T. Brown Constructors, Inc. v. Federico Pena, Secretary of Transportation

132 F.3d 724
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 2, 1998
Docket96-1147
StatusPublished
Cited by45 cases

This text of 132 F.3d 724 (T. Brown Constructors, Inc. v. Federico Pena, Secretary of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. Brown Constructors, Inc. v. Federico Pena, Secretary of Transportation, 132 F.3d 724 (Fed. Cir. 1998).

Opinion

PLAGER, Circuit Judge.

T. Brown Constructors, Inc. (“Brown”) appeals from a decision of the Department of Transportation Board of Contract Appeals (“Board”) in DTBCA No.1986, dated August 18, 1995. We affirm-in-part and reverse-in-part.

I. BACKGROUND

On December 4,1984, Brown and the Federal Highway Administration (“FHWA” or “Government”) entered into a contract. Under the contract, Brown was required to perform grading, drainage, and asphaltic surfacing along 4.6 miles of two-lane highway on Sunspot Road in the Lincoln National Forest, near Cloudcroft, New Mexico (“Cloud-croft project”). The work was to be completed within 200 calendar days of receipt of the notice to proceed. The contract was a fixed-unit-price, variable quantity contract in the amount of $2,739,812. The Bid Schedule was comprised of individual pay items for estimated quantities. For each pay item, appellant bid a unit price and extended that price to reflect the bid for the entire estimated quantity. The work was to be performed in accordance with the standard Federal Acquisition Regulation clauses applicable to construction contracts, the “Standard Specification for Construction of Roads and Bridges on Federal Highway Projects, FP-79 (Revised edition — June 1981)” (“FP-79”), the Special Contract Requirements (“SCR”), which amended FP-79, the plans, and the Bid Schedule.

Subsequently, by letter dated August 1, 1986, Brown’s attorney asserted that Brown was entitled to additional compensation for extra work related to (1) a differing site condition, i.e., clay in the quarry, (2) an overly restrictive subgrade tolerance, (3) changes to the traffic control requirements, (4) FHWA-caused delay, (5) improper calculation by the FHWA of a “pay factor,” (6) improper reduction of price for out-of-specification material, and (7) failure of the FHWA to pay Brown for individual removal of trees and stumps. Although the letter included a Contract Disputes Act (“CDA”) certification, the amounts sought for each item were only estimates.

The contracting officer (“CO”) responded by letter dated August 25, 1986, noting first that, despite the certification, the August 1 letter was not a claim under the CDA because the amounts were not set forth as sums certain. The contracting officer, nonetheless, addressed the merits of each issue raised and rejected all of Brown’s requests. In its response, the FHWA indicated that Brown’s allegations lacked supporting documentation. Brown sent another letter to the Contracting Officer on March 13, 1987, in response to FHWA’s request for additional information, reiterating its position. The Contracting Officer again objected to the lack of supporting evidence but proceeded to make a final decision on each of Brown’s *727 claims. The CO denied all of Brown’s claims on December 14,1987.

Brown promptly appealed the CO’s decision to the Board. Almost six years later, following a trial on entitlement, the Board issued its decision denying substantially all of Brown’s requested relief. Brown now appeals to this court from that decision.

II. STANDARD OF REVIEW

This appeal is brought pursuant to the CDA, .41 U.S.C. §§ 601-613 (1994). Our review is therefore circumscribed. Under the CDA:

The decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.

41 U.S.C. § 609(b) (1994). As the statute plainly states, and as we have said before, § 609(b) means that if the Board’s findings of fact are supported by substantial evidence, we will not alter them even though the record may contain evidence supporting a contrary position. See Erickson Air Crane Co. of Washington v. United States, 731 F.2d 810, 814 (Fed.Cir.1984). “Substantial evidence ‘means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.’ ” United States v. General Elec. Corp., 727 F.2d 1567, 1572 (Fed.Cir.1984) (quoting Consolidated Edison Corp. v. NLRB, 305 U.S. 197, 229, 59 S.Ct. 206, 216, 83 L.Ed. 126 (1938)). Accordingly, a contractor bears a heavy burden in demonstrating that a Board’s factual findings should be overturned. See Fruin-Colnon Corp. v. United States, 912 F.2d 1426, 1430 (Fed.Cir.1990); Koppers Co. v. United States, 186 Ct.Cl. 142, 405 F.2d 554, 557-59 (1968).

As to questions of law, however, a Board’s decision is not final or conclusive, see 41 U.S.C. § 609(b); American Elec. Labs., Inc. v. United States, 774 F.2d 1110, 1112 (Fed.Cir.1985), and thus a Board’s interpretation of a contract is not binding upon this court, see B.D. Click Co. v. United States, 614 F.2d 748, 752, 222 Ct.Cl. 290 (1980). Nonetheless, we give careful consideration and great respect to a Board’s interpretation because “legal interpretations by tribunals having expertise are helpful to us, even if not compelling.” United States v. Lockheed Corp., 817 F.2d 1565, 1567 (Fed.Cir.1987); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).

III. DISCUSSION

Road construction, in general, proceeds in several distinct steps. This ease is no different. The first is the clearing and grubbing step to remove trees, brush, and other obstructions. Next, the excavation and embankment or “cut and fill” operation is performed to bring the road to the required subgrade level. This step entails cutting, or excavating, the hills and filling in the valleys with the excavated materials. Finally, the “pavement structure” is placed on top of the subgrade. The pavement structure consists of subbase, base course, and asphalt-treated or bituminous-treatéd material. The asphalt-treated material further consists of “host mix,” also referred to as “binder,” and open graded friction course, also referred to as seal. The seal is the top layer of the pavement structure. Most of these steps are implicated in the present appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Endure Industries, Inc.
Armed Services Board of Contract Appeals, 2026
Hahnenkamm, LLC v. United States
104 F.4th 1333 (Federal Circuit, 2024)
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
Dynamic Systems Technology, Inc.
Armed Services Board of Contract Appeals, 2023
Tanik Construction Company, Inc.
Armed Services Board of Contract Appeals, 2022
Odyssey International, Inc.
Armed Services Board of Contract Appeals, 2021
Tyler v. Uber Technologies, Inc.
District of Columbia, 2020
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)
Asi Constructors, Inc. v. United States
129 Fed. Cl. 707 (Federal Claims, 2016)
King Aerospace, Inc.
Armed Services Board of Contract Appeals, 2016
Diversified Construction of Oklahoma
Armed Services Board of Contract Appeals, 2015
Delhur Industries, Inc. v. United States
95 Fed. Cl. 446 (Federal Claims, 2010)
Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
International Technology Corp. v. Winter
523 F.3d 1341 (Federal Circuit, 2008)
Metric Construction Co. v. United States
80 Fed. Cl. 178 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
132 F.3d 724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-brown-constructors-inc-v-federico-pena-secretary-of-transportation-cafc-1998.