G & C Enterprises, Inc. v. United States

55 Fed. Cl. 424, 2003 U.S. Claims LEXIS 37, 2003 WL 1135409
CourtUnited States Court of Federal Claims
DecidedMarch 6, 2003
DocketNo. 99-370C
StatusPublished
Cited by1 cases

This text of 55 Fed. Cl. 424 (G & C Enterprises, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G & C Enterprises, Inc. v. United States, 55 Fed. Cl. 424, 2003 U.S. Claims LEXIS 37, 2003 WL 1135409 (uscfc 2003).

Opinion

ORDER

MILLER, Judge.

This case brings into question, on defendant’s motion for summary judgment, whether the U.S. Army took beneficial occupancy of a project being constructed by plaintiff before a storm caused damage to the facilities. Failing a ruling that the risk of loss passed to the U.S. Army, the contractor faults the adequacy of contract specifications, alleging that they were not sufficient to withstand the elements. The court deems argument unnecessary.

FACTS

The following facts are undisputed, unless otherwise noted. On February 1, 1994, the U.S. Army awarded a firm fixed-price contract, No. DAHA28-94-C-0001 to G & C [425]*425Enterprises, Inc. (“plaintiff’). The contract incorporated by reference Federal Acquisition Regulation (FAR), 48 C.F.R. §§ 52.236-7 & 236-11 (2002), commonly known as the “Permits and Responsibilities” and the “Use and Possession Prior to Completion” clauses. The contract was for the construction of a project located at McGuire Air Force Base in New Jersey to fulfill a requirement for the New Jersey Air National Guard.

The contract required plaintiff to construct two facilities: a composite maintenance hangar and a fuel systems maintenance dock. The hangar is a 59,000 square-foot facility. Its purpose is to house military aircraft during maintenance. The hangar walls do not include pressure relief panels, which are designed to release from the steel support structures in the event of an internal fire or explosion, reducing the internal pressure on the structure and minimizing personal injury and damage to the facility. Instead, the wall panels in the hangar are fixed panels, which do not release from the structure upon impact. The fuel dock is a 19,500 square-foot facility intended to provide shelter for aircraft during fuel systems maintenance and was constructed with 13,400 square feet of pressure relief panels, which were attached to the steel structure by a wire tether designed to prevent a panel from becoming airborne when released from the structure.

Plaintiff began performing the contract in or about February 1994. On June 22, 1996, a severe storm with wind gusts exceeding 84 miles per hour, struck McGuire Air Force Base and significantly damaged the hangar and the fuel dock. Plaintiff was not insured against any damage resulting from the storm. LTC Edward R. Sain, Base Civil Engineer, initially evaluated the storm damages at approximately $1 million. The Army retained Foster Wheeler, an engineering consultant, to prepare a formal cost estimate for the repairs. He estimated a cost of $787,313.00 to repair the damage to the project caused by the storm.

Contracting Officer Capt. John W. Simms issued Modification P00013 on December 19, 1996. The modification was issued as a no-cost change order. The contract modification directed plaintiff to resume work on the contract, prepare a critical path method for the remaining work, repair damage caused by the storm, and complete all outstanding items which were not completed prior to the storm.

Plaintiff sought funding for the work required by the modification from its surety, American Insurance Company (“AIC”), which provided the funds to complete the repairs and rebuild the two damaged facilities.

Plaintiff alleges that it reached an informal agreement with AIC and the Army whereby, “in return for [AIC’s] providing financial assistance in the completion of the Project, the Army would support and sponsor and thereby recommend extraordinary contractual relief under [Public Law] No. 85-804, in order to secure the funds necessary to reimburse [plaintiff].” Compl. filed June 10, 1999, 1Í16.

Plaintiff filed a request for extraordinary contractual relief (“ECR”), pursuant to Public Law No. 85-804, 50 U.S.C. §§ 1431-1435 (2003), on or about January 28, 1997. The ECR request asked for an upward price adjustment of $903,284.00. This amount was based on Mr. Wheeler’s repair estimate, with added overhead of 21.14% for direct costs, a 10% profit, and 1% for the cost of bonding and insurance.

Plaintiff alleges that it proceeded with the work under protest after receiving financing from its surety, and that it completed the project reconstruction according to the original plans and specifications. The total cost to reconstruct the damaged facilities is claimed to be $1,026,316.94 over and above the original contract price.

A letter dated October 16, 1997, from the contracting officer, listed September 10, 1997, as the date of the Army’s acceptance of beneficial occupancy of the two facilities. Plaintiff contends that the projects were fit for their intended use prior to that date and, as a consequence, that the Army accepted the beneficial occupancy of the two projects prior to September 10,1997.

On or about April 17, 1998, plaintiff submitted to the contracting officer a claim for an equitable adjustment in accordance with the changes clause of the contract, and pur[426]*426suant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (2003) (the “CDA”). The adjustment requested was in the amount of $1,026,316.94. Plaintiff alleges that it has made several requests for a final decision from the contracting officer, but none was forthcoming as of June 10, 1999, the date on which the complaint was filed. Plaintiff deemed its claim denied, 41 U.S.C. § 605(c)(5), and filed this suit for equitable adjustment.

Plaintiffs complaint advances four claims. Count I claims $1,026,316.94, which represents the sum plaintiff requested in its ECR claim under the contract’s changes clause. Plaintiff alleges that the risk of loss for damage had shifted to the Army prior to the storm, because at that time the project was more than 99% complete and plaintiff had achieved substantial completion; the Army had begun to occupy the facilities; and the project was constructed in accordance with the specifications.

Count II of the complaint pleads that the Army made an “express[ed] and implied warranty that [the plan] specifications were sufficient so that a satisfactory Project would result from [plaintiffs] efforts.” Compl. ¶ 29. Alleging that the Army’s plans and specification for the hangar and fuel dock were insufficient, plaintiff seeks judgment in the amount of $1,026,316.94, which represents the amount it sought through the equitable adjustment request.

Count III alleges that the Army and plaintiff had reached an informal agreement to compensate plaintiff for the reconstruction of the project, including the processing of relief pursuant to Public Law No. 85-804. The Army’s refusal to compensate plaintiff therefore constitutes a breach of contract. Plaintiff claims that the fair and reasonable value of the work is approximately $1,300,000.00, and represents a portion of plaintiffs indebtedness to AIC.

Count IV pleads breach of contract resulting from the Army’s allegedly making a cardinal change to the contract. Plaintiff alleges that Modification P00013 altered the scope of the contract “far beyond that which was required from, and anticipated by, [plaintiff].” Compl. ¶ 39.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Betance Enterprises, Inc.
Armed Services Board of Contract Appeals, 2023

Cite This Page — Counsel Stack

Bluebook (online)
55 Fed. Cl. 424, 2003 U.S. Claims LEXIS 37, 2003 WL 1135409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-c-enterprises-inc-v-united-states-uscfc-2003.