D & L Construction Co. & Associates v. The United States

402 F.2d 990, 185 Ct. Cl. 736, 1968 U.S. Ct. Cl. LEXIS 164
CourtUnited States Court of Claims
DecidedNovember 15, 1968
Docket159-65
StatusPublished
Cited by17 cases

This text of 402 F.2d 990 (D & L Construction Co. & Associates v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & L Construction Co. & Associates v. The United States, 402 F.2d 990, 185 Ct. Cl. 736, 1968 U.S. Ct. Cl. LEXIS 164 (cc 1968).

Opinion

OPINION

PER CURIAM:

This ease was referred to Trial Commissioner Richard Arens with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a). The commissioner has done so in an opinion and report filed on February 28, 1968, wherein such facts as are necessary to the opinion are set forth. Defendant excepted to that portion of the commissioner’s report which states that plaintiff is entitled to recover on Claim 4, “Closing of Access Roads”, but took no exception to the remaining portions of the opinion covering Claims 1 through 8. No exceptions were filed by plaintiff and the ease has been submitted to the court on defendant’s brief and oral argument of counsel. Since the court agrees with the commissioner’s opinion, findings and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, plaintiff is not entitled to recover on Claims 2 and 3, and as to them the petition is dismissed; plaintiff is entitled to recover extra compensation under the changes provisions of the contract on Claim 1 and as to it proceedings are suspended so that the parties can return to the Armed Services Board of Contract Appeals for determination of the amount due (with plaintiff to advise the court at intervals of not more than 60 days beginning with the date of this opinion of the status of the case before the Board pursuant to General Order of April 1, 1968, implementing Rule 100); and, that plaintiff is entitled to recover in this court on Claim 4, with judgment thereon entered for plaintiff and the amount of recovery to be determined pursuant to Rule 47(c).

OPINION OF COMMISSIONER

ARENS, Commissioner: This case arises out of a contract entered into on June 23, 1959, by plaintiff, a joint venture, with the Department of the Army for the construction of a 251 unit Cape-hart Housing Project at White Sands Missile Range, New Mexico. In this court, plaintiff, relying exclusively upon the administrative record, challenges by way of an assignment of errors decisions by the Armed Services Board of Contract Appeals denying three appeals from adverse decisions by the contracting officer. 1

Upon the basis of a stipulation entered into by the parties, plaintiff also seeks in this court damages on a breach of contract theory due to alleged delays as a result of the closing of access roads to the project site.

Claim 1 — Foundations, Footings and Stem Walls 2

The project was divided into two areas, one designed for housing commissioned officers, and the other for non- *992 commissioned officers. This claim concerns only the latter area containing 215 units.

The houses were to be built on concrete slabs laid over flat, compacted earth pads. The structural drawings, entitled “Structural — Foundation Plan and Details,” disclosed that as a general rule the finished grade lines were to be a uniform 8" below floor level. Section 1, subparagraph 1-11 of the specifications required grading of “the surfaces within 5 feet of the building in a manner satisfactory to the Contracting Officer, to the contours shown on the drawings.” The grading and drainage drawings showed varying finished ground elevations by contour lines which intersected the actual sides of the buildings. 3

Plaintiff interpreted the contract documents as generally providing for construction of houses with a uniform 8" stem wall and a 1' 6" footing, and submitted its bid on this basis which would enable it to use a standard form for pouring stem walls and foundations. It was not until after plaintiff had completed the foundation on several houses that plaintiff was shown by defendant individual drawings for each house, which depicted detailed elevations of ground levels at various points around the perimeter of the house, and was required by defendant to tailor the stem walls and foundations of each individual house, to varying heights. This involved a more costly operation than plaintiff had contemplated and plaintiff asserted that it constituted a change for which extra compensation should be granted. Plaintiff’s project manager, Mr. Hazel-tine testified, in the words of the ASBCA, as follows:

Mr. Hazeltine stated that in estimating the contract requirements he used the plans and specifications and based the estimate for concrete on a uniform footing depth of 1' 6" below the finished grade and considered the finished grade to be a uniform 8" below the level of the floor. He did consider the contour lines on the Grading and Drainage plans and noted that they came to the perimeter of the houses but did not consider there was a conflict between the structural details, the Grading and Drainage plans and the specifications. He did not believe the contours were really intended to come to the perimeter of the buildings but only to the edge of the pads some five feet out, as this was the general practice and had been his past experience. The appellant did not intend to completely ignore the Drainage and Grading plans and the contours shown thereon, but intended to use a uniform 8" stem wall and wrap the flat pad into the contours five feet out from the building, *993 as this was the usual practice. Mr. Hazeltine stated that although he recognized there were instances where deeper footings would be required due to the contract requirement that the footings of a house would all be either in natural ground or fill, he still estimated the concrete requirement on the basis of a uniform footing.

Although there was conflict in the expert testimony as to whether contours are practicable in depicting finished grades, the ASBCA stated that it was especially impressed by the Government’s expert witness on contours, who explained and illustrated the use of contours in establishing finished grades and the simplicity of applying the typical drainage pattern to arrive at a comparatively accurate finished grade elevation at different points around the perimeter of a house. In denying plaintiff’s appeal, the ASBCA found that:

1. While there were admitted inconsistencies between the structural drawings and the grading and drainage plans and specifications, plaintiff knew of these inconsistencies at the time of bidding but chose to ignore them in view of its past experience; and that it was incumbent upon a bidder to seek clarification of an ambiguity before bidding;

2. When considered as a whole, the contract required the grading to contours around the perimeter of the houses and that this definitely precluded any possibility of uniform 8" stem wall or uniform footings;

3. Representation by contours was one of the acceptable methods of showing finished grades and the original drawings furnished by the Government were adequate for this purpose;

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chugach Federal Solutions, Inc
Armed Services Board of Contract Appeals, 2024
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Walter Dawgie Ski Corp. v. United States
39 Cont. Cas. Fed. 76,583 (Federal Claims, 1993)
United States v. Board of Educ. of City of Chicago
588 F. Supp. 132 (N.D. Illinois, 1984)
Dale Ingram, Inc. v. United States
475 F.2d 1177 (Court of Claims, 1973)
Rawleigh, Moses & Co. v. United States
475 F.2d 606 (Court of Claims, 1973)
Astro-Space Laboratories, Inc. v. United States
470 F.2d 1003 (Court of Claims, 1972)
Tri-Cor, Inc. v. United States
458 F.2d 112 (Court of Claims, 1972)
Liles Construction Co. v. United States
455 F.2d 527 (Court of Claims, 1972)
Cosmo Construction Co. v. United States
451 F.2d 602 (Court of Claims, 1971)
J. W. Bateson Co. v. United States
450 F.2d 896 (Court of Claims, 1971)
Singer-General Precision, Inc. v. The United States
427 F.2d 1187 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
402 F.2d 990, 185 Ct. Cl. 736, 1968 U.S. Ct. Cl. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-l-construction-co-associates-v-the-united-states-cc-1968.