Tanik Construction Company, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJune 7, 2022
DocketASBCA No. 62527
StatusPublished

This text of Tanik Construction Company, Inc. (Tanik Construction Company, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tanik Construction Company, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Tanik Construction Company, Inc. ) ASBCA No. 62527 ) Under Contract No. W911KB-14-D-0016 )

APPEARANCE FOR THE APPELLANT: B. Neal Ainsworth, Jr., Esq. Ainsworth Law Wasilla, AK

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Carl F. Olson, Esq. Engineer Trial Attorney U.S. Army Engineer District, Alaska

OPINION BY ADMINISTRATIVE JUDGE PROUTY

Before us is a government motion for summary judgment premised upon the fact that appellant, Tanik Construction Co., Inc. (Tanik) signed a release, waiving its rights to advance claims on the issues before us. Tanik does not dispute that it signed the release, but produces three affidavits that it says provides evidence that it signed the release only after being assured that it could still bring a later claim. Generally, extrinsic evidence of Tanik’s intent is forbidden from our consideration by the parol evidence rule, but there are exceptions to this rule, including fraud. Under the very forgiving standards that apply to raising disputed facts in opposing motions for summary judgment, Tanik has produced enough evidence to avail itself of this defense and avoid summary judgment.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

I. The Contract and Task Order

The United States Army Corps of Engineers (the Corps) awarded the above-captioned contract to Tanik on April 9, 2014 (R4, tab 50 at COE 447 1). It was a multiple award task order contract for performing sustainment, restoration, and modernization of various government facilities in Alaska (id. at COE 449).

1 The government-provided Rule 4 file is Bates numbered with the prefix “COE” appearing before a six-digit number that begins with zeroes. Here, we delete the unnecessary zeroes. A few months after the award of the contract, on September 25, 2014, the Corps awarded Task Order No. 0001 (the TO) to Tanik. The TO was for apron 2 improvements at the Coast Guard Station, Kodiak, Alaska. The amount of the TO was $5,738,047 and it had a completion date of October 1, 2015. (R4, tab 50 at COE 568, 574, 596)

The original scope of the TO required the asphalt apron to be milled by two inches prior to sealing cracks and resurfacing. (SUMF ¶ 2). 3

On October 2, 2014, Tanik entered a subcontract with Brechan Enterprises to perform the lion’s share of the work on the project, including the milling of the existing asphalt and the re-paving. The amount of this subcontract was $4,864,000. (R4, tab 48 at COE 338-39)

II. Along Comes a Differing Site Condition

A. Discovery of Paved-Over Metal Tie-Downs and Performance of a Survey to Determine Their Extent

On May 13, 2015, after performance of the TO had begun, Tanik informed the Corps that it had discovered metal tie-downs in the apron that had been paved over by a few inches of asphalt and would adversely affect its ability to mill the asphalt. Characterizing the existence of these hidden tie-downs as a differing site condition, Tanik proposed conducting a ground penetrating radar (GPR) survey to identify the locations of all such tie-downs. (See R4, tab 4 at COE 47-48)

The Corps agreed with Tanik that the use of GPR to localize the covered tie-downs and other metal obstructions was appropriate and issued bilateral contract Modification No. P00005 (Mod 5) on August 27, 2015 for Tanik to conduct such a GPR survey (R4, tab 23 at COE 109-10). Mod 5 paid Tanik $480,816 (id. at COE 110) and explicitly stated that it did not increase the time to conclude the contract (id. at COE 111). Finally, it included a “Closing Statement” providing that:

The contractor hereby accepts the foregoing adjustment as a final and complete equitable adjustment in full accord and satisfaction of all past, present and future liability originating under any clause in the contract by reason of the facts and circumstances giving rise to this modification.

2 An apron is a hard surface on an airfield for maneuvering and parking aircraft. 3 SUMF is short for the Statement of Undisputed Material Facts included in the government’s motion for summary judgment. Tanik disputes none of these proposed facts and even incorporates them, as a whole, by reference into its brief (see app. opp’n at 1), thus we treat them as conceded. 2 (id.).

On October 15, 2015, the Corps forwarded to Tanik’s president, Ms. Julie Jury, a proposed bilateral contract modification, P00006 (Mod 6), which would extend the time to complete the project (R4, tab 28 at COE 120-21). Ms. Jury executed Mod 6, which included no additional money, but extended the contract completion date by 91 days (R4, tab 29 at COE 123-24). Mod 6 also included identical release language to that in Mod 5 (id. at COE 124), but in her cover email forwarding the executed modification, Ms. Jury stated:

By signing this modification Tanik Construction in no way releases the COE for: Our upcoming (REA) Request for Equitable Adjustment for the discovery of additional tie downs (1825).

(R4, tab 28 at COE 120)

On February 26, 2016, Tanik provided the results of the GPR survey to the Corps (R4, tab 31 at COE 126).

B. The Parties Negotiate a Contract Change to Address the Tie Down Problem

Having reviewed the GPR survey results, on March 22, 2016, the Corps issued Request for Proposal (RFP) 004 to Tanik, soliciting a proposal for it to complete the apron repairs after a re-design of the project based on the survey results (see R4, tab 32 at COE 128-30). In particular, RFP 004 specified that it was for the removal of the following:

1. Ground rods 2. Tie-downs 3. Concrete with and without rebar 4. Unknown objects 5. Dowel bars in concrete that the contractor deems necessary to meet the revised grading plan

(id. at COE 128). Nothing in RFP 004 referred to compensation to Tanik for delay or other costs beyond the work specified above (see R4, tab 32).

Tanik responded to RFP 004 on April 18, 2016, and submitted a proposal seeking $1,685,015 for the work (R4, tab 33). On June 6, 2016, Tanik submitted to the Corps a revised proposal along with additional back-up information, now seeking $1,910,837 for the work (R4, tab 34 at COE 169, 171).

3 The parties engaged in negotiations (see R4, tab 39) and, on July 28 4, 2016, the Corps forwarded Modification No. P00008 (Mod 8) to Tanik for signature (R4, tab 40 at COE 230). Mod 8 included the five different removals noted above for RFI 004 and had other aspects, such as revising the contract to reduce the depth of the milling in certain locations and changes to the “striping” plan (see id. at COE 232). Mod 8 increased the contract price by $1,410,000 and added 640 days to the completion date, making it October 1, 2017 (id. at COE 233).

Mod 8 also included the following “Closing Statement” (which is identical to the “Closing Statements” in Mod 5 and Mod 6):

The contractor hereby accepts the foregoing adjustment as a final and complete equitable adjustment in full accord and satisfaction of all past, present and future liability originating under any clause in the contract by reason of the facts and circumstances giving rise to this modification.

(Id. at COE 233-34)

C. Tanik Expresses Unhappiness With the Mod 8 Release but Executes it Anyway

On August 1, 2016, Tanik’s project manager, Mr. William Jury, forwarded to the Corps a letter from its subcontractor, Brechan, expressing disagreement with a number of provisions in the proposed Mod 8 (R4, tab 41 at COE 235). In addition to many technical issues, Brechan’s letter expressed great displeasure with the “Closing Statement.” After referencing that statement, the letter continued:

This statement is totally inappropriate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
United States v. James C. Dunkel
927 F.2d 955 (Seventh Circuit, 1991)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
J. G. Watts Construction Co. v. United States
161 Ct. Cl. 801 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
Tanik Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/tanik-construction-company-inc-asbca-2022.