Solar Turbines, Inc. v. United States

37 Cont. Cas. Fed. 76,092, 23 Cl. Ct. 142, 1991 U.S. Claims LEXIS 181, 1991 WL 77932
CourtUnited States Court of Claims
DecidedMay 14, 1991
DocketNo. 53-88C
StatusPublished
Cited by25 cases

This text of 37 Cont. Cas. Fed. 76,092 (Solar Turbines, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Solar Turbines, Inc. v. United States, 37 Cont. Cas. Fed. 76,092, 23 Cl. Ct. 142, 1991 U.S. Claims LEXIS 181, 1991 WL 77932 (cc 1991).

Opinion

OPINION

ANDEWELT, Judge.

In this government contract action filed pursuant to the Contract Disputes Act (CDA), 41 U.S.C. § 601, et seq., plaintiff, Solar Turbines, Inc. (Solar), seeks to recover costs and damages arising out of a contract with the Department of the Navy (the Navy). This case is presently before the court on defendant’s motion for summary judgment. For the reasons set forth below, defendant’s motion is granted in part and denied in part.

I.

The contract in dispute involves the design and production of a Rankine Cycle Energy Recovery (RACER) system for use on Navy gas-turbine powered ships. The RACER system uses waste heat recovered from gas turbine engines to drive a steam turbine. Through the capture and use of waste energy, the RACER system potentially can increase fuel efficiency and thereby increase the distance a ship can travel before having to refuel.

As originally awarded on September 30, 1981, the RACER contract (No. N00024-81-C-5340) was limited to the preliminary design of a RACER system. The contract subsequently was modified, however, to provide for full-scale engineering development, including designing, building, and testing RACER prototypes.

Congress placed the RACER project on an accelerated development schedule with the intent of using the RACER system on the new Burke class guided missile destroyer (the DDG-51 class) that was then being designed. By October 19, 1984, the RACER contract had been modified approximately 34 times. The numerous changes to the contract scope significantly increased Solar’s total estimated cost for completing the contract work.

[145]*145On December 28, 1984, Solar and the Navy entered into a “Memorandum of Understanding” (MOU), involving a series of additional modifications to the RACER contract. The parties agreed to convert the existing cost-plus-award fee contract into a cost-reimbursement contract with a $55 million limitation on government liability. In addition, the MOU provided that Solar would “design, fabricate, test and deliver three RACER units [Units # 1, # 2, and # 3].” The MOU further provided that “the understandings of the parties ... will be included in a formal contract modification.”

In April 1985, the parties entered such a formal contract modification on Standard Form 30 (SF 30). The modification, referred to in the documents and briefs as the P00037 modification, contained the $55 million ceiling and specified the obligations with respect to the three RACER units outlined in the MOU. Inter alia, the P00037 modification also granted the Navy an unpriced option to have Solar design and manufacture two additional RACER units (Units #4 and #5).

By November 1985, Solar’s costs on the RACER project approached the $55 million ceiling. In early November, Peter Carroll, Solar’s vice president, had a series of meetings with Navy personnel. Following these meetings, on November 8,1985, Solar notified the Naval Sea Systems Command (NAVSEA) in writing that it expected to have incurred $55 million in costs under the contract by November 18, 1985. Ultimately, Solar received the full $55 million in payments.

Thereafter, Solar continued work on the RACER project. In early 1986, Solar requested additional funds to cover the costs it had incurred above $55 million. The parties engaged in negotiations during April 1986, and on April 24, a senior Solar official and a Navy officer initialed a “Proposed Mutual Termination Modification” (PMTM). The PMTM provided that Solar would cease all contract work “as of the effective date of this contract modification,” except preparation of a settlement proposal under the termination clause of the contract. That settlement proposal would include, inter alia, costs that Solar incurred prior and subsequent to the effective date of the P00037 modification. The $55 million limitation would not bar payment of such costs if the costs were found otherwise to be valid either by the contracting officer or under the disputes procedures of the RACER contract.

The PMTM was never included in a formal contract modification. After negotiations failed, on May 8, 1986, 14 days after the initialing of the PMTM, David Boyer, the Navy’s procurement contracting officer, unilaterally terminated the RACER contract for convenience of the government. The termination letter took the position that pursuant to the P00037 modification, the Navy’s total liability under the contract, including liability for termination for convenience, was limited to $55 million. Thereafter, plaintiff filed a claim with the termination contracting officer in which it sought payments in excess of the $55 million ceiling. After its claim was denied, plaintiff filed the instant eight-count complaint. Defendant moves for summary judgment on each of the eight counts.

II.

The grant of summary judgment is appropriate where there is an absence of a genuine issue of fact and the moving party is entitled to judgment as a matter of law. RUSCC 56. Summary judgment is not “a disfavored procedural short cut, but rather ... an integral part of the Federal Rules as a whole, which are designed ‘to secure the just, speedy, and inexpensive determination of every action.’ ” Celotex Corp. v. Catrett, 477 U.S. 317, 327, 106 S.Ct. 2548, 2555, 91 L.Ed.2d 265 (1986) (quoting Fed.R.Civ.P. 1). See also, Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560, 1562 (Fed.Cir.1987). The summary judgment procedures of RUSCC 56, like their counterpart in Rule 56 of the Federal Rules of Civil Procedure, are designed to protect the legitimate interests of all parties to a law suit by permitting the efficient disposition of claims that lack a [146]*146sufficient basis. See Celotex, 477 U.S. at 327, 106 S.Ct. at 2555.

Under summary judgment procedures, the moving party has the burden of establishing the absence of any genuine issue of material fact. Adickes v. S.H. Kress & Co., 398 U.S. 144, 159-60, 90 S.Ct. 1598, 1609-10, 26 L.Ed.2d 142 (1970); see Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987). The moving party can initially discharge this burden by demonstrating an absence of evidence to support the nonmoving party’s case, i.e., the absence of evidence as to an essential element of the cause of action on which the nonmovant bears the burden of proof. Celotex, 477 U.S. at 322-25, 106 S.Ct. at 2552-53. When the moving party successfully discharges its initial burden in this way, the nonmovant cannot defeat summary judgment merely by alleging a dispute as to a material fact. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westlands Water District v. United States
109 Fed. Cl. 177 (Federal Claims, 2013)
Public Service Co. v. United States
91 Fed. Cl. 363 (Federal Claims, 2010)
Southern California Edison v. United States
58 Fed. Cl. 313 (Federal Claims, 2003)
Chambery v. United States
54 Fed. Cl. 2 (Federal Claims, 2002)
Coast-To-Coast Financial Corp. v. United States
52 Fed. Cl. 352 (Federal Claims, 2002)
Ft Sumter Tours Inc v. Babbitt, Bruce D.
202 F.3d 349 (D.C. Circuit, 2000)
Rosboro Lumber Co. v. United States
43 Fed. Cl. 606 (Federal Claims, 1999)
Allstates Air Cargo, Inc. v. United States
42 Cont. Cas. Fed. 77,391 (Federal Claims, 1998)
Northrop Grumman Corp. v. United States
42 Cont. Cas. Fed. 77,381 (Federal Claims, 1998)
Ebasco Services, Inc. v. United States
41 Cont. Cas. Fed. 77,082 (Federal Claims, 1997)
McDonnell Douglas Corp. v. United States
41 Cont. Cas. Fed. 77,046 (Federal Claims, 1997)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
Donahue v. United States
33 Fed. Cl. 600 (Federal Claims, 1995)
Ford v. United States
33 Fed. Cl. 560 (Federal Claims, 1995)
A Olympic Forwarder, Inc. v. United States
40 Cont. Cas. Fed. 76,788 (Federal Claims, 1995)
Lawrence E. Link v. Department of the Treasury
51 F.3d 1577 (Federal Circuit, 1995)
Gates v. United States
40 Cont. Cas. Fed. 76,753 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,092, 23 Cl. Ct. 142, 1991 U.S. Claims LEXIS 181, 1991 WL 77932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/solar-turbines-inc-v-united-states-cc-1991.