Rma Engineering S.A.R.L v. United States

CourtUnited States Court of Federal Claims
DecidedAugust 29, 2018
Docket14-1202
StatusPublished

This text of Rma Engineering S.A.R.L v. United States (Rma Engineering S.A.R.L v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rma Engineering S.A.R.L v. United States, (uscfc 2018).

Opinion

In the United States Court of Federal Claims No. 14-1202 Filed: August 29, 2018

**************************************** Breach of Contract; * Constructive Change; Contract Disputes Act of 1978, 41 U.S.C. §§ * 601–613 (2006); * Duty of Good Faith and Fair Dealing; * Federal Acquisition Regulation, 48 C.F.R. §§ * 6.101 (Competition Requirements), 16.202-1 * (Firm, Fixed-Price Contract), 49.103 (Methods of Settlement), 52.221-13 (Change Order RMA ENGINEERING S.A.R.L., d/b/a/ * Extensions), 52.233-1 (Disputes), 52.236-2 RMV ARCHITECTS, * (Differing Site Conditions), 52.236-3 (Site * Investigations and Conditions Affecting Plaintiff, * Work), 52.236-13 (Safety Equipment), * 52.242-14 (Excusable Delays), 52.243-7 (Change Order), 52.246-12 (Inspection of v. * Construction), 52.249-2 (Termination For * Convenience), 52.249-10 (Termination For THE UNITED STATES, * Default), 53.301-1436 (Settlement Proposal * (Total Cost Basis)); Defendant. * Ratification; Rules of the United States Court of Federal Claims * 9(k) (Pleading Requirements for Contract * Claims), 11(b)(3) (Representations to the * Court), 12(b)(1) (Subject Matter Jurisdiction), * 12(b)(6) (Failure to State a Claim), 15 * (Amending Pleadings); Safety and Health Regulations for Construction, 29 * C.F.R. §§ 1926.1–1926.1442; * Tucker Act Jurisdiction, 28 U.S.C. § 1491. ****************************************

John M. Manfredonia, Manfredonia Law Offices, LLC, Creskill, New Jersey, Counsel for Plaintiff.

Sean Siekkinen, United States Department of Justice, Civil Division, Washington, D.C., Counsel for the Government.

MEMORANDUM OPINION AND ORDER

BRADEN, Senior Judge.

On November 9, 2017, the Government filed a Motion To Dismiss a Second Amended Complaint filed by RMA Engineering S.A.R.L d/b/a RMV Architects (“RMA”) that alleged twenty-three counts arising from the United States Army’s (“Army”) August 4, 2010 decision to terminate an August 1, 2009 contract awarded to RMA for default. In response, RMA filed a March 22, 2018 Cross-Motion, requesting that the court grant RMA leave to file a Third Amended Complaint. For the reasons discussed herein, the Government’s Motion To Dismiss is granted as to Counts 1 through 9 and 11 through 23, but denied as to Count 10. RMA’s Cross-Motion For Leave To Amend is denied.

To facilitate review of this Memorandum Opinion And Order, the court has provided the following outline:

I. FACTUAL BACKGROUND. A. On August 1, 2009, The United States Army Awarded Contract No. W90BRJ-09- C-0036 To RMA Engineering S.A.R.L. B. On August 1, 2009, RMA Engineering S.A.R.L. Received A Notice To Proceed. C. On August 4, 2010, The United States Army Terminated The August 1, 2009 Contract For Default.

II. PROCEDURAL HISTORY.

III. DISCUSSION. A. Jurisdiction. B. Standing. C. The Government’s November 9, 2017 Motion To Dismiss, Pursuant to RCFC 12(b)(1). 1. The Government’s Argument. 2. RMA Engineering S.A.R.L.’s Response. 3. The Government’s Reply. 4. The Court’s Resolution. a. Standard Of Review For A Motion To Dismiss, Pursuant To RCFC 12(b)(1). b. RMA Engineering S.A.R.L.’s Claim For Wrongful Termination (Count 1). c. RMA Engineering S.A.R.L.’s Claims For Delay, Post-Termination Costs, Breach of Contract, And Breach Of The Duty Of Good Faith And Fair Dealing (Counts 2, 21, 22, and 23). D. The Government’s November 9, 2017 Motion To Dismiss, Pursuant To RCFC 12(b)(6). 1. The Government’s Argument. 2. RMA Engineering S.A.R.L.’s Response. 3. The Government’s Reply. 4. The Court’s Resolution a. Standard Of Review For A Motion To Dismiss, Pursuant To RCFC 12(b)(6). b. Differing Site Conditions (Counts 3 and 10). c. Constructive Changes (Counts 4–9, 11–14, and 17–20). d. Misrepresentation Or Unjust Enrichment (Counts 15 and 16). e. Post-Termination Costs (Count 21). E. RMA Engineering S.A.R.L.’s March 22, 2018 Cross-Motion For Leave To File A Third Amended Complaint. 1. RMA Engineering S.A.R.L.’s Argument. 2. The Government’s Response.

2 3. RMA Engineering S.A.R.L.’s Reply. 4. The Court’s Resolution. a. Governing Precedent. b. Whether The Third Amended Complaint Is Unduly Delayed Or Prejudicial To The Government. c. Whether The Third Amended Complaint Is Futile. i. Differing Site Conditions (Counts 3 and 10). ii. Constructive Change (Counts 4–9, 11–14, and 17–20). iii. Uncompensated Pre-Award Design Work (Counts 15–16).

IV. CONCLUSION.

I. FACTUAL BACKGROUND.1

A. On August 1, 2009, The United States Army Awarded Contract No. W90BRJ- 09-C-0036 To RMA Engineering S.A.R.L. On August 1, 2009, the Army awarded Contract No. W90BRJ-09-C-0036 (the “Contract”) to RMA to build training facilities at the Saudi Arabian National Guard (the “SANG”) base in Khashm Al An, Riyadh, Saudi Arabia (the “Project”). Gov’t App’x at 1–2. The Contract was a Foreign Military Sales procurement, whereby RMA agreed to design and build a two-story administrative building, one warehouse, and three sunshades for outdoor training for the 43rd Mechanized Infantry Battalion. 2d Am. Compl. ¶¶ 1, 2, 12. The Contract provided that the administrative building and warehouse would be original designs, but the covered training shelter would be a “modified and site adapted design.” Gov’t App’x at 9–10. A Joint Engineering Team (“JET”) was designated with “cognizance over all technical aspects of the [C]ontract and . . . [responsibility] for monitoring [c]ontractor performance.” Gov’t App’x at 27. The JET included personnel from the SANG and the Army, including the Contracting Officer’s Representative (“COR”). 2d Am. Compl. ¶ 2. The JET was responsible for reviewing three phases of proposed designs, i.e., the S-1, S-2, and S-3. Gov’t App’x at 11.

The Contract required RMA to submit the S-1 design to the JET and, “[u]pon receipt of JET S-1 comments, [RMA was to] incorporate all comments in the drawings and documents, concurrently with the preparation of S-2[ design].” Gov’t App’x at 11. Thereafter, RMA was required to submit the S-2 design to the JET for additional comments and approval. Gov’t App’x at 11. Then, RMA was required to incorporate any JET comments on the S-2 design into the S-3 design, i.e., the final design. Gov’t App’x at 11. RMA was required to build each of the structures according to the S-3 design and, on completion, the buildings were to be “complete and usable in all respects[.]” Gov’t App’x at 12.

1 The facts discussed herein were derived from the September 6, 2017 Second Amended Complaint (“2d Am. Compl.”) and Appendix, filed with the Government’s November 9, 2017 Motion To Dismiss (“Gov’t App’x”).

3 The Contract provided that RMA agreed to supply “all materials, equipment, labor, supervision, and resources required to design and construct” for a firm, fixed-price2 of 4,370,771 Saudi Riyals, of which 352,500 Saudi Riyals would be paid for the S-1, S-2, and S-3 designs. Gov’t App’x at 7–9. On August 1, 2009, the Army issued a Notice To Proceed that required RMA to complete all work within 180 days, i.e., by February 6, 2010. 2d Am. Compl. ¶ 14; Gov’t App’x at 21. Mobilization was to begin after the S-1 design was approved by the JET; full payment would be made “in accordance with Contract Paragraph G.7” and under the relevant CLINs. Gov’t App’x at 12. RMA was required to construct all required buildings, in “accordance with the technical specifications, contract drawings, approved site adapt drawings, and contract requirements.” Gov’t App’x at 15. “[C]hanges in or deviation from the scope of work” could be made, but could be authorized only by the Contracting Officer (“CO”), by a contract modification.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Macktal v. Chao
286 F.3d 822 (Fifth Circuit, 2002)
United States v. Beebe
180 U.S. 343 (Supreme Court, 1901)
Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
United States v. Hougham
364 U.S. 310 (Supreme Court, 1960)
Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Warth v. Seldin
422 U.S. 490 (Supreme Court, 1975)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Franconia Associates v. United States
536 U.S. 129 (Supreme Court, 2002)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Cary v. United States
552 F.3d 1373 (Federal Circuit, 2009)
Tokyo Kikai Seisakusho, Ltd. v. United States
529 F.3d 1352 (Federal Circuit, 2008)
Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)
Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
Figueroa v. United States
466 F.3d 1023 (Federal Circuit, 2006)
Farnsworth & Chambers Co., Inc. v. The United States
346 F.2d 577 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
Rma Engineering S.A.R.L v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rma-engineering-sarl-v-united-states-uscfc-2018.