SCM Corp. v. United States

675 F.2d 280, 29 Cont. Cas. Fed. 82,334, 230 Ct. Cl. 199, 1982 U.S. Ct. Cl. LEXIS 154
CourtUnited States Court of Claims
DecidedMarch 24, 1982
DocketNo. 141-80C
StatusPublished
Cited by28 cases

This text of 675 F.2d 280 (SCM Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SCM Corp. v. United States, 675 F.2d 280, 29 Cont. Cas. Fed. 82,334, 230 Ct. Cl. 199, 1982 U.S. Ct. Cl. LEXIS 154 (cc 1982).

Opinions

KASHIWA, Judge,

delivered the opinion of the court:

This suit, brought under the Contract Disputes Act of 1978, is before the court on cross motions for summary judgment. At issue is the interpretation of the royalty provision of a contract between the plaintiff, the Kleinsch-midt division of SCM Corporation (SCM), and the Government. After careful consideration of the parties’ submissions and after oral argument, we deny plaintiffs motion for summary judgment, grant in part defendant’s motion for summary judgment, and remand the remainder of the case to a trial judge for further determination.

During the mid-1960’s, the Department of the Army embarked on a program to replace its obsolete electromechanical teletypewriter field equipment with an electronic teletypewriter using modern solid state techniques.1 The [201]*201Government awarded a contract for the development of a forward area tactical teletypewriter (FATT) to the plaintiff. This contract, not in issue here, was divided into two phases. Phase I required delivery of the FATT while Phase II gave the Government an option to require plaintiff to complete an advanced production engineering (APE) effort to further develop the FATT and an option to use the technical data developed as a result.

The Government exercised the APE option. Part of this option required delivery of a technical data package (TDP) composed of engineering drawings of FATT test models. The cost of the right to use this data was covered in a second contract, Contract No. DAABO7-71-C-0294, at issue here.

This contract granted the Government a license with respect to background data and inventions owned by the plaintiff which were part of the TDP. It provided for an initial payment of $1 million upon the acceptance of the TDP. The TDP was accepted by the Government and the $1 million paid to SCM. The contract also provided for payment of royalties on the following basis:

In addition to the sum set forth in the preceding paragraph of this ARTICLE, Royalties shall accrue under this CONTRACT in favor of CONTRACTOR, upon the utilization of the TDP in whole or in part for the procurement of FATT Systems, or parts thereof, other than those furnished by CONTRACTOR, licensed under this CONTRACT and accepted by the Department of the Army, and embodying the background data supplied under the APE contract. Royalty payments will be made in accordance with the following schedule:
6% on the first Thirty Million Dollars ($30,000,000.00) procurement
4% on the next Thirty Million Dollars ($30,000,000.00) procurement
2% thereafter.

It is the interpretation of this provision that is in dispute.

After its acceptance of the TDP, the Army conducted its own modernization program of the FATT design and developed what has become known as the "smart FATT.” The "smart FATT” made improvements upon SCM’s FATT design. The Government then awarded a contract to [202]*202Honeywell Incorporated for production of "smart FATT’s.” Subsequently, Honeywell made its own changes upon the FATT design.

. On May 18, 1979, plaintiff sent defendant an invoice requesting payment of royalties allegedly due under provision VI C 2 of the contract in the amount of $187,403.24. This amount was derived by applying 6 percent to the total cost as of that date of the Honeywell procurement. The Government refused to pay this amount, contending plaintiffs interpretation of Article VI C 2 was erroneous. It contends royalties should be paid only on that portion of the procurement which "embod[ies] the background data supplied under the APE contract.” The Government believes it owes the plaintiff $13,768.78 in royalty payments.

The parties rely upon the following provisions of the contract:

ARTICLE I. DEFINITION
* * * * *
B. "FATT System” is defined as any one or combination of the several components now denominated as the AN/UGC-72 ( ) V Teletypewriter Distributor-Transmitter; AN/UGC-73 ( ) V Teletypewriter Reperforator; AN/UGC-74 ( ) V Teletypewriter Page Printer with Keyboard; AN/UGC-75 () V Teletypewriter Tape Relay and Preparation Set; AN/UGC-76 ( ) V Teletypewriter Automatic Send-Receive Set, or any improved version of any one of these which embodies any background data with respect to items developed at private expense and submitted by CONTRACTOR in accordance with ARTICLE IV herein and the provisions of the APE contract, and which data has been accepted by the GOVERNMENT. "FATT System” shall not include equipment such as radio communication transmitting, receiving, relay or terminal equipment, telephone lines or cables or the like electrical signal equipment for transmission to, from and between teletype stations.
ARTICLE VI. PAYMENT
* * * * *
C. The GOVERNMENT, in consideration for this CONTRACT for RELEASE AND LICENSE FOR MANUFACTURING RIGHTS, PRIVATELY OWNED RIGHTS, DATA AND PATENTS, shall, subject to the provisions and limitations expressed in SUB-ARTICLES A, B, D, E [203]*203and F of this ARTICLE, make payment to the CONTRACTOR in accordance with the following:
1. Initial Payment: Upon delivery and acceptance of the TDP under the APE contract for competitive procurement of the FATT System, in whole or in part, employing background data delivered and accepted in accordance with ARTICLE IV herein, One Million Dollars ($1,000,000.00) shall be due CONTRACTOR, and the GOVERNMENT shall within thirty (30) days of such issuance give notice to CONTRACTOR to submit the certified invoice called for by SUB-ARTICLE VI-A above.
2. Royalty Payments: In addition to the sum set forth in the preceding paragraph of this ARTICLE, Royalties shall accrue under this CONTRACT in favor of CONTRACTOR, upon the utilization of the TDP in whole or in part for the procurement of FATT Systems, or parts thereof, other than those furnished by CONTRACTOR, licensed under this CONTRACT and accepted by the Department of the Army, and embodying the background data supplied under the APE contract. Royalty payments will be made in accordance with the following schedule:
6% on the first Thirty Million Dollars ($30,000,000.00) procurement
4% on the next Thirty Million Dollars ($30,000,000.00) procurement
2% thereafter.
ARTICLE VII. REPORTING AND PAYMENT OF ROYALTIES
The U. S. Army Materiel Command or the installation thereunder designated to administer this CONTRACT shall, on or before the 60th day next following June 30 and December 31 of each calendar year during which royalties have accrued under this CONTRACT in accordance with ARTICLE VI, deliver to CONTRACTOR a report in writing stating the number of FATT Systems, or parts thereof accepted by the Department of the Army during said year on which royalties have accrued under this CONTRACT.

I.

This court’s primary function in interpretation of contracts is to discern the parties’ intentions. Dynamics Corp. of America v. United States, 182 Ct. Cl. 62, 72, 389 F. 2d 424, 429 (1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)
Ohio Valley Health Services & Education Corp. v. Riley
149 F. Supp. 3d 709 (N.D. West Virginia, 2015)
United States v. Travelers Casualty & Surety Co. of America
55 F. Supp. 3d 852 (N.D. West Virginia, 2014)
Imprimis Investors LLC v. United States
83 Fed. Cl. 46 (Federal Claims, 2008)
Federal Group, Inc. v. United States
67 Fed. Cl. 87 (Federal Claims, 2005)
Bechtel National, Inc. v. Roche
65 F. App'x 277 (Federal Circuit, 2003)
P.R. Burke Corp. v. United States
47 Fed. Cl. 340 (Federal Claims, 2000)
Gambino v. United States
47 Fed. Cl. 275 (Federal Claims, 2000)
Landmark Land Co. v. United States
46 Fed. Cl. 261 (Federal Claims, 2000)
ECC International Corp. v. United States
43 Cont. Cas. Fed. 77,452 (Federal Claims, 1999)
Roy v. United States
38 Fed. Cl. 184 (Federal Claims, 1997)
Rockwell International Corp. v. United States
39 Cont. Cas. Fed. 76,651 (Federal Claims, 1994)
W.D.C. Carthage Associates v. United States
37 Cont. Cas. Fed. 76,252 (Court of Claims, 1991)
Gresham, Smith & Partners v. United States
37 Cont. Cas. Fed. 76,247 (Court of Claims, 1991)
Solar Turbines, Inc. v. United States
37 Cont. Cas. Fed. 76,092 (Court of Claims, 1991)
Town of Port Deposit v. United States
36 Cont. Cas. Fed. 75,910 (Court of Claims, 1990)
Western Empire Constructors, Inc. v. United States
36 Cont. Cas. Fed. 75,878 (Court of Claims, 1990)
Craft Machine Works, Inc. v. United States
36 Cont. Cas. Fed. 75,861 (Court of Claims, 1990)
Seaboard Lumber Co. v. United States
19 Cl. Ct. 310 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
675 F.2d 280, 29 Cont. Cas. Fed. 82,334, 230 Ct. Cl. 199, 1982 U.S. Ct. Cl. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scm-corp-v-united-states-cc-1982.