Swinerton Builders Northwest

CourtArmed Services Board of Contract Appeals
DecidedApril 24, 2017
DocketASBCA No. 57329
StatusPublished

This text of Swinerton Builders Northwest (Swinerton Builders Northwest) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swinerton Builders Northwest, (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Swinerton Builders Northwest ) . ASBCA No. 57329 ) Under Contract No. NAF26-04-C-0025 )

APPEARANCES FOR THE APPELLANT: Durward E. Timmons, Esq. Milton L. Smith, Esq. Ryan J. Klein, Esq. Sherman & Howard L.L.C. Colorado Springs, CO

Arnold R. Hedeen, Esq. Hedeen & Caditz, PLLC Seattle, WA

APPEARANCES FOR THE ARMY LODGING FUND: Raymond M. Saunders, Esq. Army Chief Trial Attorney LTC Lawrence P. Gilbert, JA Robert T. Wu, Esq. MAJ John C. Dohn II, JA Erica S. Beardsley, Esq. Trial Attorneys 1

OPINION BY ADMINISTRATIVE JUDGE DICKINSON

This appeal arises from a contract awarded by CFSC 2 on behalf of respondent Army Lodging Fund (AL, ALF or Fund), a Nonappropriated Fund Instrumentality (NAFI), to Swinerton Builders Northwest (appellant or SBN) to build a 185-room

1 Mr. Wu and MAJ Dohn represented the Fund at the hearing and Ms. Beardsley represented the Fund at the time the briefs were filed. 2 The U.S. Army Family and Morale, Welfare and Recreation Command, known at all

times relevant to the matters before us as the U.S. Army Community and Family Support Center (CFSC), is a field operating activity of the U.S. Army and the organization responsible for contracting on behalf of the Army Lodging Fund (answer~~ 2, 3). lodging facility at Fort Lewis, Washington. 3 Only entitlement is before us for decision. 4

JURISDICTION

It is undisputed that CFSC has never issued a contracting officer's final decision addressing SBN's 2005 and 2008 Requests for Equitable Adjustment (REAs) or SBN' s 3 June 2010 certified claim. It is further undisputed that SBN appealed to the Board from a deemed denial on 18 August 2010.

Under the Disputes clause of the NAF contract at issue, the Board has jurisdiction over an appeal from the denial of a claim arising under the contract (finding 25). The contract's Disputes clause, however, does not contain a provision for an appeal from a deemed denial of a contractor's claim. Under certain circumstances we have taken jurisdiction in the absence of a final decision under a NAF contract.

It is well established that the purpose of the Disputes clause is to provide the parties with a rapid and inexpensive means of resolving disputes between the parties. Mite Corporation, ASBCA No. 18534, 73-2 BCA ,10,312.

Prior to the CDA's enactment and under contracts where the CDA does not apply, we have taken jurisdiction over disputes that have existed for lengthy periods without a final decision. See Mite Corp., supra; Atlantis Construction Corp., ASBCA No[s]. 44044, 44860, 96-1 BCA, 28,045. As the Board explained in Mite Corp., supra, at 48,687, failure or r~fusal by the CO to issue a final decision within a reasonable time constitutes a final decision [denying the appeal and] giving jurisdiction to the Board.

Charitable Bingo Associates, Inc., d/b/a Mr. Bingo, ASBCA No. 53249, 01-2 BCA, 31,478.

The situation before us is even more compelling than the one the Board addressed in Charitable Bingo. From the 3 June 2010 submission of SBN's claim to the September 2012 hearing, not only did CFSC not issue a contracting officer's final

3 Fort Lewis and McChord AFB were combined and became Joint Base Lewis-McChord as of 1 October 2010. http://www.military.com/base-guide/joint-base-lewis-mcchord. 4 The number of days of any delay are considered to be part of entitlement (tr. 119).

2 decision, but the contracting officer never formally acknowledged receipt of SBN's 6,800-page claim, nor did he ever meaningfully respond to the many pleas from SBN and its counsel in letters and phone calls seeking a response to the claim. We find CFSC's near-complete failure of response to SBN's claim in more than two years to constitute a refusal to issue a final decision which, if not deemed to be a denial of SBN' s claim, would effectively deprive SBN of its right of appeal under the contract's Disputes clause (see finding 25). We, therefore, hold that we have jurisdiction over this appeal from a deemed denial. 5

FINDINGS OF FACT

A. Background and Pre-Contract Matters

1. Appellant SBN is a corporation organized and existing under the laws of the State of Delaware and has its principal place of business in San Francisco, California. The company was originally started as a small construction business in 1888 and at the time they were awarded the contract which is the subject of this appeal they were performing over a billion dollars in construction business per year. (R4, tab 3 at 1964 6, tab 127 at 2873; tr. 1121-22, 45, 5/173)

2. Under a pre-existing indefinite-delivery, indefinite quantity (IDIQ) contract between CFSC and ORB 7, ORB was tasked with providing a 10% concept design for the F ~rt Lewis Lodge design-build project that included a site plan drawing, followed by ORB' s drafting of the Request for Proposals (RFPs), within which the 10% concept design and site plan drawing were incorporated. John Patterson, 8 ORB's Vice

5 Neither party alleges that our jurisdiction is based on the Contract Disputes Act (CDA). Since we have held that we have jurisdiction pursuant to the Disputes clause of the contract and the basis of our jurisdiction is not material to our consideration of the entitlement issues presented, we do not address the issue of CDA jurisdiction. 6 Page number references are to the consecutively-numbered pages unless specified

otherwise. 7 ORB was an architectural firm on contract to CFSC to prepare the RFP for the Lodge project and to be CFSC's on-site representative during contract performance (tr. 2/102-03, 120, 8/39-40, 42, 9/30-33, 10/12-13, 15-16). ORB, in tum, contracted with BCE Engineers (BCE) to review the mechanical design, starting with the 35% design review (tr. 21120, 123, 9/39-40, 46). 8 Mr. Patterson has 23 years of active military duty, reaching the rank ofChiefMSgt,

and had been a military project manager/designer) (tr. 10/6-11, 123-24). He is not a licensed professional engineer (tr. 10111-12), however, he has worked very closely with Fort Lewis since 1984 on "engineering and construction

3 President and military projects manager, was the individual responsible for drafting the RFP. (Tr. 10/14, 18, 27; see also R4, tabs 171, 1001 (SOW for AIE preparation of RFP)) Mr. Patterson specifically developed RFP Sections C-1 through C-5 and portions of Sections J and L, leaving other sections unchanged as "standard language" (tr. 10/19-28, 136-47, 168). He testified that he was particularly concerned with the "site layout plan, utility plan" (tr. 10/19).

1. Request for Proposals

3. On 20 October 2003, the Fund issued RFP No. NAF26-04-R-0004 for the design and construction of a four-story, 100,500 square foot, 185-room Army lodging facility (Lodge) at Fort Lewis, Washington (R4, tabs 2, 169 at 3122, 3353, tab 1012). The RFP included the following language:

No appropriated funds of the United States will become due or be paid to the Contractor or Concessionaire by reason of this contract. This contract is governed exclusively by the provisions of Army Regulation 215-4}91

(R4, tab 2 at 866) The RFP identified contracting officer (CO) Bartholomew, who was assigned to the CFSC, NAF Contracting Directorate (CFSD-NC), and stated that CFSC was located in Alexandria, Virginia. SBN's Montoya testified that he scheduled many meetings with CO Bartholomew, "but I never had meetings" (tr. 3/183). It is a matter of record that CO Bartholomew's office (as well as that of COR Dyer) was located in Alexandria, Virginia, and the project was under construction in Tacoma, Washington.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
C.B.C. Enterprises, Inc. v. United States
37 Cont. Cas. Fed. 76,171 (Court of Claims, 1991)
S.T.G. Construction Co. v. United States
157 Ct. Cl. 409 (Court of Claims, 1962)
Liles Construction Co. v. United States
455 F.2d 527 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Swinerton Builders Northwest, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swinerton-builders-northwest-asbca-2017.