M.C. & D. Capital Corporation v. The United States

948 F.2d 1251, 1991 WL 226832
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 22, 1992
Docket91-1182
StatusPublished
Cited by8 cases

This text of 948 F.2d 1251 (M.C. & D. Capital Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.C. & D. Capital Corporation v. The United States, 948 F.2d 1251, 1991 WL 226832 (Fed. Cir. 1992).

Opinion

FRIEDMAN, Senior Circuit Judge.

This is another of the all too frequently seen cases in which a government contractor attempts to cut corners by substituting cheaper and lower quality materials, methods and services for those specified in the contract, and as a result is unable to perform the contract in accordance with its terms. In this case, the government terminated its contract with the appellant M.C. & D. Capital Corp. (MC & D) for default because of the contractor’s failure to comply with the contractual terms, and retained $100,000 of the contractual price to cover the defaults.

The Armed Services Board of Contract Appeals (Board) upheld those actions, and also sustained the government’s denial of the contractor’s claim for an award for its value engineering change proposal it allegedly submitted to the government and the government allegedly accepted. M. C. & D. Capital Corp., ASBCA Nos. 38181, 38300, 38301, 38483, 91-1 B.C.A. (CCH) If 23,563. We affirm.

I

A. The following facts, as found by the Board and as shown by the record, are not in dispute.

*1253 In 1985, MC & D and the Army Corps of Engineers entered into a contract for the installation of a so-called rubber “membrane” roof and underlying rigid insulation on the roofs of four buildings containing sophisticated and sensitive electronic defense equipment. MC & D was to provide the government with a completed “membrane roofing system,” comprising rubber sheets, bonding adhesives, sealants and other components that join the sheets together and to the underlying insulation and roof structure.

Two provisions of the contract are particularly important for purposes of this appeal. Paragraph seven provided:

Installation shall be in accordance with the manufacturer’s approved instructions for applicable system, except as otherwise specified. Installer shall be a certified installer by membrane manufacturer for membrane system used for a period of not less than five years.

Paragraph nine provided:

Contractor shall provide membrane manufacturer’s standard 10-year warranty upon final acceptance.

In its proposal that the government accepted, MC & D undertook to install a membrane system provided by International EPDM Rubber Roofing Systems, Inc. (IRS), a fabricator and installer of such systems. The membrane system would use rubber sheets manufactured by Colonial Rubber Works, Inc. (Colonial), IRS brand adhesives, and an IRS “bonded-plate” attachment system. The contractually-required warranty for the system would be provided by Colonial to IRS and by IRS to MC & D. The government approved this proposal.

At approximately the same time, MC & D hired Ken Register, a commission salesman of roofing materials, and requested that he propose a membrane system. Register had no affiliation with either IRS or Colonial and was not a manufacturer of rubber membrane systems.

At a subsequent meeting, MC & D introduced Register to the government as a “manufacturer’s representative,” who was affiliated with Colonial and with Weather Maintenance Services, Inc. (Weather). Weather was not a manufacturer of rubber sheets or membrane systems.

When Register attempted to arrange a sale from Colonial to Weather of Colonial’s rubber membrane, however, Colonial refused to supply it because neither Register nor Weather could establish that Weather met Colonial’s financial and technical requirements for membrane system manufacturers. Colonial informed Register that Colonial’s warranty was not transferable, and that Colonial’s policy was to sell and warrant only to full membrane system manufacturers. MC & D knew that neither Register nor Weather could meet Colonial’s criteria for a membrane system manufacturer.

In July 1985, MC & D began installing the membrane roofing system containing the components Register recommended. MC & D purchased rubber membrane from IRS, which in turn purchased it from Colonial. Register then informed IRS that Weather had taken over the job as membrane system manufacturer, that Weather had underpriced IRS and would warrant the job, and that MC & D would cancel its order for rubber membrane unless IRS agreed to a lower price. IRS reduced its price, but informed MC & D that because it was supplying only the rubber sheets and not the IRS complete membrane system, neither IRS nor Colonial would issue any warranty for the job.

As the work progressed, Register informed the government that he was the “manufacturer’s representative for Colonial working in conjunction with” IRS. The membrane system that MC & D installed was unique. It included components purchased by MC & D from various manufacturers and suppliers, contrary to the requirement of paragraph two of the contract that certain components come from a single supplier, and it had not been in use for at least five years, as the contract required.

Early in 1986, the government learned that Register did not represent either Colonial or IRS and that neither company would *1254 warrant the system being installed. The government then instructed MC & D to stop work pending proof that a “membrane manufacturer’s standard 10-year warranty will be given at the time of final acceptance.” MC & D responded by forwarding a letter from Register containing sample warranties of Colonial, IRS, and a company Register had formed, and by assuring the government that the contracted-for warranty would be issued to Weather and that Weather would provide a complete system warranty. MC & D was allowed to proceed.

In August 1986, after MC & D stated that the work was completed, the government “took possession of the work” as substantially complete. Soon thereafter, problems arose. IRS informed MC & D and the government that it would guarantee only that it had delivered Colonial’s first-line rubber, and would not go beyond that because the membrane system was not installed with IRS-approved materials or methods. This guarantee differed from the sample IRS warranty MC & D had earlier provided to the government and from the contractual requirement.

The government then paid MC & D the balance of the contract amount except for $100,000, which it retained pending completion of certain parts of the work, resolution of a Davis-Bacon Act dispute, receipt of the ten-year system warranty, and final acceptance.

Attempts by the government to obtain the 10-year full-system warranty the contract required were unsuccessful. The government ultimately agreed to accept a different warranty, on condition that MC & D also provide a bond or insurance policy protecting the government against any failure in the roofing system for the 10-year-warranty period. MC & D failed to provide either the bond or insurance.

Early in 1987, serious defects in construction appeared, involving numerous breaches of the roofs’ water-tight barriers due to peeling patches, as well as other defects in workmanship. By the summer of 1988, the Government still had not received a standard, ten-year system warranty from MC & D. There were numerous uncorrected deficiencies in materials and workmanship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Betance Enterprises, Inc.
Armed Services Board of Contract Appeals, 2023
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
ECCI-C Metag, JV
Armed Services Board of Contract Appeals, 2015
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Professional Services Supplier, Inc. v. United States
45 Fed. Cl. 808 (Federal Claims, 2000)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
948 F.2d 1251, 1991 WL 226832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mc-d-capital-corporation-v-the-united-states-cafc-1992.