Relyant, LLC

CourtArmed Services Board of Contract Appeals
DecidedJune 27, 2018
DocketASBCA No. 59809
StatusPublished

This text of Relyant, LLC (Relyant, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Relyant, LLC, (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Relyant, LLC ) ASBCA No. 59809 ) Under Contract No. W91B4N-08-D-0011 )

APPEARANCE FOR THE APPELLANT: James H. Price, Esq. Lacy, Price & Wagner, PC Knoxville, TN

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ Jason W. Allen, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE PROUTY

The dispute before us, 1 which was aired in a three-day hearing, is centered upon the government's acceptance of certain pre-fabricated relocatable buildings (RLBs) for use at two different sites in Afghanistan. As will be described in far greater detail below, different government contracting officer representatives (CORs) at the two different locations had diverging views regarding whether the RLBs initially provided by appellant, Relyant, LLC (Relyant), should be permitted under the contract specifications that applied to both locations. In particular, the RLBs delivered to the first site passed a First Article Test (FAT) at that site, but were deemed to be out of compliance with the contract's statement of work (SOW) by the contracting officer (CO), and were not permitted at the second site. To get around the problem, Relyant shipped the RLB components first delivered to second site to the first site, where the local accepting authority (not the CO) apparently turned a blind eye to the RLBs' failure to comply with the SOW2 ; Relyant then revamped its means of manufacturing the RLBs to provide RLB components that satisfied the CO (and contract) at the second site. Yet, despite the equities of the matter superficially weighing in favor of Relyant for having had some units accepted, we find that we cannot grant it the relief

1 We granted summary judgment in favor of the government in the related appeal of ASBCA No. 58172. See Relyant, LLC, ASBCA No. 58172, 16-1 BCA ,r 36,228, aff'd, 683 F. App'x 960 (Fed. Cir. 2017). Citations to the Rule 4 file herein refer to a single Rule 4 file that was originally submitted for that first appeal and later supplemented for this one. 2 To be clear, there was only one CO at a time on the contract. As noted, though, there was more than one COR. sought. The CO was within her rights to hold Relyant to the specifications contained within the contract's SOW, and the evidence does not support a finding of superior knowledge on the part of the government. Moreover, the doctrine of good faith and fair dealing does not override the express terms of the contract; however, in the circumstances presented here, it does impose upon the government certain obligations with regard to timeliness of government responses to Relyant's request to amend the SOW, for which Relyant is entitled to certain relief. 3

FINDINGS OF FACT

I. The Contract The idea behind the RLB is rather clever: standard sized steel shipping containers - ubiquitous in the modem world and designed to be easily transported - would be modified to be used as modular building blocks to make larger buildings for use in contingency operations (tr. 1/195-96, 201-04). On 15 May 2008, the Bagram Regional Contracting Center in Afghanistan (the Army or the government} solicited proposals for the above-captioned contract (the contract), which was a multiple award, indefinite-delivery/indefinite-quantity (IDIQ) contract for the manufacture, delivery, and installation ofRLBs in Afghanistan (R4, tab 1).

The seeds of the dispute that are now before us were sown in Relyant' s4 proposal in response to this solicitation. The SOW accompanying the solicitation for the contract required the installation of gypsum interior drywall to the interior of the shipping containers that would cover fiberglass insulation that was a minimum of three inches thick (R4, tab 1 at 17, 1 4.1.1.1 ). Relyant proposed a different configuration: this was the use of a sandwich panel, including Styrofoam5 as the insulator, instead of separate insulation and drywall (R4, tab 243 at 11-12 6 ; see also tr. 2/124-26). This configuration made all the difference in the world to how Relyant

3 We also resolve a number of motions regarding the entitlement of Relyant to amend its complaint; the government's entitlement to amend its answer; and whether an adverse inference should be drawn against the government due to certain discovery hiccups. Our decisions on those matters - granting, in large part, the motions to amend the complaint and the answer and denying the motion for an adverse inference -will be explained herein. 4 Critical Mission Support Services was Relyant' s predecessor in interest for this contract and, in fact, was the company that bid on and obtained this award (tr. 1/44). We, nevertheless, generally refer to it as Relyant, herein, for simplicity. 5 Relyant's Chief Executive Officer (CEO), Mr. Smith, testified that the insulating material in the sandwich panel was polystyrene, as opposed to Styrofoam (tr. 2/127). For our purposes, this is not a material difference. 6 These pages are numbered 8 and 9 in Rule 4, tab 248. 2 would manufacture the RLBs. Its single sandwich panel would be less likely to be damaged during shipping than the drywall/insulation combination (tr. 2/155), thus Relyant could install the sandwich panel at its factory in Turkey prior to shipping it to Afghanistan, rather than shipping the items separately and installing the drywall in Afghanistan (id., tr. 2/207). Indeed, the advantages of this method were key to Relyant's operations plan (see generally tr. 2/196, 206-07).

On 22 September 2008, the Army awarded the above-captioned contract (the contract)7 under the solicitation to Relyant (R4, tab 1 at 1). The contract signed by Relyant and the government did not adopt the change to the SOW proposed by Relyant relating to the substitution of the sandwich panel for the drywall and insulation interior walls (R4, tab 1), 8 although Relyant's management initially assumed that the proposal had been adopted (tr. 2/176). As will be seen, this assumption was unfortunate.

The contract incorporated by reference a number of standard clauses under the Federal Acquisition Regulation (FAR), including FAR 52.209-4, FIRST ARTICLE APPROVAL - GOVERNMENT TESTING (SEP 1989) (hereinafter, the first article test clause or FAT clause), with the words "Shall be incorporated in every delivery order" immediately following its notation (R4, tab 1 at 39). One provision of this FAT clause that is of importance to the dispute here is paragraph (b ), which provides in part, "The notice of... approval [of the test] shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of the contract."

Another contract provision that is important with respect to changes to the SOW is contained in paragraph 3.0 to the SOW portion of the contract, "Modifications," which provides that "[a]ll ... modifications to requirements specified in this SOW must be directed by the Contracting Officer (CO)" (R4, tab 1 at 15).

The contract also included the FAR's Ordering clause (FAR 52.216-18, ORDERING (OCT 1997)), which provides that, in the event of a conflict between a task order and the contract, "the contract shall control" (R4, tab 1 at 44).

7 Relyant was not the only awardee under this multiple award task order contract (tr. 1/45-46). 8 Relyant's proposal was written in such a way that the government was not required to accept its proposed deviation from the solicitation's SOW (tr. 2/175). 3 II. Delivery Order 1

Delivery Order 1 (DO 1) was issued to Relyant on 22 September 2008 (R4, tab 4 ), the same day the contract was awarded. DO 1 required the delivery and installation of nine two-story RLBs to Forward Operating Base (FOB) Sharana, Afghanistan (Sharana) (id. at 1-2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Micron Technology, Inc. v. Rambus Inc.
645 F.3d 1311 (Federal Circuit, 2011)
Hynix Semiconductor Inc. v. Rambus Inc.
645 F.3d 1336 (Federal Circuit, 2011)
Helene Curtis Industries, Inc. v. The United States
312 F.2d 774 (Court of Claims, 1963)
Melka Marine, Inc. v. United States
187 F.3d 1370 (Federal Circuit, 1999)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Indiana Michigan Power Company v. United States
422 F.3d 1369 (Federal Circuit, 2005)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Gresham & Co. v. United States
470 F.2d 542 (Court of Claims, 1972)
Ling-Temco-Vought, Inc. v. United States
475 F.2d 630 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
Relyant, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/relyant-llc-asbca-2018.