North American Landscaping, Construction and Dredge, Co., Inc.

CourtArmed Services Board of Contract Appeals
DecidedAugust 9, 2018
DocketASBCA No. 60235, 60236, 60237, 60238
StatusPublished

This text of North American Landscaping, Construction and Dredge, Co., Inc. (North American Landscaping, Construction and Dredge, Co., Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North American Landscaping, Construction and Dredge, Co., Inc., (asbca 2018).

Opinion

.

- . ARMED SERVICES BOARD OF CONTRACT APPEALS .

Appeals of -- ) .

) North American Landscaping, Construction ) · ASBCA Nos. 60235, 60236 and Dredge, Co., Inc. ) 60237,60238 ) Under Contract No. W912WJ-14-C-0004 )

- APPEARANCE FOR THE APPELLANT: Joseph L. Katz, Esq. Huddles Jones Sorteberg & Dachille, P.C. Columbia, MD

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Theresa A. Negron, Esq .. Engineer Trial Attorney U.S. Army Engineer District, New England

OPINION BY ADMINISTRATIVE JUDGE CLARKE

North American Landscaping, Construction and Dredge, Co., Inc. (NALCO) contracted with the U.S. Army Corps of Engineers (COE) for maintenance dredging of the Scarborough River, Scarborough, Maine. NALCO claims the unpaid contract balance of $960,482.48 (ASBCA No .. 60235); unabsorbed overhead in the amount.of $108,868 (ASBCA No. 60236); differing site conditions in the amount of $507,914.19 (ASBCA . No. 60237); and a time extension of 94 days (ASBCA No. 60238). We decide entitlement only. We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 710r-7109. The appeal is sustained in part and denied in part.

FINDINGS OF .FACT

The Solicitation

1. Sealed bid Solicitation No. W912WJ-13-B-0012, issued on 23 August 2013, invited bids for maintenance dredging of an eight-foot channel, a six-foot channel, and a six-foot anchorage on the Scarborough River, Scarborough, Maine (tr. 2/222; R4, tab 4b); Due to environmental restrictions dredging was only permitted from 1 November 2013 through 31 March 2014 (R4, tab 4b at 33, ,i l.2(b)). Dredging was to commence within · 30 days of the Notice to Proceed (NTP) unless that fell within the "no dredge season" of 1 April 2013 through 31 October 2013 (id.). 2. The solicitation contained five-contract line item numbers (CLINs). CLIN_ 000 l was a lump sum for Mobilization and Demobilization. CLINs 0002 through 0004 were for dredging in the three channels for stated estimated quantities at a unit price for each cubic yard of dredged material. CLIN 0005 was an option item for Derelict Mooring Removal and Disposal. Bidders were instructed to bid all items and that all the work would be awarded to one bidder. (R4, tab 4b at 4) There were no instructions concerning what costs were to be included in which CLINs.

3. The solicitation included Federal Acquisition Regulation (FAR) 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4, tab 4b at 25), and Defense FAR Supplement (DF ARS) 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DEC 1991) (tr. 2/223; R4, tab 4b at 36, ,r 1.9). This clause, in full text in the solicitation, reads:

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.

(1) Sixty percent of the lump sum price upon completion of the contractor's mobilization at the work site.

(2) The remaining 40 percent upon completion of demobilization.

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs a(l) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determ,ined by the Contracting Officer, of-

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization; and

(iii). The remainder of this item in the final payment under this contract.

2 (2) The Contracting Officer's det~rmination of the actual costs in paragraph b(l) of this clause is not subject to appeal.

(R4, tab 4b at 36, ~ 1.9) Ms. Jessica Kidd was the contracting officer (CO) for NALCO's contract (tr. 2/220-21). CO Kidd testified that paragraph (b) allows the COE to pay "actual costs at the time of mobilization and demobilization and then make full payment for that line item at the end of the contract" (tr. 2/224).

4. The construction specifications for the project included section 35 20 23, "HYDRAULIC DREDGING" (R4, .tab 4d at 160}. Part_ 3, "EXECUTION," paragraph 3.6.2, Deposition in Disposal Sites, required that the dredged material be placed "at ' Western Beach at the Prouts Neck Country Club [PNCC] as shown on the contract drawings." "[D]redged material shall be transported to Western Beach by locating the pipeline on [PNCC] property at Ferry Rock and then along the beach face above the Mean High Water elevation to the discharge area." (R4, tab 4d at 166, 171) The western beach disposal area was shown on Drawing G-101. Ferry Rock was at the northern·end of western beach and dredged material was to be placed north to south from Ferry Rock along the Western Beach. (R4, tab 4c, drawings G-101, -104) There is no indication on the disposal area drawing that a stone revetment 1 was to be built at the northern end of the western beach disposal area by PNCC (id.; tr. 2/103, 3/99). The 8-foot deep channel was to be completed first, "prior to the start of dredging of all other areas" (R4, tab 4d at 62, ~ 1.1 ).

5. Specification section 35 20 23, Hydraulic Dredging, part 3, Execution, provides other details relating to dredging (R4, tab 4d at 160). Paragraph 3.4.3, Adjacent Property and Structures, required the contractor to "conduct the dredging operation such that it does not undermine, weaken or otherwise impair existing structures located in or near the areas to be dredged" (id. at 168). Paragraph 3.5.7, Safety of Structures and Utilities, likewise requires protection of "piers, bulkheads, revetments, and other structures and utilities lying on, under or adjacent to the site of the work" (id. at 170). The specification also requires construction of temporary seaward berms to "contain the maximum amount of dredged material as possible on · the beach disposal area" (id.,~ 3.6.l(d)), and the use of a "baffle at the pipe discharge to prevent erosion of the existing beach" (id.,~ 3.6.4(b)).

Site Visit

6. · The COE held a site visit on 4 September 2013. In addition to three COE representatives, representatives from Southwind Construction, the Town of· Scarborough's harbormaster, and the president and general manager of Prouts Neck

1 See finding 77, infra, for an explanation of what a revetment is.

3 Country Club attend€d. NALCO did not attend: (R4, tab Sa) There are no minutes or any other record of what was discussed during the site visit.

Two Bidders Responded

7. Bids were publicly opened on 23 September 2013. When the bids were opened they were recorded on an abstract of offers. (Tr. 2/225; R4, tab 8) The two. offerors were NALCO and Village Dock (VD). The Independent Government Estimate (IGE) and bids were:

IGE -IGE NALCO NALCO VD VD CLIN· Unit Estimated Unit Estimated Unit Estimated Description Price Amount Price Amount Price Amount Mobilization and LS 701,770 LS 1,457,044 LS 1,500,000 Demobilization · Dredging 8' 19.34 771,666 2.50 99,750 14.30 570,570 channel First 39,900 CD Over 39,900CD 19.~4 427,414 1.40 30,940 14.30 316,030 Dredging 6' 24.49 198,3(:,9 2.50 20,250 14.30 115,830 channel Fjrst ' 8,100 CD Over 8, 100 CD 24.49 210,614" 1.40 12,040 14.30 122,980 Dredging 6' 13.51 347,207 2.50 64,250 14.30 367,510 anchorage First . 25,700 CD Over 25,700 13.51 133,749 1.40 13,860 14.30 141,570 Derelict Mooring 5,020 25,100 346 1,730 1,000 5,000 Total $2,815,889 $1,699,864 $3,139,490

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
Alabama v. North Carolina
560 U.S. 330 (Supreme Court, 2010)
States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Beatty v. United States
168 F. Supp. 204 (Court of Claims, 1958)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Hunkin Conkey Construction Co. v. United States
461 F.2d 1270 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
North American Landscaping, Construction and Dredge, Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-american-landscaping-construction-and-dredge-co-inc-asbca-2018.