Slsco, Ltd. v. United States

CourtUnited States Court of Federal Claims
DecidedJune 24, 2025
Docket24-447
StatusPublished

This text of Slsco, Ltd. v. United States (Slsco, Ltd. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slsco, Ltd. v. United States, (uscfc 2025).

Opinion

In the United States Court of Federal Claims

SLSCO, LTD.,

Plaintiff, No. 24-447 v. Filed: June 24, 2025 THE UNITED STATES,

Defendant.

Dean Baxtresser, Kyle R. Jefcoat, Genevieve P. Hoffman, Latham & Watkins LLP, Washington, D.C., for Plaintiff. Nelson Kuan, Trial Attorney, Eric P. Bruskin, Assistant Director, Patricia M. McCarthy, Director, Commercial Litigation Branch, Brett A. Shumate, Acting Assistant Attorney General, Civil Division, United States Department of Justice, Washington, D.C., and J. Drew Piersa, Assistant District Counsel, Los Angeles District, United States Army Corps of Engineers, Los Angeles, California, for Defendant. OPINION AND ORDER HADJI, Judge. Plaintiff SLSCO, Ltd. (SLS) brings this action against the United States under the Tucker Act, 28 U.S.C. § 1491, and the Contract Disputes Act (CDA), 41 U.S.C. § 7101 et seq., challenging a Contracting Officer’s Final Decision (COFD) declining to overturn allegedly improper Contractor Performance Assessment Report (CPAR) ratings. Before the Court is the Government’s Motion to Dismiss pursuant to Rule 12(b)(1) and 12(b)(6) (ECF 32). For the following reasons, the Government’s Motion to Dismiss is GRANTED. BACKGROUND Plaintiff was one of several construction contractors tasked by the Government to construct a border wall on the United States’ southern border in 2019 and 2020. Am. Compl. ¶ 2. On April 9, 2019, the United States Army Corps of Engineers (USACE) awarded Contract No. W912PP-19-C-0018 (the Contract) to SLS for “a design-build project consisting of approximately 46 miles of primary bollard fence replacement including gates, drainage, roads, power distribution, demolition and disposal in El Paso Sector, New Mexico.” Pl.’s Ex. 1 at 1; see also Am. Compl. ¶¶ 36, 38. Work did not commence immediately due to ongoing environmental litigation. Am Compl. ¶ 36. In the following months, Plaintiff and USACE were unable to reach agreement on price or schedule. Am. Compl. ¶ 37. In September 2019, USACE unilaterally definitized the Contract via modification P00005, effectively setting fixed prices under which Plaintiff would perform and establishing January 5, 2021, as the contract completion date. Am. Compl. ¶ 37. Although Plaintiff deemed the schedule unreasonable, Am. Compl. ¶ 37, it does not allege that it asserted any right to an adjustment in accordance with Federal Acquisition Regulation (FAR) 52.243-4(e) (the Changes Clause) within 30 days of the change. See Pl.’s Ex. 1 at 7 (Plaintiff “failed to comply with contractually mandated notice provisions”). Several months later, in modification P00006, USACE again unilaterally modified the Contract to add an additional segment of border wall to the work requirements. Pl.’s Ex. 1 at ¶ 2. The additional 2.4-mile segment covered “steep and rocky terrain,” different in kind from the terrain previously involved in the Contract. Am. Compl. ¶ 40. Although Plaintiff assessed that additional days were necessary to complete the primary barrier and again raised scheduling concerns, USACE added no additional construction days to complete the extra 2.4 miles. Am. Compl. ¶¶ 41-43. Instead, USACE required that construction of the entire 48.4 miles of primary border barrier be completed no later than December 31, 2020. Am. Compl. ¶ 43. However, as part of the same action, USACE extended the overall contract completion date to the end of June 2021, giving Plaintiff additional time to complete the attributes (electrical, CCTV, fiber, and lighting). Am. Compl. ¶ 43. Again, Plaintiff did not assert any right to an adjustment in accordance with the Changes Clause of the Contract. See Pl.’s Ex. at 7. Plaintiff alleges that, in performing the Contract, it faced significant unexpected delays caused by events beyond its control, including severe weather, the COVID-19 pandemic, and Government-caused delays and requirements associated with blasting operations. Am. Compl. ¶¶ 44-57. Nonetheless, Plaintiff completed the original 46-mile segment of border wall in mid-December 2020, as well as “nearly all of the 2.4-mile segment … except for approximately 2000 linear feet” located on a mountain peak. Am. Compl. ¶¶ 58-59. Plaintiff does not allege that, when the performance period closed, it notified USACE of any delays within 10 days as required by FAR 52.249-10(b)(2) (the Default Clause) or sought additional time to complete the project. See Pl.’s Ex. at 7. On January 21 and 23, 2021, USACE formally suspended Plaintiff’s performance on the Contract. Am. Compl. ¶ 27. On May 1, 2021, USACE terminated the Contract in its entirety for convenience. Am. Compl. ¶ 27, 60. USACE issued the initial CPAR for the Contract on October 10, 2020 (the 2020 CPAR). Am. Compl. ¶ 62. USACE rated Plaintiff as “Marginal” for each evaluation factor. Am. Compl. ¶ 62. Plaintiff challenged the 2020 CPAR, with the Contracting Officer ultimately recognizing that the “Government failed to meet many of the requirements and guidelines in the FAR and CPARS guidance.” Am. Compl. ¶ 64. The Contracting Officer directed that the 2020 CPAR be vacated and that Plaintiff’s performance be reassessed. Am. Compl. ¶ 64.

2 Rather than reissue the 2020 CPAR, the Government issued a new CPAR on January 27, 2022, which covered the entire performance period, from April 9, 2019 – April 30, 2021 (the 2021 CPAR). Am. Compl. ¶ 65. Plaintiff was assessed “Marginal” ratings in Quality, Management, and Regulatory Compliance, an “Unsatisfactory” rating in Schedule, and a “Satisfactory” rating in Small Business Subcontracting. Am. Compl. ¶ 65. Although Plaintiff again challenged these ratings, the Reviewing Official finalized the CPAR on March 28, 2022. Am. Compl. ¶ 67. On September 7, 2022, Plaintiff submitted a claim pursuant to the CDA and FAR 52.233-1 (the Claim) in connection with the Contract. Am. Compl. ¶ 13. The Claim requested that USACE vacate and reassess the 2021 CPAR. Am. Compl. ¶ 13. On March 23, 2023, the Contracting Officer issued a COFD granting in part and denying in part the Claim. Am. Compl. ¶ 15; see generally Pl.’s Ex. 1. Specifically, the Contracting Officer concluded that Plaintiff’s Schedule and Regulatory Compliance ratings warranted adjustments from “Marginal” to “Satisfactory.” Pl.’s Ex. 1 at 6; see also Am. Compl. ¶ 124. However, the Contracting Officer affirmed Plaintiff’s “Marginal” Quality and Management ratings. Am. Compl. ¶¶ 20, 124; Pl.’s Ex. 1 at 6. The Contracting Officer deemed Plaintiff’s arguments with respect to timeliness meritless. Am. Compl. ¶ 20; Pl.’s Ex. 1 at 8. On March 22, 2024, Plaintiff brought this suit under the Tucker Act, 28 U.S.C. § 1491(a), and the CDA, 41 U.S.C. §§ 7101-7109. Compl. at 1; Am. Compl. ¶ 18. LEGAL STANDARDS The Government moves to dismiss this suit pursuant to Rules 12(b)(1) and 12(b)(6) of the Rules of the Court of Federal Claims. Rule 12(b)(1) permits dismissal for lack of subject-matter jurisdiction.1 This Court’s jurisdiction is dependent on an unequivocal waiver of sovereign immunity by the United States. United States v. Testan, 424 U.S. 392, 399 (1976). If the Court determines that it lacks subject-matter jurisdiction, it must dismiss the action. Rule 12(h)(3); see Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 94 (1998). The plaintiff bears the burden to demonstrate that jurisdiction is proper by a preponderance of the evidence. Reynolds v. Army and Air Force Exch.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
United States v. Testan
424 U.S. 392 (Supreme Court, 1976)
Allen v. Wright
468 U.S. 737 (Supreme Court, 1984)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Labatt Food Service, Inc. v. United States
577 F.3d 1375 (Federal Circuit, 2009)
St. Christopher Associates, L.P. v. United States
511 F.3d 1376 (Federal Circuit, 2008)
Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
Cook Biotech Inc. v. ACell, Inc.
460 F.3d 1365 (Federal Circuit, 2006)
Crowley v. United States
398 F.3d 1329 (Federal Circuit, 2005)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Slsco, Ltd. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slsco-ltd-v-united-states-uscfc-2025.