American Western Corporation v. The United States

730 F.2d 1486, 32 Cont. Cas. Fed. 72,337, 1984 U.S. App. LEXIS 14883
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 28, 1984
DocketAppeal 83-1277
StatusPublished
Cited by13 cases

This text of 730 F.2d 1486 (American Western Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Western Corporation v. The United States, 730 F.2d 1486, 32 Cont. Cas. Fed. 72,337, 1984 U.S. App. LEXIS 14883 (Fed. Cir. 1984).

Opinion

SKELTON, Senior Circuit Judge.

This case involves the construction of a contract between the General Services Administration (GSA) and the American Western Corporation (appellant). On August 22, 1980, GSA awarded a requirements contract to appellant to supply polyethylene plastic bags for the Government for the period from August 22, 1980, to July 30, 1981. The contract contained an Economic Price Adjustment (EPA) clause which provided that the “price(s) of all items which are purchased under this contract are subject to price adjustment, upward or downward” based upon a formula contained in the clause. The clause provided that, while appellant had to submit a written request for a price adjustment upward, the Government could unilaterally obtain a price reduction. The clause did not fix a time for requesting an increase or for asserting a decrease in prices.

Subsequent to the award of the contract, the Government began placing purchase orders with appellant. After shipping these orders, appellant would submit invoices to the Government based on the original contract prices. All of the purchase orders issued under the contract were shipped, and the Government paid the final invoice on November 17, 1981.

On November 3, 1981, two weeks before the final payment was made, the contracting officer notified appellant that some of the bags shipped under the contract were defective and would have to be replaced under the terms of a Quality Approved Manufacturer’s Agreement between the parties. Negotiations ensued which ultimately resulted in a modification of the contract which was executed on May 10, 1982. This modification called for a refund of five percent of the contract price by appellant. Appellant remitted the money owed under the modification on June 18, 1982, and, in addition, offered $8,000 to settle for other defective bags discovered after November 3, 1981.

Prior to the contract’s official July 30, 1981, termination date, the price of PE resin — a raw material used in manufacturing polyethylene bags — declined to a point which entitled GSA to obtain a price reduction under the EPA clause. The Government failed to realize this at the time, however, and thus made final payment according to the original contract prices. On or about December 15, 1981, the GSA Inspector General notified the contracting officer that the Government could have obtained a price reduction under the EPA clause. The contracting officer decided to obtain a ret *1488 roactive price reduction by requesting a refund from appellant, and on December 31, 1981, GSA notified appellant of its intention to adjust the contract price downward. In a final decision dated March 17, 1981, the contracting officer demanded payment from appellant in the amount of $22,521.08. The appellant appealed to the GSA Board of Contract Appeals, which upheld the Government’s claim in a 2 to 1 decision.

Appellant initially contends that the Board erred in failing to find that the EPA clause is ambiguous with respect to the time in which the Government must assert its right to a decrease. Because of this alleged ambiguity, appellant argues that we must adopt its construction of the clause, i.e., that the Government may not claim a price reduction after full performance of the contract. We cannot accept appellant’s interpretation of the EPA clause because, after careful consideration, we fail to find any ambiguity in the contract. It very clearly states the relative rights of the parties in obtaining price adjustments, and establishes a formula for determining the amount of adjustment available. It merely fails to set a time limit within which the Government must claim a reduction in price. Omission of an express time provision does not of itself create an ambiguity.

Appellant points to certain provisions in the EPA clause that allegedly imply that price adjustments can be made only during the contract period. The clause states, for example, that the price indexes used to determine price adjustments shall be “the indexes for the third, sixth; and ninth succeeding months of the contract period.” This provision is directed to the method for determining the amount of adjustment. It clearly was not inserted for the purpose of establishing a time limit for asserting a price reduction and should not be given such an effect. We are unable to find any provision in the EPA clause which could reasonably be construed to impose a time limit on the Government for asserting its right to a price reduction. In the absence of such a time limit, the courts will imply a reasonable time. See, Nager Electric Co., Inc. v. United States, 177 Ct.Cl. 234, 368 F.2d 847, 864 (1966); Roberts v. United States, 174 Ct.Cl. 940, 357 F.2d 938, 946 (1966); Merritt-Chapman & Scott Corp. v. United States, 174 Ct.Cl. 250, 355 F.2d 622, 627 (1966).

The amici, American Transparents Plastic Corporation and Chicago Transparent Products, Inc., argue that final payment by the Government bars the assertion of a claim by either party to a Government contract. As authority for this proposition, the amici cite the cases of Gulf & Western Industries, Inc. v. United States, 226 Ct.Cl. 159, 639 F.2d 732 (1980), and Dubois Construction Corp. v. United States, 120 Ct.Cl. 139, 98 F.Supp. 590 (1951).

In Gulf & Western the contract contained a Changes clause which provided that the contracting officer could receive and act upon any claim asserted prior to final payment, if the facts justified such action. The court denied the contractor’s claim challenging defective specifications because the claim was not made until after final payment. The decision was clearly based upon the language in the Changes clause, which set forth an express time limit. This was also the case in Jo-Bar Mfg. Corp. v. United States, 210 Ct.Cl. 149, 535 F.2d 62 (1976), cited by the court in Gulf & Western.

In Dubois the Government’s counterclaim for defective work by the contractor was barred because it was not asserted until after full performance and final payment. The contract in that case contained a Disputes clause which required all disputes concerning questions of fact to be decided by the contracting officer. The court’s denial of the Government’s claim was clearly based upon the Government’s failure to follow the procedure set out in the Disputes clause.

The final payment rule enunciated in the above cases was predicated upon express contractual provisions. In the instant ease no such provisions are found in the agreement. The contract simply contains a pro *1489 vision allowing the Government to make a unilateral price adjustment, with no express time limit. In such case, the final payment rule does not apply. As the Court of Claims stated in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
730 F.2d 1486, 32 Cont. Cas. Fed. 72,337, 1984 U.S. App. LEXIS 14883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-western-corporation-v-the-united-states-cafc-1984.