Betance Enterprises, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 25, 2023
DocketASBCA No. 63076, 63077, 63078, 63079
StatusPublished

This text of Betance Enterprises, Inc. (Betance Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Betance Enterprises, Inc., (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Betance Enterprises, Inc. ) ASBCA Nos. 63076, 63077, 63078 ) 63079 ) Under Contract No. W9128F-16-D-0003 ) Task Order No. W9128F-18-F-0032 ) Task Order No. W9128F-18-F-0034 ) Task Order No. W9128F-18-F-0035 ) Task Order No. W9128F-17-F-0152 )

APPEARANCE FOR THE APPELLANT: Dennis C. Gardner, Esq. Ogletree, Deakins, Nash, Smoak & Stewart, P.C. Houston, TX

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Stacy K. Birkel, Esq. Engineer Trial Attorney U.S. Army Engineer District, Omaha

OPINION BY ADMINISTRATIVE JUDGE STINSON ON PARTIES’ CROSS MOTIONS FOR SUMMARY JUDGMENT

These appeals present the issue of which party, under task orders to repair or replace roofing systems, is responsible for the cost of repairing roofs damaged by hailstorms after the contractor began working on the roofs but prior to project completion and issuance of the requisite roof warranties, and prior to government acceptance of the work. Appellant Betance Enterprises, Inc. (BEI), appeals from four contracting officer’s final decisions dated August 19, 2021, denying BEI’s four claims in the amounts of $701,398.73, $380,993.57, $247,929.46, and $387,458.13, totaling $1,717,779.89, for additional costs incurred to make repairs to roofs damaged by two hailstorms in June and August 2018. We have jurisdiction pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§7101-7109. 1 The parties submitted cross-motions for summary judgment, responses, and reply briefs, for consideration in deciding these

1 On June 15, 2021, we dismissed appeals of four claims previously submitted by BEI under these task orders for failure to properly certify the claims. Betance Enters., Inc., ASBCA No. 62819 et al., 21-1 BCA ¶ 37,881 at 183,980 (Betance I). appeals. 2 Appellant also submitted two declarations with attached exhibits. For the reasons stated below, the Board grants the government’s motion for summary judgment and denies appellant’s cross-motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On June 26, 2015, the government issued Solicitation No. W9128F-15-R- 0016 for a firm-fixed-price Design-Build Single Award Task Order Contract (SATOC) for construction at Fort Carson, Colorado (R4, tab 1).

2. The solicitation included Federal Acquisition Regulation (FAR) 52.236-4, PHYSICAL DATA (APR 1984), which provides, in part, “(b) Weather conditions shall have been investigated by the Contractor to satisfy himself as to the hazards likely to arise therefrom. Complete weather records and reports may be obtained from the local U.S. Weather Bureau.” (R4, tab 1 at 0227)

3. Specification Section 01 35 26, GOVERNMENTAL SAFETY REQUIREMENTS, paragraph 1.13, “FACILITY OCCUPANCY CLOSURE,” stated that “[s]treets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer” (R4, tab 1 at 0313).

4. On July 10, 2015, BEI submitted a proposal in response to the solicitation (gov’t supp. R4, tab 1). Under Factor 1, Construction Experience, BEI stated:

Betance has been providing the highest level of design/build construction services concurrently throughout the CONUS including numerous projects in the Western United States, the Rocky Mountain community and specifically Fort Carson.

...

During the past two (2) years, Betance has successfully completed or is currently working on eight (8) projects

2 The government’s motion for summary judgment also included a motion to stay proceedings in these appeals, which appellant did not oppose in its response and cross-motion for summary judgment. Accordingly, the Board issued an Order dated September 15, 2022, staying proceedings in these appeals. 2 at Fort Carson Army Post, utilizing the resources and strategies of our proposed management approach.

WHY CHOOSE BETANCE

• Executed over $11.2M in similar services at Ft. Carson in the past 2 years • Proven DoD provider – in past 3 years, completed $40M in renovation projects

(Gov’t supp. R4, tab 1 at 1642) (emphasis in original).

5. The government awarded SATOC No. W9128F-16D-0003 to BEI on October 29, 2015, for construction at Fort Carson, Colorado, in the maximum amount of $49,000,000 (R4, tab 2 at 0393-94).

6. The contract incorporated by reference FAR 52.236-7, PERMITS AND RESPONSIBILITIES (NOV 1991) (R4, tab 2 at 0409), which provides, in part, the contractor shall “be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.” 48 C.F.R. § 52.236-7.

7. The contract incorporated by reference FAR 52.236-11, USE AND POSSESSION PRIOR TO COMPLETION (APR 1984) (R4, tab 2 at 0409), which provides: (a) The Government shall have the right to take possession of or use any completed or partially completed part of the work. Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use. However, failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government’s possession or use shall not be deemed an acceptance of any work under the contract.

(b) While the Government has such possession or use, the Contractor shall be relieved of the responsibility for the loss of or damage to the work resulting from the

3 Government’s possession or use, notwithstanding the terms of the clause in this contract entitled “Permits and Responsibilities.” If prior possession or use by the Government delays the progress of the work or causes additional expense to the Contractor, an equitable adjustment shall be made in the contract price or the time of completion, and the contract shall be modified in writing accordingly.

48 C.F.R. § 52.236-11.

8. In July 2017, the government issued Solicitation No. W9128F-16-D-0003 RFP 38, Wind Damage Repair Package VI, for roof repairs on Buildings 1160, 1231, 1390, 1680, 2390, 2429, 2605, 6215, 8021, 9249, 9418, R0518B, R0518D, and RG035B (R4, tab 5 at 0475, 0481-0482). In September 2017, the government issued: (1) Solicitation No. W9128F-16-D-0003 RFP 43 for roof replacement on Buildings 1352, 1551, and 1851 (R4, tab 16); (2) Solicitation No. W9128F-16-D-0003 RFP 41 for roof replacement on Buildings 1030 and 1200 (R4, tab 33); and (3) Solicitation No. W9128F-16-D-0003 RFP 42 for roof replacement on Buildings 1526 and 2161 (R4, tab 50). The solicitations for each of these four projects identified a mandatory performance period of 270 days, 270 days, 210 days, and 210 days, respectively, commencing from issuance of the Notice to Proceed (R4, tabs 5 at 0479, 0512 (RFP 38); 16 at 0696, 0732-33 (RFP 43); 33 at 0982, 1016 (RFP 41); 3 50 at 1222, 1258, 1260 (RFP 42)). The specifications for each solicitation contained nearly identical warranty requirements regarding roof replacement:

The phased installation of the new PVC roof system shall be installed by the contractor in such a manner as to maintain a watertight integrity with positive drainage on a daily basis and possess a Twenty (20) Year, 99 MPH wind, and 1 ½” diameter hail warranty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
John McShain, Inc. v. United States
375 F.2d 829 (Court of Claims, 1967)
Phillips Construction Co., Inc. v. The United States
394 F.2d 834 (Court of Claims, 1968)
Tombigbee Constructors v. The United States
420 F.2d 1037 (Court of Claims, 1970)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Sweats Fashions, Inc. v. Pannill Knitting Company, Inc.
833 F.2d 1560 (Federal Circuit, 1987)
M.C. & D. Capital Corporation v. The United States
948 F.2d 1251 (Federal Circuit, 1992)
Daniel A. Lindsay v. United States
295 F.3d 1252 (Federal Circuit, 2002)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
G & C Enterprises, Inc. v. United States
55 Fed. Cl. 424 (Federal Claims, 2003)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)
Liberian Poplar Transports, Inc. v. United States
26 Cl. Ct. 223 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Betance Enterprises, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/betance-enterprises-inc-asbca-2023.