Design & Production, Inc. v. United States

35 Cont. Cas. Fed. 75,718, 18 Cl. Ct. 168, 1989 U.S. Claims LEXIS 181, 1989 WL 106521
CourtUnited States Court of Claims
DecidedSeptember 14, 1989
DocketNo. 553-84C
StatusPublished
Cited by19 cases

This text of 35 Cont. Cas. Fed. 75,718 (Design & Production, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Design & Production, Inc. v. United States, 35 Cont. Cas. Fed. 75,718, 18 Cl. Ct. 168, 1989 U.S. Claims LEXIS 181, 1989 WL 106521 (cc 1989).

Opinion

OPINION

HORN, Judge.

Plaintiff, Design and Production, Inc. (D & P), filed its complaint on October 26, 1984, pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982). The case was assigned to Judge Philip R. Miller. In its complaint, plaintiff alleges that defendant, through employees at the Department of Commerce, directed it to perform work outside the scope of the contract. Plaintiff has asked for an equitable adjustment in the contract price.

Prior to filing the complaint in this court, plaintiff submitted a certified, and then an amended certified claim, to the contracting officer on the contract and subcontract at issue in this proceeding. The contracting officer issued a final decision on February 1, 1985, after the complaint in this court had been filed. In his final decision, the contracting officer denied the plaintiff’s claim on the basis that all of the claimed additional work was within the scope of the original contract. Subsequent to the filing of pre-trial submissions, plaintiff moved for leave to file an amended complaint in order to clarify that it seeks recovery for all items mentioned in the amended certified claim, including for the amount of the subcontract with the J.A. Jones Construction Co. (Jones), plus overhead expenses and profit. Plaintiff’s motion was allowed by an Order of the Court issued, by Judge Miller, on May 16, 1986.

In the amended complaint filed in this court, plaintiff specifies portions of the work performed under the subcontract, which it alleges were outside the scope of its contract with the defendant, specifically to construct demising walls separating the pavilion theaters from adjoining queuing and exit hallways (“the theater walls”), installation of lighting in the theaters, application of acoustical spray to the walls and ceiling in the theaters, and to construct walls and ceilings in the queuing areas adjacent to the theaters. Plaintiff’s claim also includes recovery for the cost of the subcontractor’s work in constructing the ceiling and doing mechanical work in the projection booth and for installing speaker brackets in the theaters, as well as for insurance, bonds, and permits, purchased by the subcontractor in performance of the subcontract.

Soon after the contracting officer issued his final decision on plaintiff’s claim, defendant amended its answer in this court to include a counterclaim based on findings in the contracting officer’s final decision. In the counterclaim, defendant alleges that plaintiff failed to supply and install all of the electronic equipment that was called for in the contract. Defendant also alleges that plaintiff failed to fully perform the work agreed to in the contract for exhibit Areas Three and Eight and for the administrative area of the pavilion.

Plaintiff also added claims for additional costs to the subcontractor, namely claims for its own direct costs for construction of the theaters, including adjusted overhead, as audited by the Defense Contract Audit Agency (DCAA) and the agency adjusted amount for general and administrative expenses. Plaintiff also claims a ten percent profit on the contract.

The case was reassigned to Judge Marian Blank Horn. Subsequent to the reassignment, a one week trial was held, followed by extensive post-trial briefings.

After careful consideration of the facts and arguments presented by both parties at the trial and in their written submissions, the court finds, as is discussed more fully below, that the plaintiff is entitled to partial recovery on its claim, but that the defendant is not entitled to recovery on its counterclaim. Plaintiff is entitled to an equitable adjustment for work properly directed by authorized government officers, namely, the construction of the theater walls, some of the acoustical work, painting, installation of the hardware for the theater doors, and portions of the drywall [172]*172and ceiling work in the queuing and exit areas. Plaintiff is also entitled to compensation for the Insurance, Bonds and Permits and for general and administrative expenses and a reasonable profit, in accordance with this opinion. All other work for which plaintiff seeks recovery was either required under the contract provisions or was not ordered by an authorized government official.

The work and equipment for which defendant seeks recovery was either not required by the contract, was deleted from the contract requirements by an authorized representative of the government or defendant has failed to substantiate its claim during these proceedings.

I. BACKGROUND

In the fall of 1982, defendant, acting through the United States Department of Commerce (“Commerce”), solicited proposals to design, fabricate, install, and maintain exhibits for the United States Pavilion at the 1984 Louisiana World Exhibition in New Orleans. Plaintiff and others responded to the government’s solicitation. The defendant awarded the initial contract to Designgroup Division of Greyhound, Inc. (“Designgroup”). Shortly thereafter, De-signgroup’s contract was terminated for default.

After terminating the Designgroup contract, Commerce decided to reprocure the contract by awarding to the next lowest bidder, D & P. At a meeting on March 4, 1983, defendant authorized plaintiff to submit a sole source proposal for the project. On March 28, 1983, D & P submitted to Commerce its “sole source” proposal, which was a firm, fixed price proposal in the amount of $4,265,981, including a cost breakdown and conceptual design Summary-

Commerce did not award a contract in response to D & P’s sole source proposal because Designgroup, the first contractor awarded the original contract, filed a formal protest against exclusion from the competition for the reprocurement of the work. On the recommendation of legal counsel, the defendant, on May 4, 1983, issued á limited solicitation for competitive bids from Designgroup and from the plaintiff. This solicitation, No. SA-83-SPB-0011, was essentially the same as that issued in the fall of 1982. The difference was that in the second solicitation, the defendant omitted the previous requirement that the contractor provide the movie and projection equipment. Plaintiff submitted cost and technical proposals on May 18, 1983. Subsequently, in response to a request from Commerce on June 3, 1983, plaintiff revised the May 18,1983 proposals with additional submissions on June 4 and 6, 1983.

On June 7, 1983, defendant awarded to plaintiff the contract, No. TA-83-SAC-02240, which is at issue in this case. The contract incorporates the May 4, 1983 solicitation (with minor exceptions, namely Section A items 1, 2, 3, and 5), and also incorporates the plaintiff’s technical proposal, as revised. The contract also incorporates the “Changes” clause from Standard Form 32 (41 C.F.R. § 1-16.901-32, ¶ 2 (1983)), and the “Subcontractor Cost or Pricing Data” clause (41 C.F.R. § 1-3.814-3 (1983)). The cost proposal was not incorporated into the contract. The contract does incorporate by reference the Subcontracting Plan submitted by plaintiff as Section 4 of its cost proposal, dated May 18, 1983. The Subcontracting Plan, however, relates only to the participation of small businesses and small, disadvantaged businesses as suppliers and contractors under the contract. Plaintiff began work shortly after the award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Spectrum Sciences & Software, Inc. v. United States
98 Fed. Cl. 8 (Federal Claims, 2011)
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
Nelson Construction Co. v. United States
79 Fed. Cl. 81 (Federal Claims, 2007)
W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)
Ryco Construction, Inc. v. United States
55 Fed. Cl. 184 (Federal Claims, 2002)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
Ed. Zueblin, A.G. v. United States
44 Fed. Cl. 228 (Federal Claims, 1999)
Marathon Oil Co. v. United States
42 Fed. Cl. 267 (Federal Claims, 1998)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
Nicholson v. United States
29 Fed. Cl. 180 (Federal Claims, 1993)
Tri-O, Inc. v. United States
38 Cont. Cas. Fed. 76,521 (Federal Claims, 1993)
Elastomeric Roofing Associates, Inc. v. United States
26 Cl. Ct. 1106 (Court of Claims, 1992)
Boehm v. United States
37 Cont. Cas. Fed. 76,073 (Court of Claims, 1991)
Design & Production, Inc. v. United States
36 Cont. Cas. Fed. 75,844 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,718, 18 Cl. Ct. 168, 1989 U.S. Claims LEXIS 181, 1989 WL 106521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/design-production-inc-v-united-states-cc-1989.