ECC International Constructors/Metag(JV)

CourtArmed Services Board of Contract Appeals
DecidedSeptember 20, 2023
Docket62124
StatusPublished

This text of ECC International Constructors/Metag(JV) (ECC International Constructors/Metag(JV)) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ECC International Constructors/Metag(JV), (asbca 2023).

Opinion

DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) ECC International Constructors/ Metag ) ASBCA No. 62124 (JV) ) ) Under Contract No. W5J9LE-11-C-0046 )

APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq. Ryan Boonstra, Esq. Cohen Seglias Pallas Greenhall & Furman, P.C. Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Martin Chu, Esq. Engineer Trial Attorney U.S. Army Engineer District, Baltimore

Samuel J. Harrison, Esq. Katherine M. Smith, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE SWEET

This appeal involves a contract between the United States Army Corps of Engineers (Corps) and appellant ECC International Constructors/Metag (JV) (Joint Venture) to construct arch-span structures at Camp Hero East in Kandahar Province, Afghanistan. The contract required that the Joint Venture include a spray polyurethane foam insulation (foam) and cementitious finish, and that that foam assembly comply with the International Building Code, which required that the foam limit flame-spread and smoke-development and have a thermal barrier. The foam assembly that the Joint Venture initially installed did not meet those requirements. Therefore, the Corps suspended work, and required the Joint Venture to add a thicker thermal barrier. In this appeal, the Joint Venture argues that that conduct constituted a constructive change, which delayed the project. Because the Corps did not direct the Joint Venture to perform work not required under the terms of the contract, or enlarge the Joint Venture’s performance requirements, there was no constructive change. Thus, we deny the appeal. DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. FINDINGS OF FACT

I. Contract

1. The North Atlantic Treaty Organization Training Mission-Afghanistan and the Combined Security Training Command-Afghanistan trained the Afghan National Security Forces. The Corps performed contracting functions for the Combined Security Training Command-Afghanistan for the design and construction of facilities for the Afghan National Security Forces. The Corps performed those functions through the Transatlantic Division and its two subordinate commands—the Transatlantic District-North and the Transatlantic District-South, which covered northern Afghanistan and southern Afghanistan respectively. 1 (Gov’t resp. to Board’s June 2, 2023 Order, ex. 1 (Adams aff.) ¶¶ 4-5;McFerrin aff. ¶¶ 12-14)

2. On August 24, 2011, the Transatlantic District-South awarded Contract No. W5J9LE-11-CC-0046 (Contract) to the Joint Venture to construct facilities at Camp Hero East in Kandahar Province, Afghanistan (Camp Hero East Project) (R4, tab 5 at 1; tab 16 at 1). The Project included the construction of numerous arch-span buildings 2 (R4, tab 5 at 70). Only the Transatlantic District-South Contracting Officer had the authority to revise the design or direct changes, and he did not delegate that authority (R4, tab 436 (Emanuel decl.) ¶ 2).

3. The Contract required that “[t]he work shall conform to the specifications and the contract drawings” (R4, tab 5 at 29; see also id. at 53, 68, 71, 218).

4. The specifications repeatedly required the Joint Venture to comply with the International Building Code (Code) (R4, tab 5 at 70, 91-94, 120-21, 226). The Code § 2603.3 indicated that:

[F]oam plastic insulation . . . shall have a flame spread index of not more than 75 and a smoke-developed index of not more than 450 where tested in the maximum thickness intended for use in accordance with [American Society for Testing and Materials] E 84 or [Underwriters Laboratories] 723.

1 Prior to a reorganization in 2009, the Transatlantic District-North and the Transatlantic District-South were called the Afghanistan Engineer District North and the Afghanistan Engineer District South respectively (gov’t resp. to Board’s June 2, 2023 Order, ex. 1 (Adams aff.) ¶ 4(c); McFerrin aff. ¶¶ 12-14). 2 Arch-span buildings—sometimes called K-Span buildings—are buildings constructed using steel rolled by a machine on-site (McFerrin aff. ¶¶ 4-5). 2 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. (R4, tab 178 at 562) The parties refer to foam that meets and does not meet the Code § 2603.3’s flame-spread and smoke-development limit requirements as rated and non- rated foam respectively (see app. supp. R4, tab 280 at 3; app. br. at 37; gov’t br. at 12). The Code § 2603.4 (collectively with the Code § 2603.3, Code Foam Assembly Provisions) 3 provided that:

[F]oam plastic shall be separated from the interior of a building by an approved thermal barrier of ½ inch (12.7 mm) gypsum wallboard or equivalent thermal barrier material that will limit the average temperature rise of the unexposed surface to not more than 250⁰ F (120⁰ C) after 15 minutes of fire exposure, complying with the standard time-temperature curve of [American Society for Testing and Materials] E 119 or [Underwriters Laboratories] 263. The thermal barrier shall be installed in such a manner that it will remain in place for 15 minutes based on [Factory Mutual Laboratories] 4880, [Underwriters Laboratories] 1040, [National Fire Protection Association Code] 286 or [Underwriters Laboratories] 1715.

(R4, tab 178 at 563) Thus, we find that, by requiring compliance with the Code, the Contract required the use of rated foam and an adequate thermal barrier.

5. The Code § 104.10 set forth a procedure for modifying Code provisions (Code Modification Procedure) as follows:

Whenever there are practical difficulties involved in carrying out the provisions of this code, the building official shall have the authority to grant modifications for individual cases, upon application of the owner or owner’s representative, provided the building official shall first find that special individual reason makes the strict letter of this code impractical and the modification is in compliance with the intent and purpose of this code and that such modification does not lessen health, accessibility, life and fire safety, or structural requirements.

(R4, tab 178 at 29 (emphasis omitted); see also app. supp. R4, tab 387 at 7) For Corps projects in Afghanistan, the building official was the Authority Having Jurisdiction (app. supp. R4, tab 387 at 2). There were three potential Authorities Having

3 We refer to the foam and the thermal barrier together as the foam assembly. 3 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. Jurisdiction (Potential Authorities Having Jurisdiction). First, the Combined Security Training Command-Afghanistan designated the Director, CJ-Engineering, Colonel William Graham, as its Authority Having Jurisdiction (app. supp. R4, tab 52 at 4; tab 319 at 1). Second, the Corps treated its Chief of the Engineering and Construction Directorate of Civil Works, James Dalton, as its Authority Having Jurisdiction (app. supp. R4, tab 93 at 2, tab 148; tab 177 at 2). Third, other evidence suggests that the Transatlantic District-South Contracting Officer became the Authority Having Jurisdiction once performance began (see app. supp. R4, tab 211 at 1; tab 397 (Schmid dep.) at 55:5-24).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Graham
110 U.S. 219 (Supreme Court, 1884)
Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
Julius Goldman's Egg City v. The United States
697 F.2d 1051 (Federal Circuit, 1983)
James T. Hannon v. Department of Justice
234 F.3d 674 (Federal Circuit, 2000)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
ECC International Constructors/Metag(JV), Counsel Stack Legal Research, https://law.counselstack.com/opinion/ecc-international-constructorsmetagjv-asbca-2023.