Planning Research Corporation v. The United States, and Electronic Data Systems Federal Corporation, Intervenor

971 F.2d 736, 38 Cont. Cas. Fed. 76,383, 92 Daily Journal DAR 11172, 1992 U.S. App. LEXIS 17857, 1992 WL 184553
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 5, 1992
Docket89-1562
StatusPublished
Cited by53 cases

This text of 971 F.2d 736 (Planning Research Corporation v. The United States, and Electronic Data Systems Federal Corporation, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Planning Research Corporation v. The United States, and Electronic Data Systems Federal Corporation, Intervenor, 971 F.2d 736, 38 Cont. Cas. Fed. 76,383, 92 Daily Journal DAR 11172, 1992 U.S. App. LEXIS 17857, 1992 WL 184553 (Fed. Cir. 1992).

Opinion

ARCHER, Circuit Judge.

Planning Research Corporation (PRC) appeals the decision of the General Services Board of Contract Appeals (board) which sustained the protest filed by Electronic Data Systems Federal Corporation (EDS) to the contract awarded to PRC by the Energy Information Administration (EIA), United States Department of Energy, 89-2 BCA 1121,655. EDS intervened and urges on appeal that the board’s decision be affirmed. The United States has contested that part of the board’s decision holding that PRC’s contract should be terminated at no cost to the government. The board’s decision terminating the contract is affirmed, but its determination that the contract termination should be at no cost to the government is vacated.

I.

EIA solicited bids for the management and support of its Forrestal Computer Facility located in Washington, D.C. EDS was the incumbent contractor at the facility. The contract was for a term of two years, with three successive one-year renewal options. The total estimated cost was in excess of $34 million.

In the original Request for Proposal EIA informed bidders that:

The selected offeror must be able to provide a dedicated, stable, and technically qualified staff to maintain continuity in level of service_ Therefore, in order for the contractor to be successful the majority of the work must be performed by a qualified work force whose personnel remain relatively constant.... Work cannot be delayed in order to continuously train new contract personnel.

To evaluate each bidder’s proposed staffing, EIA required the submission of a ré-sumé for each of the nineteen “key” and eighty-two “non-key” personnel to be committed for the first year’s staffing. The solicitation also required a statement defining the extent to which the corporation would commit the named key personnel to the contract. 2

*738 PRC submitted its initial proposal to EIA containing the résumés of 101 people retrieved from a database of employee ré-sumés maintained for bidding and other purposes. In its proposal, however, PRC disclosed that, if awarded the contract, it intended to hire and rely on incumbent EDS employees to staff the contract. The PRC proposal stated that “immediately upon contract award, PRC will obtain a roster of incumbent employees and begin recruiting efforts” and that it “estimate[d] that a high percentage of incumbent personnel at EIA will be available to join PRC.” After the field of potential contractors was reduced to PRC and EDS, EIA asked the two corporations to respond to written and oral questions. Specifically, EIA questioned PRC’s statement concerning the hiring of incumbent personnel and advised PRC that, if true, it would be considered a weakness in its proposal. Thereafter, PRC repeatedly assured EIA both orally and in writing that incumbent personnel would not be required and that the people named in its proposal would be the actual ones who would perform the contract. For example, in its written response to one of EIA’s questions, PRC stated:

PRC will provide, as proposed, a full and complete staff for the EIA Forrestal Computer Facility from our current personnel resources. No incumbent personnel are required.

The revised PRC proposal also provided:

It should be noted that PRC’s transition planning does not assume the retention of incumbent personnel. PRC has developed a superior project staff from our own current resources, the key people being members of our most senior staff. PRC has identified employees for all project positions.
We do not anticipate recruiting new personnel to initially staff the EIA project.

Despite the repeated assurances regarding staffing, the board found that, with the exception of the project director and one or two other key personnel, PRC had not contacted the people who had been proposed, or their supervisors, to determine their availability to work on the EIA contract at the time of submitting its best and final offer (BAFO). Moreover, at about the time PRC’s BAFO was submitted, a senior personnel manager sent a memorandum regarding the EIA contract to PRC’s vice president in charge of the procurement stating that:

[bjased upon assumptions that relatively few internal candidates will actually be assigned to the effort and few of the incumbents will join PRC, I am anticipating that we will have to hire in excess of 50 people over the next two months.

PRC’s personnel office then began planning the recruiting effort for the EIA contract.

During the course of contract negotiations, the changes that PRC and EDS made in their proposed staffing received the close scrutiny of EIA. In the nine-month period between the submission of its initial offer and its BAFO, PRC made twelve substitutions. In every case, these substitutions were made only after PRC was ad *739 vised by government representatives that its selected people appeared to be overqualified or underqualified for the position involved or no longer worked for PRC.

EDS, on the other hand, made numerous substitutions to its proposed staffing for various reasons. EDS stated at the time of submitting its BAFO that the information on the changes in proposed staffing was to “make sure that they reflected the exact situation at the time of submission.” EIA viewed EDS’s substitutions to be “turnover” and considered it a weakness in evaluating EDS’s proposal. The board found that EIA “downgrade^] EDS for its forthright revisions in staffing.” As a result, PRC was awarded the contract.

After contract award, PRC’s project director asked EIA’s contract supervisor (who had also served as chairman of the EIA source evaluation board that reviewed PRC’s and EDS’s BAFOs) if there were incumbent EDS personnel he would like to see hired by PRC. The names of four or five incumbent employees were provided, as well as the home telephone numbers of all incumbent employees of EDS and its subsidiary. With EIA’s approval, PRC then discussed employment or offered positions to all of EDS’s (and its subsidiary’s) personnel at the Forrestal Computer Facility. In the same time frame, PRC ran an advertisement in The Washington Post for an open house at which it recruited for the EIA contract.

The board found that PRC’s substitutions of personnel to staff the contract were extensive. At the time the board issued its order suspending the contract, seventy-four people had been “identified” to work on the EIA contract. PRC had hired twenty-four of these people from EDS or its subsidiary and had five offers outstanding. Twelve were hired from other sources. Three positions were filled by PRC employees who were not among those proposed. For the key positions, PRC had replaced three employees and was seeking replacements for four others. Based on these findings of the board, forty-two of the seventy-four employees for the EIA contract were not the ones proposed by PRC in its BAFO.

EDS filed a protest with the board challenging the award of the contract to PRC and the board suspended EIA’s procurement pending the resolution of the protest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richardson v. United States
110 F.4th 1375 (Federal Circuit, 2024)
Algese 2 S.C.A.R.L. v. United States
125 Fed. Cl. 431 (Federal Claims, 2016)
Rotech Healthcare, Inc. v. United States
121 Fed. Cl. 387 (Federal Claims, 2015)
Bannum, Inc. v. United States
119 Fed. Cl. 291 (Federal Claims, 2014)
Kingdomware Technologies, Inc. v. United States
754 F.3d 923 (Federal Circuit, 2014)
Jordan Pond Company, LLC v. United States
115 Fed. Cl. 623 (Federal Claims, 2014)
Optimization Consulting, Inc. v. United States
115 Fed. Cl. 78 (Federal Claims, 2014)
Excel Manufacturing, Ltd. v. United States
111 Fed. Cl. 800 (Federal Claims, 2013)
Skyline Contractors, Inc. v. Spokane Housing Authority
289 P.3d 690 (Court of Appeals of Washington, 2012)
Phoenix Management, Inc. v. United States
107 Fed. Cl. 58 (Federal Claims, 2012)
Electronic On-Ramp, Inc. v. United States
104 Fed. Cl. 151 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
971 F.2d 736, 38 Cont. Cas. Fed. 76,383, 92 Daily Journal DAR 11172, 1992 U.S. App. LEXIS 17857, 1992 WL 184553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/planning-research-corporation-v-the-united-states-and-electronic-data-cafc-1992.