Winter v. Cath-dr/Balti Joint Venture

497 F.3d 1339, 2007 U.S. App. LEXIS 19565, 2007 WL 2333236
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 17, 2007
Docket2006-1359
StatusPublished
Cited by62 cases

This text of 497 F.3d 1339 (Winter v. Cath-dr/Balti Joint Venture) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winter v. Cath-dr/Balti Joint Venture, 497 F.3d 1339, 2007 U.S. App. LEXIS 19565, 2007 WL 2333236 (Fed. Cir. 2007).

Opinions

Opinion for the court filed by Circuit Judge MOORE. Opinion dissenting-in - part filed by Circuit Judge PROST.

MOORE, Circuit Judge.

The Secretary of the Navy (Navy) appeals the decision of the Armed Services [1341]*1341Board of Contract Appeals (Board) finding in favor of Cath-dr/Balti Joint Venture (Cath) on 13 of 37 claims for an equitable adjustment in contract price. Cath-dr/Balti Joint Venture, ASBCA Nos. 53581, 54239, 05-2 BCA ¶ 33046 (Aug. 17, 2005) (Board Opinion). The Navy asserts that the Board erred in concluding that a Resident Officer in Charge of Contracts1 (ROICC), who was also the Project Manager (PM) during the performance period, had the authority to commit the government to compensable contract changes. Because the contract explicitly reserved authority to modify the contract to the Contracting Officer (CO), the ROICC did not have actual express or implied authority to direct the contractor to perform com-pensable contract changes, and we reverse the Board’s conclusion as to claims 2, 8,13, 17, and 26/32. However, we affirm the Board decision on claim 3 because that claim is independently sustainable based on a differing site condition, which the Navy does not appeal. Finally, we remand claims 7, 33, and 37 to the Board to determine whether the ROICC’s directives on these claims were ratified.

BACKGROUND

I.

On September 29, 1998, Cath and the Navy entered into a fixed price contract for external renovation of a historic dental research facility at the Great Lakes Naval Training Center in Illinois. The contract incorporates by reference several standard government clauses including Federal Acquisition Regulation (FAR) § 52.243-4 (Aug.1987) (Changes Clause), which provides that the CO may, at any time, make changes in the work within the general scope of the contract by written order designated as a change order. FAR § 52.243-4 also provides that for any change affecting the contractor’s cost or time of performance under the contract “whether or not changed by any such order, the [CO] shall make an equitable adjustment and modify the contract in writing.” The contract also includes FAR § 52.236-2 Differing Site Conditions (April 1984), which requires that a contractor give written notice to the CO of subsurface, latent, or unknown physical conditions at the site that differ materially from those indicated in the contracting documents. After such notice, the CO “shall” investigate the site conditions and if they do materially differ and cause an increase in the cost of or time required for completion of the contract “an equitable adjustment shall be made under this clause and the contract modified accordingly” by the CO. Additionally, the contract incorporates Naval Facilities Engineering Command (NAVFAC) Clause 5252.201-9300 Contracting Officer Authority (June 1994) and NAVFAC Clause 5252.242-9300 Government Representatives (June 1994). The Contracting Officer Authority clause reserves authority to the CO to bind the government to any “contract, modification, change order, letter or verbal direction to the contractor,” and the Government Representatives clause indicates that while the Engineer in Charge (EIC) will be designated by the Contracting Officer as his authorized representative responsible for monitoring performance and technical management, in no event will any modification of the contract by anyone other than the CO bind the government.

[1342]*1342II.

Before work under the contract began, a preconstruction conference was held, as required by contract specification section OHIO “Summary of Work,” paragraph 1. 10, entitled “Preconstruction Conference.” Paragraph 1.10 states that the conference will be held with the CO to “develop a mutual understanding” relative to the administration of the contract. The precon-struction conference attendees included numerous individuals from Cath and the Navy, including both the ROICC PM and EIC. Although the contract required that the CO attend the preconstruction conference, the CO was not present.

During the preconstruction conference, the Navy set forth its detailed guidelines for contract administration in a presentation that designated the ROICC PM to administer the contract and stated that all correspondence should be addressed to the attention of Lt. Ken Osmun — the active ROICC PM. The presentation directed the contractor to use the Requests for Information (RFI) form routinely and “[i]f necessary, forward RFI to Navy PM for action.” The presentation included two slides related to contract modification which state “[m]odifications are written alterations to the contract which may change the work to be performed and/or the contract price and time” and “[n]o work is to be performed beyond the contract requirements without written notification from the ROICC.” Another slide related to disputes directed the contractor to submit a request for equitable adjustment to the ROICC if it feels a contract modification is required and “[i]f the ROICC sees no entitlement, or the contractor doesn’t agree with the entitlement, the contractor has the right to request a Contracting Officer’s Final Decision, using the procedures outlined in the Disputes Clause” but that “[t]he contractor must proceed diligently with the work while awaiting the final decision.”

Cath began work under the dental facility contract on January 25, 1999. Soon thereafter, Cath received a letter from the Navy that reassigned the day-to-day administration of the contract to EIC Tim Meland and indicated that all correspondence regarding the contract should be sent to Meland’s attention. In response to this letter, Cath submitted a RFI seeking “documentation of assignment of authority” and the “level of authority” of Meland, among others. The Navy responded to this RFI with respect to Meland as follows:

Mr. Tim Meland. Project Manager: Serves as the Government Construction Manager on all assigned projects. Responsible for construction management and contract administration on assigned projects while providing quality assurance and technical engineering construction advice. Provides technical and administrative direction to resolve problems encountered during construction. A project manager analyzes and Interprets contract drawings and specifications to determine the extent of Contractors’ responsibility. Prepares and/or coordinates correspondence, sub-mittal reviews, estimates, and contract modifications in support to ensure a satisfactory and timely completion of projects.

During the course of the project, Meland and his successor received numerous RFIs from Cath that requested clarification of the contract requirements and gave notice of site conditions that may require deviation from the contract specifications with a request for a decision. In each case, the [1343]*1343ROICC PM signed the response to the RFI. When necessary, the PM asked for the architect/engineer’s input, which was also provided to the contractor in the PM’s response. Some of these responses included a preprinted statement that the response is a contract requirement, which the PM marked.

III.

After Cath’s renovation work under the contract was deemed substantially complete, it submitted a cumulative request for a contract modification and several adjustments to the PM, in accordance with the procedure for equitable adjustment requests set forth in the preconstruction conference presentation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ECC International Constructors, LLC
Armed Services Board of Contract Appeals, 2025
Slsco, Ltd. v. United States
Federal Claims, 2025
Jones v. United States
Federal Claims, 2025
Sheffield Barbers, LLC
Armed Services Board of Contract Appeals, 2025
ECC International Constructors/Metag(JV)
Armed Services Board of Contract Appeals, 2023
Derian, Inc.
Armed Services Board of Contract Appeals, 2023
Trident Engineering & Procurement, P.C.
Armed Services Board of Contract Appeals, 2023
Heartland Energy Partners LLC
Armed Services Board of Contract Appeals, 2022
Bgt Holdings LLC v. United States
984 F.3d 1003 (Federal Circuit, 2020)
ECC International, LLC
Armed Services Board of Contract Appeals, 2020
Guardian Safety & Supply LLC d/b/a Enviro Safety Products
Armed Services Board of Contract Appeals, 2019
North American Landscaping, Construction and Dredge, Co., Inc.
Armed Services Board of Contract Appeals, 2018
Relyant, LLC
Armed Services Board of Contract Appeals, 2018
Bullock v. United States
Federal Claims, 2018
Stromness Mpo, LLC v. United States
134 Fed. Cl. 219 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
497 F.3d 1339, 2007 U.S. App. LEXIS 19565, 2007 WL 2333236, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winter-v-cath-drbalti-joint-venture-cafc-2007.