Skyline Contractors, Inc. v. Spokane Housing Authority

289 P.3d 690, 172 Wash. App. 193
CourtCourt of Appeals of Washington
DecidedDecember 6, 2012
DocketNo. 30190-7-III
StatusPublished
Cited by5 cases

This text of 289 P.3d 690 (Skyline Contractors, Inc. v. Spokane Housing Authority) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skyline Contractors, Inc. v. Spokane Housing Authority, 289 P.3d 690, 172 Wash. App. 193 (Wash. Ct. App. 2012).

Opinion

Siddoway, J.

¶1 — The Spokane Housing Authority awarded a public works contract to Skyline Contractors Inc. but then refused to execute its owner-contractor agreement with Skyline and withdrew acceptance of its bid after Skyline failed to produce documentation of its subcontractor arrangements. The parties dispute whether a contract arose from the award and whether Skyline can pursue a claim for monetary damages for its breach.

f 2 Under well-settled principles of law, contractual obligations arose when the housing authority conveyed its written award of the contract to Skyline. But equally well-settled policy protecting taxpayers from the cost of disputes over such awards compels the conclusion that Skyline’s exclusive remedy was to enjoin the housing authority’s entry into an agreement with another bidder — a remedy it did not pursue. We affirm the trial court’s summary judgment dismissal of Skyline’s claim for damages.

FACTS AND PROCEDURAL BACKGROUND

¶3 In February 2010, the Spokane Housing Authority issued an invitation for bids for a federally funded project to furnish and install windows on 75 homes or duplexes. The invitation for bids included, as a quality assurance contract specification, that the installer of the new windows specialize in performing such work, with a “minimum five years of documented experience.” Clerk’s Papers (CP) at 151.

[196]*196¶4 Among the information required to be submitted with a bid was a “Bidder’s Qualification and Subcontractor’s List,” on which the bidder was to identify its experience, the portions of the work that the bidder would self perform, the portions of the work that would be performed by subcontractors, and the name and qualifications of each subcontractor. The form stated that if the bidder intended to use subcontractors on the project, “you must show the name of the subcontractor WITH the Bid.” CP at 87. In executing the Bidder’s Qualification and Subcontractor’s List, the bidder was required to certify that the information contained “is accurate, complete and current.” Id.

¶5 Skyline submitted a timely bid. It disclosed on its Bidder’s Qualification and Subcontractor’s List that it had been in business for only 3 years as Skyline, but that its key personnel had 20 years of experience. It represented that it would perform 30 to 70 percent of the work and would use one subcontractor, McVay Brothers, who had 21 years of experience in window and door installation.

¶6 Skyline submitted the lowest bid, but the housing authority determined it was not a responsible bidder based on its less-than-five years of experience in window installation. On March 22, it notified all of the bidders that “[ajfter reviewing all of the submitted bids, we have determined that WRS Contractors Inc. [,] DBA Window Replacement System!,] shall be awarded the contract.” CP at 196.

¶7 Skyline protested the award the next day. Although it had not yet been able to determine why its bid was rejected, it pointed out that in addition to its own experience, “we provided McVay Brothers as an additional installation company that also qualifies us under your guidelines.” CP at 200.

¶8 It soon learned from housing authority representatives that its bid was rejected on the basis of its less-than-five years of experience. Armed with that information, it supplemented its protest, arguing that the quality assurance specification section “specifically calls for the installer [197]*197to have ‘five years documented experience’ ” and “[w]e submitted not only [Skyline’s] proof of experience, but also the 20+ years of experience from our subcontractor McVay Windows.” CP at 205 (emphasis omitted).

¶9 Skyline asked in its protest that the housing authority reevaluate its bid, which the housing authority did. As part of its reevaluation, the housing authority asked for three items of additional information: first, a specific clarification of the percentage of work Skyline would perform; second, the type of work that Skyline would perform; and third, “[i]f Skyline is performing installation related work please provide 5 years of experience. You may not serve as your own reference.” CP at 212.

¶10 In its response, Skyline stated that it “has full intention of subcontracting all installation of the windows as stated in the bid documents.” CP at 215. In response to the third request for clarification, concerning the installation work, it stated, “Skyline, as stated above, does not intend to self perform installation of the windows. All contract documents will be followed as they were bid.” Id. The response did not suggest any modification or addition to its earlier identification of McVay Brothers as its sole subcontractor.

¶11 After considering the further information, the housing authority treated Skyline’s bid as responsive and on March 29 it notified Skyline that it “shall be awarded the contract” and that a preconstruction meeting would be held on April 12. CP at 218. The instructions to bidders had stated that a “written award shall be furnished to the successful bidder within the period for acceptance specified in the bid and shall result in a binding contract without further action by either party.” CP at 45 (United States Department of Housing and Urban Development Form 5369, § 8(g)). The invitation for bids had provided that the form of agreement between the housing authority and the contractor would be on a form furnished by the housing authority; elsewhere, the housing authority’s minutes and [198]*198communications refer to the form of agreement to be signed as its “Owner-Contractor Agreement.” CP at 38, 220.

¶12 Disagreements and misunderstandings arose shortly after the housing authority notified Skyline of the award. We recap only the principal dispute.

¶13 At the preconstruction meeting held on April 12, discussion touched on Skyline’s use of subcontractors. Minutes of the meeting prepared by representatives of the housing authority characterized Skyline’s representatives as reporting that “[Skyline] had not finalized subcontractors at this time, and may not be using the listed subcontractor per the bid proposal.” CP at 220.

¶14 The housing authority followed up shortly thereafter with notice to Skyline that “a formal request is required to modify your bid in order to change any listed subcontractor or add any additional subcontractor.” CP at 485. Steve Spady, Skyline’s senior project manager, immediately objected that “[a]ny discussions about other subs / workers e[tc]. was and is only discussions in case McVay can’t or chooses not to perform,” and asked for correction of the meeting minutes. Id. at 484. Mr. Spady later testified that Skyline was seeking approval of additional contractors only for risk management reasons, out of concern that the bid process had already delayed commencement of work and McVay Brothers might not be able to provide enough labor to complete the work on schedule.

¶15 Whatever the reason for Skyline’s request for approval of other subcontractors, the housing authority, expressing concern at the deviation from Skyline’s bid, demanded that Skyline produce a copy of its subcontract with McVay Brothers and with any other proposed subcontractor, asserting that submission of all subcontracts with listed subcontractors was a condition precedent to formation of a contract.1 It notified Skyline that it would not execute its [199]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Global Tel Link Corp., V. State Dept. Of Corrections
Court of Appeals of Washington, 2022
Specialty Asphalt & Constr., LLC v. Lincoln County
421 P.3d 925 (Washington Supreme Court, 2018)
Montgomery v. Engelhard
352 P.3d 218 (Court of Appeals of Washington, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
289 P.3d 690, 172 Wash. App. 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skyline-contractors-inc-v-spokane-housing-authority-washctapp-2012.