Balboa Insurance v. United States

31 Cont. Cas. Fed. 71,682, 3 Cl. Ct. 543, 1983 U.S. Claims LEXIS 1593
CourtUnited States Court of Claims
DecidedOctober 24, 1983
DocketNo. 295-82C
StatusPublished
Cited by6 cases

This text of 31 Cont. Cas. Fed. 71,682 (Balboa Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balboa Insurance v. United States, 31 Cont. Cas. Fed. 71,682, 3 Cl. Ct. 543, 1983 U.S. Claims LEXIS 1593 (cc 1983).

Opinion

OPINION

SPECTOR, Senior Judge.

Defendant has moved to dismiss plaintiff’s complaint under Rule 12(b)(4) on the grounds that it fails to state a cause of action upon which relief can be granted. The complaint alleges breach of plaintiff-surety’s “takeover” agreement with the United States which was entered into following default of a Government construction contractor bonded by plaintiff-surety.

Facts as Pleaded 1

On December 13, 1976, the Federal Aviation Administration (FAA) entered into a contract with the Small Business Administration as prime contractor, and Southwest Construction Company as subcontractor, for construction of an airport surveillance radar facility to be located at Standiford Field, Louisville, Kentucky. Plaintiff executed a performance bond as surety warranting Southwest’s performance.

By letter dated April 28, 1977, the FAA terminated the right of Southwest to proceed on the project by reason of nonperformance. On the same day, the FAA made a demand upon plaintiff to complete the project in accordance with its bond. Thereafter, on May 19, 1977, the FAA and plaintiff entered into a surety “takeover” agreement under which the latter undertook to complete the remainder of the work.

The takeover agreement provides in pertinent part that:

[The] FAA agrees to pay the sum of $69,106.00, representing the contract balance retained on said project to surety in accordance with the terms of the original contract between FAA and Southwest Construction Company had there not been a default. Said payments are to be made directly to the completion contractor specified by surety after approval of all said payments by surety.

On the same day plaintiff entered into a contract with Milton Contracting Company to complete the actual work on the project on plaintiff’s behalf. Milton subsequently assigned its right to payment under its contract with plaintiff to the Action Capital Corporation, and plaintiff received notice of that assignment.

In the latter part of May or early June 1977, Milton began performance on its completion contract, and in June 1977, Milton submitted a progress payment request to plaintiff-surety in the amount of $36,000. This payment request was forwarded to the FAA on June 16,1977, and plaintiff’s representative directed the FAA contracting officer to make the payment to Milton Construction Co., in care of Action Capital Corp. The FAA, contrary to plaintiff’s direction, made this progress payment directly to Milton. Subsequent payments under the contract were, however, made care of Action Capital, as plaintiff had specified and directed.

[545]*545Action Capital sued plaintiff for payment of the money which the FAA had paid directly to Milton. In that case, a jury rendered a verdict in favor of Action Capital in the amount of $33,296, plus interest, and that judgment was affirmed on appeal.2 Balboa now seeks to recover from the United States its compensatory and consequential damages, including the cost of defending itself on the claim brought against it by Action Capital.

Discussion

As a general rule, a motion to dismiss for failure to state a claim is viewed with disfavor and should rarely be granted.3 Therefore, the question is whether in the light most favorable to plaintiff and with every doubt resolved in plaintiff’s behalf, the complaint states any claim for relief.4 A motion brought under Rule 12(b)(4) should be denied “unless it appears beyond a doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.”5

Accordingly, defendant argues the “plain meaning” rule of contractual interpretation, namely, that if a writing appears clear and unambiguous on its face, its meaning must be determined from the four corners of the instrument without resort to extrinsic evidence of any kind.6 That rule would exclude the use of parol evidence relating to events prior to or contemporaneous with the formation of an integrated contract in determining the meaning of contractual terms unless those terms are inherently ambiguous and subject to more than one reasonable interpretation. Defendant then focuses on the specific language in the takeover agreement to the effect that payments shall be made “directly to the completion contractor specified by surety after approval of payments by surety.” As argued by defendant, this portion of the takeover agreement unambiguously requires the FAA to pay the completion contractor directly. Consequently, it is argued, the Government had the right to ignore plaintiff’s directions to pay Milton “care of” Action Capital. It is noteworthy, as related above, that subsequent payments were in fact made in accordance with those directions, that is, in “care of” Action Capital, and there is no dispute with respect to those subsequent payments.

Plaintiff responds with the argument that it was reasonable to interpret the payment provision to require the FAA to pay the plaintiff, as the party to the takeover agreement, or whomever the plaintiff specifies, following plaintiff’s approval of the payment; that its approval was conditioned upon payment to Milton, “care of” Action Capital. Observing that the overriding purpose in construing a contract is to arrive at an interpretation which will give effect to all of the contractual terms,7 plaintiff states as follows:

[546]*546In this case, ignoring the phrase “ * * * specified by surety (Balboa) after approval of all said payments by surety,” cannot be justified. The first sentence of the clause quoted above establishes that the right to receive payment under the contract belongs solely to Balboa. The last sentence of the clause deals only with the manner of payment under the contract. The wording of the sentence recognizes the proprietary interest of Balboa in the funds to be disbursed by the FAA and preserves Balboa’s right to control such disbursements. Under the contract, Balboa has an absolute right to receive payment from the FAA, “in accordance with the terms of the original contract between the FAA and Southwest Construction had there not been a default.” It would be inconsistent with this right to construe the very next sentence of the contract as giving the FAA the power to disregard completely Balboa’s request regarding manner of payment. Moreover if, as the FAA contends, the FAA could only make payment to the “completion contractor,” and only the FAA could determine who the “completion contractor” is, then the phrase “ * * * specified by surety after approval by surety” is rendered meaningless surplusage.

In accordance with the contract, plaintiff had “specified” Milton, care of Action Capital. In determining “whether a reasonable man could attach [that meaning] to the manifestation,”8 the course of performance under the contract may be considered. The fact that plaintiff interpreted the contract as authorizing it to specify that payment could be made to Action Capital, and the fact that all subsequent payments were in fact made to Action Capital, is evidence that reasonable persons could attach varying interpretations to the provision, including that intended by plaintiff. It is argued, moreover, that the “plain meaning” rule applies only to integrated contracts, or integrated portions thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duncan v. United States
22 Cl. Ct. 1 (Court of Claims, 1990)
Ainsley v. United States
8 Cl. Ct. 394 (Court of Claims, 1985)
Standard Manufacturing Co. v. United States
32 Cont. Cas. Fed. 73,131 (Court of Claims, 1984)
Anderson v. United States
5 Cl. Ct. 573 (Court of Claims, 1984)
Alexander v. United States
5 Cl. Ct. 57 (Court of Claims, 1984)
Adams v. United States
3 Cl. Ct. 696 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,682, 3 Cl. Ct. 543, 1983 U.S. Claims LEXIS 1593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balboa-insurance-v-united-states-cc-1983.