Hadaller v. Port of Chehalis

986 P.2d 836, 97 Wash. App. 750
CourtCourt of Appeals of Washington
DecidedOctober 29, 1999
Docket24167-6-II
StatusPublished
Cited by8 cases

This text of 986 P.2d 836 (Hadaller v. Port of Chehalis) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hadaller v. Port of Chehalis, 986 P.2d 836, 97 Wash. App. 750 (Wash. Ct. App. 1999).

Opinion

Armstrong, A.C.J.

John Hadaller d/b/a J. Hadaller Construction Company bid on a construction project for the Port of Chehalis. When the Port awarded the contract to another bidder, Hadaller sued, alleging that when the *752 Port voted to award him the bid, an oral contract was formed. The trial judge granted the Port’s motion for summary judgment. We affirm.

FACTS

At the invitation of the Port of Chehalis, Hadaller submitted a bid for construction of the McBride Court Building. On March 30, 1998, Heidi Pehl, the Port’s Executive Director, notified Hadaller and two other contractors in writing that they were the “three apparent low bidders for this project.” In her letter, Pehl said, “In accordance with the project specifications the Port of Chehalis must now determine the lowest qualified bidder.” She then asked each contractor to submit additional information so that the Port could determine “the lowest qualified bidder.” The requested information included: (1) AIA Document A305, Contractor’s Qualification Statement and Performance Record; (2) a list of work that would be performed by the general contractor; (3) a list of products, manufacturers, and supplies; (4) a list of subcontractors; (5) schedule of values, including description of work and cost of each division; and (6) letters of recommendation. Hadaller completed these documents and submitted them to the Port.

On April 8, 1998, the project architect, John Scherer, wrote Pehl that Hadaller “is the lowest qualified bidder.” A “pre-contract” meeting was scheduled for April 10, 1998. On April 9, 1998, Pehl told the Port commission that “the three lowest bids have been reviewed by the architect, attorney and the USDA representative and they have been deemed responsive.” In addition, she said that the contract qualifications of the three low bidders had been reviewed. According to the minutes, she said, “[T]he apparent low bidder is J. Hadaller Construction and the contract will be ready to award after the lease for the building has been signed.” During the meeting, Pehl was notified that the lease had been signed. The commissioners then approved the award of the bid to Hadaller. The USDA, who approves *753 the Port’s plans and specifications for the project, said in a letter, “We have also reviewed and hereby concur in the contract award to J. Hadaller Construction in the base bid amount of $379,490.”

The day after the commission’s vote, Hadaller and his subcontractors met with Scherer and Pehl. At this meeting, Pehl told Hadaller that he had been awarded the bid. Immediately following the meeting, Scherer requested three items of additional information concerning the metal building systems, including a 10-year list of satisfactory installations from his subcontractor, a certification for the metal building manufacturer, and a 20-year manufacturer’s warranty. On the same day, the Port also notified one of the contractors who submitted a bid that “[w]e have awarded the bid to J Hadaller Construction, Inc., . . . and are returning herewith your bid bond.”

On April 14, 1998, Scherer faxed a follow-up to his letter and again expressed his concerns about the metal building systems. He told Hadaller to submit the same three items and indicated that he had spoken to Hadaller on the phone about his concerns the previous day. Scherer wrote, “Please Note: We have a number of issues that need to be laid to rest before we can move ahead with award of the work.” He set a deadline of April 16, 1998, for a “complete response.”

In a fax to Hadaller later that day, Scherer suggested that Hadaller’s subcontractor could not meet the requirement for 10 years of installing steel structures and that a substitution of contractors would violate the bid specifications. On April 16, 1998, the Port commission voted to reject Hadaller’s bid as being “not responsible.” The same day, the Port voted to award the project to Andrew Noel Construction, Inc., subject to approval by the architect. *754 The Port signed a contract with Noel Construction on April 29, 1998. 1

Hadaller did not attempt to enjoin the award of contract to Noel Construction, but instead, after the contract with Noel had been signed, sued for damages for breach of contract. The Port moved for summary judgment, claiming that no oral contract was formed. The trial court granted summary judgment, and Hadaller appeals.

ANALYSIS

A. Summary Judgment

Hadaller first argues that the trial court erred in granting summary judgment because formation of an oral contract is a question of fact. Specifically, Hadaller argues that an issue of material fact exists as to whether an oral contract was formed when the Port voted to award him the contract or when Pehl told him the next day that he had been awarded the contract or bid.

When reviewing an order for summary judgment, we engage in the same inquiry as the trial court. Failor’s Pharmacy v. Department of Soc. & Health Servs., 125 Wn.2d 488, 493, 886 P.2d 147 (1994) (citing Syrovy v. Alpine Resources, Inc., 122 Wn.2d 544, 548-49 n.3, 859 P.2d 51 (1993)). Our review is de novo. Id. at 493 (citing Syrovy, 122 Wn.2d at 548-49 n.3). We will affirm summary judgment if no genuine issue of any material fact exists and the moving party is entitled to judgment as a matter of law. CR 56(c). All facts and reasonable inferences are considered in the light most favorable to the nonmoving party. Failor’s, 125 Wn.2d at 493 (citation omitted). But where reasonable minds could reach but one conclusion on the facts presented, summary judgment is appropriate. Galbraith v. TAPCO Credit Union, 88 Wn. App. 939, 946, 946 P.2d 1242 (1997) (quoting Marquis v. City of Spokane, 130 Wn.2d 97, *755 105, 922 P.2d 43 (1996)), review denied, 135 Wn.2d 1006 (1998).

Hadaller relies on Crown Plaza Corp. v. Synapse Software Systems, Inc., 87 Wn. App. 495, 962 P.2d 824 (1997) and Garbell v. Tall’s Travel Shop, Inc., 17 Wn. App. 352, 563 P.2d 211 (1977), for the proposition that “[djisputes over the existence of oral agreements are not appropriately decided on summary judgment.” Crown Plaza, 87 Wn. App. at 500 (citing Garbell, 17 Wn. App. at 354). But in both cases the parties disagreed over material facts and resolution of the disputes necessarily turned on the credibility of witnesses. See Crown Plaza, 87 Wn. App. at 501; Garbell, 17 Wn. App. at 355.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skyline Contractors, Inc. v. Spokane Housing Authority
289 P.3d 690 (Court of Appeals of Washington, 2012)
Jay Dee/Mole Joint Venture v. Mayor & City Council
725 F. Supp. 2d 513 (D. Maryland, 2010)
Evans & Son, Inc. v. City of Yakima
136 Wash. App. 471 (Court of Appeals of Washington, 2006)
State v. McInally
106 P.3d 794 (Court of Appeals of Washington, 2005)
McFreeze Corp. v. State, Dept. of Revenue
6 P.3d 1187 (Court of Appeals of Washington, 2000)
McFreeze Corp. v. Department of Revenue
102 Wash. App. 196 (Court of Appeals of Washington, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
986 P.2d 836, 97 Wash. App. 750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hadaller-v-port-of-chehalis-washctapp-1999.