Sheffield Korte Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedAugust 11, 2023
Docket62972, 62973
StatusPublished

This text of Sheffield Korte Joint Venture (Sheffield Korte Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sheffield Korte Joint Venture, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Sheffield Korte Joint Venture ) ASBCA Nos. 62972, 62973 ) Under Contract No. W912QR-15-C-0027 )

APPEARANCE FOR THE APPELLANT: Michael E. Wilson, Esq. Greensfelder, Hemker & Gale, P.C. St. Louis, MO

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney R. Lauren Horner, Esq. James M. Inman, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Louisville

OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT AND APPELLANT’S CROSS-MOTION FOR PARTIAL SUMMARY JUDGMENT

These appeals involve a contract for design and construction of a new 600- member Army Reserve Center near Waldorf, Charles County, Maryland. Sheffield Korte Joint Venture (SKJV) seeks additional compensation from the United States Army Corps of Engineers (USACE) to meet permitting requirements imposed on this project. SKJV also appeals the contracting officer’s (CO) decision to rescind a series of five unilateral modifications issued by USACE providing additional compensation to SKJV for difficulties it encountered in obtaining sewer, water, and access permits from Charles County and the Maryland State Highway Administration (MDSHA).

USACE moves for summary judgment on the grounds that Federal Acquisition Regulation (FAR) 52.236-7, PERMITS AND RESPONSIBILITIES (NOV 1991) and other contract provisions required SKJV to obtain licenses and permits necessary for project completion without additional expense to the government. USACE also seeks summary judgment of its affirmative claim for recoupment of the amounts paid under the unilateral modifications. SKJV moves for partial summary judgment on the grounds that USACE constructively changed the contract by providing defective specifications and by misrepresenting the project’s requirements. SKJV also challenges the credit sought by the government in the amount of $418,406 arguing that there was accord and satisfaction between SKJV and USACE regarding the five unilateral modifications. USACE responds that there was no accord and satisfaction regarding the five unilateral modifications as appellant contends. For the reasons identified below, we grant USACE’s motion and deny SKJV’s motion.

STATEMENT OF FACTS (SOF) FOR THE PURPOSE OF THE MOTIONS

1. On August 28, 2015, USACE awarded Contract No. W912QR-15-C-0027 to SKJV for “Design and Construction of a New 600-Member Bowie Army Reserve Center Project located near Waldorf, Charles County, Maryland” (R4, tab 11A at 720, 722; 1 tab 11B at 733).

2. The total contract price was $21,427,802, including base work and all exercised options at time of award (R4, tab 11A at 720; tab 11B at 734).

3. The as-awarded project also included design and construction of an organizational maintenance shop, an unheated storage building, and military equipment parking (R4, tab 11B at 739-41).

4. The contract’s statement of work (SOW) included specification Part 1, entitled “Design Objectives, and Functional and Area Requirements” (R4, tab 11C at 1017). Section 1.1.2 of Part 1 provided: “This project shall consist of the design and construction of an Army Reserve Center complete with required utilities, storm drainage, communications, electric, HVAC, fire protection/alarm systems, IDS, force protection measures, paving, walks, curbs, parking, access roads, exterior lighting, site improvements, grading and landscaping on Government-owned land” (id.).

5. Section 1.2.4 of Part 1, “Design Freedom,” provided:

Requirements stated in this RFP are minimums. Innovative, creative, or cost-saving proposals, which meet or exceed these requirements are encouraged, and will be considered more favorably.

....

1.2.4.2 The conceptual design Drawings, this Statement of Work, and the Outline Technical Specifications, along with the other information and requirements in this RFP, serve as requirements for Contractor building design and construction completion, along with other code, regulatory and professional practice requirements. The extent of

1 The government R4 page numbers begin with “GovR4-000” and are omitted here. 2 development of these RFP documents in no way relieves the successful offeror from responsibility for completing the design, construction documentation, and construction of the facility in conformance with Applicable Criteria and codes.

1.2.4.3 The conceptual design illustrates desired general arrangements, orientation, and adjacencies, and provides examples of exterior images which is acceptable to the Government – it is not intended to dictate the final layout and image for the project. The Contractor’s designers shall develop and refine the conceptual site and building design in their completion of the design and construction documents. Such development shall be consistent with the criteria and acceptable to the Government.

(R4, tab 11C at 1018) (emphasis added)

6. Section 1.3 of Part 1, “Contractor Responsibility,” provided: “The Contractor shall provide all labor, materials, equipment, supplies, permits, fees, and consultant services to design and construct this Training Center complex” (R4, tab 11C at 1020) (emphasis added).

7. Section 1.7 of Part 1, “Site,” provided, in part:

Site work includes all design and construction of site features necessary to meet the intent of the RFP, including but not limited to, site planning, demolition, clearing, grading, erosion control, site drainage, utility systems, pavements, pedestrian and vehicular circulation systems, signage, site lighting, landscaping, physical security measures, fencing, permitting, and site furnishings.

(R4, tab 11C at 1023) (emphasis added)

8. Section 1.7.8 of Part 1, “Regulatory Compliance,” provided:

The Contractor shall assure that the site development complies with all applicable local, State and Federal regulations. A list of known regulations is located in the Attachments to this Statement of Work. Timely acquisition of the necessary design and construction related permits

3 shall be the responsibility of the Contractor. The Contractor, upon notice to proceed, shall immediately begin working on the permits so as not to delay completion of the project. The Contractor shall prepare permits, associated drawings, public notices, and other related documentation as necessary to successfully meet permit approval status. The Contractor shall pay for associated permit fees.

(R4, tab 11C at 1026) (emphasis added)

9. The SOW included specification Part 2, entitled “Applicable Criteria and Coordination With Local Authorities” (R4, tab 11C at 1029). Section 2.2, “Local and State Codes or Standards,” provided:

The following specifications, codes, standards, bulletins and handbooks form a part of this RFP.

2.2.1 State and Local

Maryland State Highway Administration - Standard Specifications for Construction and Materials Maryland State Highway Administration – State Highway Access Manual Engineering Access Permits Division January 2004 Maryland State Highway Administration – Highway Drainage Manual Maryland Department of the Environment - 2011 Maryland Standards and Specifications for Soil Erosion and Sediment Control Maryland Department of the Environment – 2000 Maryland Stormwater Design Manual Maryland Department of the Environment - Erosion and Sediment Control Guidelines Maryland Department of the Environment - Stormwater Management Guidelines for State and Federal Projects, April 15, 2010 Maryland Forest Conservation Act Charles County Department of Planning and Growth Management – Water and Sewer Ordinance, September 2011 or current edition

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Krygoski Construction Company, Inc. v. United States
94 F.3d 1537 (Federal Circuit, 1996)
P.R. Burke Corp. v. United States
277 F.3d 1346 (Federal Circuit, 2002)
Varilease Technology Group, Inc. v. United States
289 F.3d 795 (Federal Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Sheffield Korte Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sheffield-korte-joint-venture-asbca-2023.