Liles Construction Co. v. United States

455 F.2d 527, 197 Ct. Cl. 164, 1972 U.S. Ct. Cl. LEXIS 203
CourtUnited States Court of Claims
DecidedFebruary 18, 1972
DocketNo. 97-70
StatusPublished
Cited by16 cases

This text of 455 F.2d 527 (Liles Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liles Construction Co. v. United States, 455 F.2d 527, 197 Ct. Cl. 164, 1972 U.S. Ct. Cl. LEXIS 203 (cc 1972).

Opinion

Nichols, Judge,

delivered the opinion of the court:

Plaintiff was awarded a prime contract, after competitive bidding, to renovate and repair 800 units of Wherry housing at MacDill Air Force Base in Tampa, Florida. Numerous disputes arose under the contract and were administratively adjudicated on appeals by the Armed Services Board of Contract Appeals; of these, three disputes remain and are brought here for review of the Board decisions under the standards of the Wunderlich Act, 41 U.S.C. §§321, 322 (1970). Our jurisdiction rests on 28 U.S.C. § 1491 (1970). We deal with each remaining dispute in turn under headings I, II and III. The original Board appeal numbers were, respectively, 12785, 11919 and 12450, reported at 68-1 BCA ¶ 7067 and 68-2 BCA ¶ 7089.

[169]*169I

Part of the renovation work included cleaning, sanding, patching and painting interior drywall surfaces. Joe Payne and Son Painting Contractor (Payne) was selected and approved as subcontractor for this work and some other exterior work not the subject of this appeal. The paint originally specified was known by the Base engineers to be unsuitable for the surfaces involved and was never intended to be applied (a fact unknown to plaintiff or to Payne). Plaintiff, however, was informed that the paint was to be changed as soon as additional funds became available. The change was effected before work began. However, the respecified paint failed to bond and peeled and blistered, precipitating a complete stoppage of painting activity. Some three months later, an alternative two-paint system suggested by another paint manufacturer was adopted. This system consisted of a primer coat (Nalprep) and a finish coat (Nalplex) and new application specifications were issued for the system. However, this paint, too, created problems; but they appeared randomly. Some units were accepted upon first application; others exhibited latent discoloration and cracking. Wide ranges of viscosity were encountered within the same day upon application. All parties were diligently seeking solutions to the problems, particularly Payne.

These problems, and Payne’s efforts to solve them, substantially reduced Payne’s performance rate, measured in multi-unit buildings per week, and resulted in the Contracting Officer’s making a threat to remove Payne from the project. Five months after the adoption of the Nalplex system, he ordered Payne to be removed for having “deliberately deviated” from specifications and for being “irresponsible, in default.” Plaintiff complied, and another subcontractor finished the painting. The Board findings describe the painting difficulties in detail, unnecessary for us to repeat in view of our disposition of this dispute.

Plaintiff pressed the theory of an express change and sought an equitable adjustment before the ASBCA for the difference in cost to Liles of painting under the contract

[170]*170due to the replacement of Payne with another, substantially more expensive painter. The Board found no substantiation for the charge of Payne’s irresponsibility and that Payne’s deviation from the specifications was not deliberate. The deviation was due to defects in the paint of which Payne could have had no knowledge. The Board further said (ASBCA No. 12785, -68-1 BOA ¶7067, 32,674):

When the contracting officer ordered Liles to relieve Payne for cause, he did so on grounds of _ deliberate deviation from specifications and irresponsibility. He did not cite the Termination for Default clause as warranting the action or any other clause of the contract vesting him with that power. Nor was a termination effected in fact, since no part of the contract work, or appellant’s right to proceed with the contract work, was terminated.
‡ $ $ $ $
The Government contends that the [Materials and Workmanship] clause empowered the contracting officer to require the removal of a subcontractor deemed incompetent, careless, or otherwise objectionable. Appellant contends that the clause has no reference to subcontracting entities as distinguished from individual employees. For the reasons stated below, we find it unnecessary to decide the point.
The posture of appellant’s claim * * * is one of constructive change emanating from the premise that the contracting officer was empowered by the contract to order the removal of a subcontractor, but that he exercised it improperly in that Payne had not exceeded the maximum 350 square feet per gallon of Nalprep as specified. Thus, there is no material issue between appellant and the Government about the Government’s contractual right of removal. On the issue which was joined, rate of Nalprep application, appellant’s claim fails upon the proofs. There is no evidence to rebut the contracting officer’s determination that the actual spread rate of Nalprep was 626 square feet per gallon. A constructive change, on the grounds urged by appellant, has not been established.

Plaintiff urges that the change was express, not constructive, but we deem this a matter of semantics not decisive to the result. More to the point, and correctly we believe, plaintiff says the Board misapprehended the nature of the change [171]*171plaintiff relied on. It was not a matter of the spread rate or of defects in the paint, but of the defendant’s changing the subcontractor plaintiff had chosen.

Here we have a written notice to terminate Payne’s association with the project with no termination of the work which Payne was originally assigned to do. Plaintiff alleges, and defendant does not deny, that it has taken all necessary procedural steps to preserve its rights under the Disputes clause. The sole issue in this Claim I is whether or not the termination of the subcontractor, resulting in higher cost, is compensable under the Changes clause of the contract. The higher cost is simply the higher price that had to be paid another subcontractor to do the work Payne was not permitted to do. The Board found as a matter of fact that Payne was not irresponsible as a subcontractor or in its performance of the painting function. This concession plaintiff says is not vital to its entitlement under this head or even relevant. The Board, however, did not find either Liles or Payne entitled to recovery as a matter of law.

We 'believe plaintiff to be correct in its contention that it has consistently assumed the posture of seeking recovery for the change ordered by the contracting officer. Plaintiff cites its brief before the Board, opening statements before the Board, a colloquy before the Board and its brief in support of its request for reconsideration by the Board as supportive of its position. After referring to all of these cited sources, it is sufficient to set forth certain excerpts from the opening statements before the Board.

TRANSCRIPT p. 567.
MR. HAMILTON: May it please the Board, Appeal No. 12785 concerns the costs arising out of the termination directed by the contracting officer of Joe Payne and Son, as the painting subcontractor of the prime contractor. It is the position of the prime contractor that such termination was a change; that it required a change in the prosecution of the work; and that such change is compensable u/nder the terms of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swinerton Builders Northwest
Armed Services Board of Contract Appeals, 2017
ECCI-C Metag, JV
Armed Services Board of Contract Appeals, 2015
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
D.F.K. Enterprises, Inc. v. United States
45 Fed. Cl. 280 (Federal Claims, 1999)
Nematollahi v. United States
38 Fed. Cl. 224 (Federal Claims, 1997)
North Slope Technical Ltd. v. United States
34 Cont. Cas. Fed. 75,430 (Court of Claims, 1988)
BCM Corp. v. United States
31 Cont. Cas. Fed. 71,110 (Court of Claims, 1983)
Mason v. United States
615 F.2d 1343 (Court of Claims, 1980)
J.G. Lockard Construction Co.
566 F.2d 1191 (Court of Claims, 1977)
Sea-Land Service, Inc. v. United States
553 F.2d 651 (Court of Claims, 1977)
Arundel Corp. v. United States
515 F.2d 1116 (Court of Claims, 1975)
McKee v. United States
500 F.2d 525 (Court of Claims, 1974)
Roscoe-Ajax Construction Co. v. United States
499 F.2d 639 (Court of Claims, 1974)
Stop & Shop Companies, Inc. v. Gilbane Building Co.
304 N.E.2d 429 (Massachusetts Supreme Judicial Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
455 F.2d 527, 197 Ct. Cl. 164, 1972 U.S. Ct. Cl. LEXIS 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liles-construction-co-v-united-states-cc-1972.