Cosmo Construction Co. v. United States

451 F.2d 602, 196 Ct. Cl. 463, 1971 U.S. Ct. Cl. LEXIS 17
CourtUnited States Court of Claims
DecidedNovember 12, 1971
DocketNo. 44-69
StatusPublished
Cited by14 cases

This text of 451 F.2d 602 (Cosmo Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cosmo Construction Co. v. United States, 451 F.2d 602, 196 Ct. Cl. 463, 1971 U.S. Ct. Cl. LEXIS 17 (cc 1971).

Opinion

Per Curiam

: This case was referred to Trial Commissioner Louis Spector with directions to prepare and file his opinion on the issues of plaintiffs’ motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 166 (c). The commissioner has done so in an opinion and report filed on January 14, 1971, wherein such facts as are necessary to the opinion are set forth. A request for review by the court was filed by defendant and the case has been submitted to the court on the briefs of the parties and oral argument of counsel.

[467]*467Since the court is in agreement with the opinion and recommendations of the commissioner, with modifications by the court, it hereby adopts the same, as modified, as the basis for its judgment in this case as hereinafter set forth. Therefore, the cross-motions of the parties are allowed in part and denied in part as set forth in the “Conclusions of Law” hereto, with judgment entered accordingly.

Commissioner Spector’s opinion, as modified by the court, is as follows:

The petition herein sets forth four causes of action based on contract. Each seeks judicial review of adverse decisions (ENGBCA Nos. 2785, 2786, 2787, and 2788,67-2 BCA ¶ 6516) of the Department of the Army Corps of Engineers Board of Contract Appeals on contractor’s four separate appeals filed under the standard “Disputes” clause contained in the contract.1

By contract dated February 23,1962, Cosmo Construction Company (hereinafter for convenience “plaintiff” or “Cosmo”), undertook the construction of “flood protection works” for the United States acting through its Army Corps of Engineers, along the Kansas Eiver and Shunganunga Creek near Topeka, Kansas.

A more detailed description of the work reads: “construction of channel, pumping plant, drainage structures, relief wells, piezometers, and levee embankment, which includes, clearing and grubbing, stone slope protection, surfacing of levee crown, and seeding * * It is a fixed price contract consisting of a unit price schedule of 63 items listing estimated quantities and unit prices. The total estimated contract price at time of award was $2,268,565.

The contract was to be completed within 700 days of a notice to proceed received on March 23, 1962, and this has been extended by 57 days for changes ordered by defendant, and an additional 144 days for delays acknowledged by defendant to be excusable. The work was completed and accepted by defendant on January 19,1965.

[468]*468First Cause of Action — The Clwmged, Conditions Claim

In a claim letter of July 29, 1966, setting forth a number of disputed items which arose during prosecution of the work, plaintiff summarized his claim of “Changed Conditions”2 encountered “in the excavation area from station — (1+76) to station 85 + 00.” The letter stated that the contract plans indicated that substantially all the material excavated from the area in question would be suitable for use in the planned embankments either adjacent to the point of excavation or within a minimum haul distance therefrom. This was the basis for plaintiff’s bid, and was discussed with the Government’s representatives. In contrast “all or substantially all of the excavated material was determined to be not satisfactory for embankments by the authorized representative of the Contracting Officer and placement of the material in waste areas was directed. The placement of the excavated material in waste areas resulted in a much longer haul and greatly increased the cost of performing the excavation and disposal over what would have been experienced had the material been satisfactory as indicated.”

Plaintiff also alleged that its inability to use excavated material for embankment required it to obtain new material from borrow pits located some distance away. All of these circumstances greatly increased the cost of this phase of the work, and plaintiff presented an exhibit showing overhaul of 65,483 yard-miles from excavation area to waste area, and overhaul of 336,000 yard-miles in transporting new material from borrow pits to embankment, plus the cost of 250,108 cubic yards of borrow material. The total claim alleged was in the amount of $216,236.07, with the related time adjustment claim to be held in abeyance, pending determination of other time adjustment claims to be later discussed. (See Fourth Cause of Action, intra.)

On June 17, 1966, the contracting officer denied the claim on the grounds “that the Government lacked timely notice, [469]*469actual or constructive, of the asserted changed conditions except at station 75+00, and that the Government has been prejudiced by your failure to give the required timely notice.” He continued: “I have not considered the merits of the claim, except as it pertains to conditions in the vicinity of station 75+00. This decision is not to be construed as a denial of the claim on its merits except as to the conditions in the vicinity of station 75+00.” His adverse decision was duly appealed to the 'Chief of Engineers who is represented in these matters by a Board of Contract Appeals.

On appeal, the board observed:

Prior to hearing, the Government moved that we first hear and determine the question of lack of notice before hearing the dispute on its merits. We declined to do so because our review of the file convinced us that we would have to take extensive evidence as to the nature of the claim in order to resolve the notice question and that as a practical matter we should take evidence on the merits of the claim even though we might not reach that issue. The hearing was condumted on that basis. We did not hear the question of quantum, but of course we did receive evidence on quantities of suitable, wasted and wet materials anticipated and encountered since they have a bearing on whether or not there was a changed condition. [Emphasis supplied.]

The foregoing is quoted with appropriate emphasis because it illustrates what this dispute is all about. It is, of course, customary to hear a case such as this on the merits (i.e., the issue of liability), separate and apart from and prior to the issue of quantum, because the latter issue may be rendered academic if liability is not found to exist. If, on the other hand, liability is found, the issue of quantum is thereafter examined by less formal procedures. Our Rule 131(c) “Separate Determination of Liability,” for example, typifies that customary practice when a trial is conducted in this court.

Of course, evidence on damages or quantum is not totally excluded, because there must be some evidence of damage to support a finding on liability.3 But that limited evidence on [470]*470damages is not of the quantity, quality, or precision necessary to support a judgment in a precise sum; it is only sufficient to demonstrate that the issue of liability is not purely academic; that some damage 'has been incurred.

That customary course of procedure is clearly programmed in the 'above quoted portion of tbe board’s opinion. Unfortunately, it was not followed in tbe remainder of tbe decision. Plaintiff alleges that it was lulled into presenting only that minimal evidence on quantum sufficient to show that there was in fact a changed condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CiyaSoft Corporation
Armed Services Board of Contract Appeals, 2018
Tektel, Incorporated v. United States
121 Fed. Cl. 680 (Federal Claims, 2015)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
Scott Timber, Inc. v. United States
86 Fed. Cl. 102 (Federal Claims, 2009)
Energy Northwest v. United States
69 Fed. Cl. 500 (Federal Claims, 2006)
Consumers Energy Co. v. United States
65 Fed. Cl. 364 (Federal Claims, 2005)
System Fuels, Inc. v. United States
65 Fed. Cl. 163 (Federal Claims, 2005)
Entergy Nuclear Indian Point 2, LLC v. United States
64 Fed. Cl. 515 (Federal Claims, 2005)
Entergy Nuclear Generation Co. v. States
64 Fed. Cl. 336 (Federal Claims, 2005)
Boston Edison Co. v. States
64 Fed. Cl. 167 (Federal Claims, 2005)
Scott Timber Co. v. United States
64 Fed. Cl. 130 (Federal Claims, 2005)
Teledyne Lewisburg v. The United States
699 F.2d 1336 (Federal Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
451 F.2d 602, 196 Ct. Cl. 463, 1971 U.S. Ct. Cl. LEXIS 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cosmo-construction-co-v-united-states-cc-1971.