Textron Defense Systems v. Sheila E. Widnall, Secretary of the Air Force

143 F.3d 1465
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 25, 1998
Docket96-1535
StatusPublished
Cited by75 cases

This text of 143 F.3d 1465 (Textron Defense Systems v. Sheila E. Widnall, Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Textron Defense Systems v. Sheila E. Widnall, Secretary of the Air Force, 143 F.3d 1465 (Fed. Cir. 1998).

Opinion

PLAGER, Circuit Judge.

This case involves a research and development contract funded by the Strategic Defense Initiative Office (“SDIO”) as part of the so-called ‘Star Wars’ anti-ballistic missile defense system. In a decision by the Armed Services Board of Contract Appeals (“the Board”) dated May 2, 1996, ASBCA Nos. 47352 and 47950, the Board denied Textron’s appeal for payment of additional costs and fees on a cost-plus-award-fee (“CPAF”) contract. Because Textron received all that it was entitled to under the language of the contract, we affirm.

BACKGROUND

The United States Air Force (hereinafter “Government”) awarded the CPAF contract to Textron’s predecessor in interest, AVCO Everett Research Laboratory, Inc., on November 8, 1984, with an effective date of September 18, 1984. The subject of the contract was the research and development of an excimer laser device (“EMRLD”) that could be used as part of the Star Wars program. The stated objective of the contract was “technology development and laser system design leading to the demonstration of a closed cycle repetitively pulsed electron beam pumped excimer laser.”

The contract incorporated the DAR 7-402.2(c) Limitation of Funds (“LOF”) (1966 OCT) clause, the DAR 7-203.10 Termination (1973 APR) clause, the DAR 7-105.3(c) Stop Work Order (1971 APR) clause, and a version of the AFSC DAR 7-150.3 Award Fee (1977 DEC) clause. The CPAF contract called for a zero base fee and an Award Fee not subject to the Termination or Disputes clauses as to the payment and amount of the award fee, respectively.

The original estimated cost of the contract, as awarded, was $53,144,000. This estimate was revised upwards as a result of a series of contract modifications to a final total of $132,618,264. The contract was incrementally funded. The contract schedule at award allotted only $3,457,992 to the contract. Subsequent adjustments brought the total allotted amount to $113,479,301. Each award fee allotment was made by a contract modification which stated that it was issued pursuant to the Award Fee clause of the contract. AJI other allotments were made pursuant either to the LOF clause or the Changes clause.

The contract created a series of award fees (i.e., profit) that Textron was eligible to receive at the end of each performance period based on its performance during that period. The decision as whether Textron would receive any such award, and if so, how much, was left to the discretion of a Fee Determining Official (“FDO”) based on the FDO’s assessment of Textron’s performance in several specified areas. Initially, the contract specified four performance periods, with the maximum award fees available in each as follows:

Period Maximum Award Fee
1 $3,095,630
2 $3,018,442
3 $1,508,560
4 $ 348,964

That award fee schedule was changed on August 3, 1988, pursuant to bilaterally executed Modification P00057. The Modification increased the number of performance periods from four to seven and ‘back end-loaded’ the award fees in order to create more incentives in the later stages of the program. The revised plan provided for the following: *1467 Under the revised schedule, approximately $11.5 million of the possible $16.8 million was available in the last three periods (i.e., periods five through seven). Modification P00057 retained the discretionary award fee determination scheme of -the original plan. Of the $5.3 million available for award fees in periods one through four, Textron was only awarded approximately $2.5 million, or less than 50% of the amount available.

*1466 Period Maximum Award Fee
1 $1,000,000
2 $1,100,000
3 $1,200,000
4 • $2,000,000
5 $4,000,000
6 $6,484,656
7 $1,000,000

*1467 Funding the program was a constant struggle. From the summer of 1985 through the end of 1987, Textron’s expenditures under the contract exceeded the allocated funding. Textron did not stop work or request the contracting officer to terminate the contract when those overruns occurred, apparently under the assumption that further funding would be allocated. On several occasions those assumptions turned out correct. However, there were no assurances ever given by the contracting officer that future overruns would be covered.

Even before the contract was awarded, the contracting officer informed Textron that “SDI[0] might not continue funding” of EMRLD. In the same notice, the contracting officer urged Textron to “pay particularly close attention to the ‘Limitation of Funding’ clause.” During the course of the contract, the contracting officer repeatedly reminded Textron that the LOF clause was in effect. On one occasion, after learning that Textron was operating in a cost-overrun situation, the contracting officer warned Textron that “any work performed beyond the funding limit is at your own risk, as there is a possibility that additional funds may not be made available.”

The funding situation became even more tenuous in the fiscal years after 1987 because funding was no longer being provided by SDIO or the Air Force. Instead, the funds,if any, were to be eongressionally directed. In an internal memorandum, Textron acknowledged the difficulty it faced obtaining future funding on “the Hill,” unless it could “find a champion in the Air Force or SDIO.”

Textron completed the fourth performance period on September 15, 1989 and began work on the fifth performance period. About that same time, Congress decided not to provide specific funding for EMRLD in fiscal year 1990. Accordingly, by letter dated September 29, 1989 — a mere two weeks into the fifth performance period — the Government directed Textron to stop all work effective October 1, 1989. Textron was permitted to perform specific close-out work, which had been separately funded by a final allotment under the LOF clause by unilateral modification P00071. On December 28, 1990, the contracting officer terminated for the convenience of the Government all remaining work under the contract, with the exception of certain atmospheric tests that are not relevant here.

On December 19, 1990, Textron submitted a termination settlement proposal to the Government. That proposal requested $13,428,-348 over and above the $113,479,301 paid to date under the contract. At that time, the total allowable costs incurred by Textron in performing the contract, including termination costs, were $112,190,867. When the parties were unable to agree on a settlement, Textron submitted a certified termination claim to the contracting officer in the amount of $10,225,925. That claim included $1,368,-389 for unreimbursed costs and $8,857,536 in additional award fee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Causam Enterprises, Inc. v. Itc
Federal Circuit, 2025
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
Auld v. United States
Federal Claims, 2023
Betance Enterprises, Inc.
Armed Services Board of Contract Appeals, 2023
Filler v. United States
Federal Claims, 2020
Shaw v. United States
131 Fed. Cl. 181 (Federal Claims, 2017)
HTA Aviation, LLC
Armed Services Board of Contract Appeals, 2014
Horn v. United States
98 Fed. Cl. 500 (Federal Claims, 2011)
McHugh v. DLT Solutions, Inc.
618 F.3d 1375 (Federal Circuit, 2010)
States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
LAI Services, Inc. v. Gates
573 F.3d 1306 (Federal Circuit, 2009)
Hallwood Plaza, Inc. v. United States
84 Fed. Cl. 804 (Federal Claims, 2008)
West Bay Builders, Inc. v. United States
85 Fed. Cl. 1 (Federal Claims, 2008)
Belize Telecom, Ltd. v. Government of Belize
528 F.3d 1298 (Eleventh Circuit, 2008)
Kerin Motors, Inc. v. United States
80 Fed. Cl. 679 (Federal Claims, 2008)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
143 F.3d 1465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/textron-defense-systems-v-sheila-e-widnall-secretary-of-the-air-force-cafc-1998.