Craft Machine Works, Inc. v. United States

36 Cont. Cas. Fed. 75,861, 20 Cl. Ct. 355, 1990 U.S. Claims LEXIS 181, 1990 WL 57612
CourtUnited States Court of Claims
DecidedMay 4, 1990
DocketNo. 634-88C
StatusPublished
Cited by1 cases

This text of 36 Cont. Cas. Fed. 75,861 (Craft Machine Works, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Craft Machine Works, Inc. v. United States, 36 Cont. Cas. Fed. 75,861, 20 Cl. Ct. 355, 1990 U.S. Claims LEXIS 181, 1990 WL 57612 (cc 1990).

Opinion

OPINION

NETTESHEIM, Judge.

This case is before the court after argument on cross-motions for summary judgment. The principal dispute between the parties is whether the term “supplies”, as used in the Cargo Preference Act of 1904, 33 Stat. 518 (1904) (current version at 10 U.S.C. § 2631 (1988), and implementing regulation, 48 C.F.R. § 52.247-64 (1986), is limited to “end items” or covers end items and their component parts.

On March 7, 1990, this court issued an unpublished opinion granting defendant’s motion for summary judgment based on the plain meaning of the contract. Since plaintiff’s claim had been pleaded as a sev-[356]*356erable cause of action (Count I pleading a unilateral change to the contract), the grant of defendant’s motion was not final and was subject to RUSCC 54(b). The opinion explained that the court was unable to resolve the parties’ contentions, in the alternative, concerning patent and latent ambiguities in the contract because of disputes as to genuine issues of material fact. Most of the briefing and exhibits were devoted to the issue of ambiguity. However, since the cross-motions joined on the issue of the plain meaning of the contract, the decision was based on this ground. Although the plain meaning of the contract was dispositive, the court exercised its discretion to require the declarants to testify pursuant to RUSCC 43(c). The percipient witnesses’ testimony concerning an alleged ambiguity spoke to events occurring over four years ago. The goal was to complete a timely record at the trial level resolving all disputed issues of fact relating to contract interpretation. Finally, the opinion explained that a ruling was issuing on one issue, plain meaning, in order to limit depositions.

Plaintiff moved for reconsideration, and defendant agreed with plaintiff’s position, arguing that requiring the declarants to testify was too expensive, given the alternative to enter judgment for defendant on the issue of the contract’s plain meaning. The court defers to the parties’ wishes. The following opinion includes the court’s earlier unpublished ruling and also identifies the factual disputes that prevented adjudication of the ambiguity issue.

FACTS

The following facts are undisputed. Craft Machine Works, Inc. (“plaintiff”), a Virginia-based manufacturer of heavy machinery, entered into a two-step, multi-year supply contract with the Naval Facilities and Engineering Command of the Department of the Navy (“NAVFAC”). Under the two-step procedure, bidders whose technical proposal was found acceptable in the first step of the procurement, were invited to submit fixed-priced bids on the design, fabrication, delivery and installation of 23 portal cranes. The portal cranes were destined for use at various naval shipyards throughout the United States. Plaintiff was awarded contract N62472-82-C-1455 on or about February 21, 1986. This five-year firm fixed-price contract was for the sum of $73,709,013.00, with $19,971,248.00 obligated in the first program year.

Following the formation of its agreement with NAVFAC, plaintiff subcontracted with Clyde Crane Division (“Clyde”), a Division of AMCA International, now renamed AmClyde Engineered Products (“AmClyde”).1 Plaintiff contracted with AmClyde for the design, manufacture, and delivery to plaintiff’s Hampton Roads, Virginia facility of the 23 portal cranes. Under the subcontract the cranes were to be delivered to the Hampton Roads facility in major subassemblies. The Craft-AmClyde agreement of May 29, 1986, included quotations totaling $57,499,350.00. AmClyde’s subcontract incorporated by reference the “Preference for Privately-owned U.S.-Flag Commercial Vessels — Alternate I,” as found at 48 C.F.R. § 52.247-64 (1986).

AmClyde, in turn, subcontracted with Hyundai Heavy Industries Ltd., a Hyundai Corporation (“Hyundai”), for fabrication of substantially all of the cranes’ major structural components. Per an agreement dated October 31, 1986, Hyundai agreed to fabricate many of the individual crane parts at its facilities in the Republic of Korea.

Following the agreements between plaintiff and AmClyde and between AmClyde and Hyundai, AmClyde solicited quotations from a variety of shipping firms to transport completed components from Korea to plaintiff’s facilities in the United States. One of the firms solicited was Mammoet Shipping, B.V. (“Mammoet”), a foreign-flag carrier. Mammoet submitted a quotation to AmClyde of $95.00 per cubic meter for shipment of cargo from Korea to Hampton Roads, Virginia.

[357]*357The Cargo Preference Act of 1904, 33 Stat. 518 (1904) (current version at 10 U.S.C. § 2631 (1988)) (the “Act”), regulates the use of foreign-flag ocean carriers on military contracts. The Act provides, in pertinent part:

Only vessels of the United States or belonging to the United States may be used in the transportation by sea of supplies bought for the Army, Navy, Air Force, or Marine Corps____

The Federal Acquisition Regulation (“FAR”) implementing the Act, 48 C.F.R. § 52.247-64, required the insertion of this clause into plaintiff’s contract:

(a) Except as provided in paragraph (b) below, the contractor shall use privately owned U.S.-flag commercial vessels, and no others, in the ocean transportation of any supplies to be furnished under this contract.
(b) If such vessels are not available for timely shipment at rates that are fair and reasonable for privately owned U.S.-flag commercial vessels, the Contractor shall notify the Contracting Officer and request (1) authorization to ship in foreign-flag vessels or (2) designation of available U.S.-flag vessels. If the Contractor is authorized in writing by the Contracting Officer to ship the supplies in foreign-flag vessels, the contract price shall be equitably adjusted to reflect the difference in costs of shipping the supplies in privately owned U.S.-flag commercial vessels and in foreign-flag vessels.
(d) Except for small purchases as described in 48 C.F.R. 13, the Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts, or purchases under this contract.

Compliance with the requirements for use of U.S.-flag vessels is monitored by requiring the contractor to submit bills of lading which identify, among other items, the flag of registry for vessels making shipments which originate outside of the United States. FAR § 54.247-64(c)(2).

The term "supplies” is defined in a FAR section dedicated to “words and terms commonly used in this regulation” as:

all property except land or interest in land.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Craft MacHine Works, Inc. v. The United States
926 F.2d 1110 (Federal Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,861, 20 Cl. Ct. 355, 1990 U.S. Claims LEXIS 181, 1990 WL 57612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/craft-machine-works-inc-v-united-states-cc-1990.