ECCI-C Metag, JV

CourtArmed Services Board of Contract Appeals
DecidedOctober 22, 2015
DocketASBCA No. 59031
StatusPublished

This text of ECCI-C Metag, JV (ECCI-C Metag, JV) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ECCI-C Metag, JV, (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) ECCI-C Metag, JV ) ASBCA No. 59031 ) Under Contract No. W5J9JE-10-D-0007 )

APPEARANCES FOR THE APPELLANT: Edward T. DeLisle, Esq. Amy M. Kirby, Esq. Cohen Seglias Pallas Greenhall & Furman PC Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Daniel B. McConnell, Esq. Geoffrey A. Mueller, Esq. Edward J. McNaughton, Esq. Matthew Tilghman, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE DICKINSON ON CROSS-MOTIONS FOR SUMMARY JUDGMENT

This appeal arises under a task order for the design and construction of an Afghan National Police facility in Kunduz Province, Afghanistan. We have jurisdiction to adjudicate this appeal pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109. The Commander ofthe United States Central Command (USCENTCOM) 1, determined that a subcontractor for appellant, ECCI-C Metag, JV (ECCi or appellant), was actively supporting an insurgency. Through another agency, appellant received notification of this determination by the USCENTCOM Commander (CDRUSCENTCOM) 2 and, after providing a copy of the notification to the contracting officer (CO) for the U.S. Army Corps of Engineers, Afghanistan District North (Corps or the government), appellant asked the CO how to proceed. The CO directed appellant to terminate the subcontract or else its own contract would

1 Directorate for Joint Force Dev., Joint Chiefs of Staff, Joint Publ'n (JP) 1-02, Dep't of Def. Dictionary of Military and Assoc'd Terms, at A-179 (2010). 2 JP 1-02, at A-27. be terminated for default. Appellant terminated the subcontractor as directed and submitted a claim for $3,252,818.92 and 61 days of delay resulting from the directed termination which, appellant contends, was a compensable change to the contract. Appellant now moves for summary judgment on the basis that nothing in the contract authorizes the CO to direct the contractor to terminate a subcontract. The government cross-moves, arguing that appellant was contractually required to terminate the subcontract, at its own expense, because the subcontractor's alleged conduct, i.e., supporting an insurgency, violated provisions of the contract requiring contractor and subcontractor personnel to comply with laws and regulations. We deny both parties' motions.

STATEMENT OF FACTS CSOF) FOR PURPOSES OF THE MOTIONS

A. The Contract

1. On 8 March 2010, the Corps awarded Contract No. W5J9JE-10-D-0007 to appellant. The contract was a firm-fixed-price, multiple award task order contract (the MATOC) for "construction type work throughout Northern Afghanistan." (R4, tab 3)

2. The MATOC provided in full text the standard Disputes clause, FAR 52.233-1, DISPUTES (JUL 2002) (R4, tab 3 at 38-39). The MATOC also set forth in full text the standard Changes clause for fixed-price construction contracts, FAR 52.243-4, CHANGES (JUN 2007) (id. at 45-46); and a standard Default clause, FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (id. at 49-50), which states, as relevant:

(a) If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure [sic] its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed ....

(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this clause if--

( 1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include

2 (i) Acts of God or of the public enemy,

[(xi)] delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers; and

(2) The Contractor, within 10 days from the beginning of any delay (unless extended by the Contracting Officer), notifies the Contracting Officer in writing of the causes of the delay. The Contracting Officer shall ascertain the facts and the extent of delay. If, in the judgment of the Contracting Officer, the findings of fact warrant such action, the time for completing the work shall be extended....

(d) The rights and remedies of the government in this clause are in addition to any other rights and remedies provided by law or under this contract.

3. The MATOC incorporated by reference FAR 52.225-19, CONTRACTOR PERSONNEL IN A DESIGNATED OPERATIONAL AREA OR SUPPORTING A DIPLOMATIC OR CONSULAR MISSION OUTSIDE THE UNITED STATES (MAR 2008), which provides in pertinent part: (a) Definitions. As used in this clause-

Combatant commander means the commander of a unified or specified combatant command established in accordance with 10 U.S.C. 161.

Designated operational area means a geographic area designated by the combatant commander or subordinate joint force commander for the conduct or support of specified military operations.

3 (b) General. ( 1) This clause applies when Contractorl31personnel are required to perform outside the United States-

(i) In a designated operational area during-

(A) Contingency operations;

(B) Humanitarian or peacekeeping operations; or

(C) Other military operations ....

(d) Compliance with laws and regulations. The Contractor shall comply with, and shall ensure that its personnel in the designated operational area ... are familiar with and comply with, all applicable-

(1) United States, host country, and third country national laws;

(2) Treaties and international agreements;

(3) United States regulations, directives, instructions, policies, and procedures; and

3 During notice-and-comment for FAR section 25.301 and FAR clause 52.225-19, it was requested that the clause define the term "contractor." In response, the FAR Council stated that "the FAR only applies to contracts as defined in FAR Part 2, not to the entire broad range of partners, ventures, and other types of contractors that may be used by the foreign assistance community." Federal Acquisition Regulation; FAR Case 2005-011, Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or Consular Mission, 73 Fed. Reg. 10,943, 10,949 (Feb. 28, 2008) (to be codified at FAR 25.301, 52.225-19); but see FAR 1.104, Applicability ("The FAR applies to all acquisitions as defined in Part 2 of the FAR, except where expressly excluded.") (emphasis added).

4 (4) Force protection, security, health, or safety orders, directives, and instructions issued by the ... Combatant Commander; however, only the [CO] is authorized to modify the terms and conditions of the contract.

(h) Contractor personnel. The [CO] may direct the Contractor, at its own expense, to remove and replace any Contractor personnel who fail to comply with or violate applicable requirements of this contract. Such action may be taken at the Government's discretion without prejudice to its rigbts under any other provision of this contract, including termination for default or cause.

(p) Changes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Medlin Construction Group, Ltd. v. Harvey
449 F.3d 1195 (Federal Circuit, 2006)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)
M.C. & D. Capital Corporation v. The United States
948 F.2d 1251 (Federal Circuit, 1992)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Liles Construction Co. v. United States
455 F.2d 527 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
ECCI-C Metag, JV, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecci-c-metag-jv-asbca-2015.