelli Associates, Inc. v. United States
30 Cont. Cas. Fed. 70,530 (Court of Claims, 1982)
Newsom v. United States
676 F.2d 647 (Court of Claims, 1982)
Lykes Bros. Steamship Co. v. General Dynamics Corp.
512 F. Supp. 1266 (D. Massachusetts, 1981)
Fruehauf Corp. v. United States
587 F.2d 486 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
390 F.2d 711, 182 Ct. Cl. 586, 1968 U.S. Ct. Cl. LEXIS 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-rosenman-corporation-v-the-united-states-cc-1968.