Muschany v. United States

324 U.S. 49, 65 S. Ct. 442, 89 L. Ed. 744, 1945 U.S. LEXIS 2612
CourtSupreme Court of the United States
DecidedFebruary 5, 1945
DocketNos. 31, 32
StatusPublished
Cited by357 cases

This text of 324 U.S. 49 (Muschany v. United States) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muschany v. United States, 324 U.S. 49, 65 S. Ct. 442, 89 L. Ed. 744, 1945 U.S. LEXIS 2612 (1945).

Opinions

Mr. Justice Reed

delivered the opinion of the Court.

Writs of certiorari were allowed to petitioners by this Court in these two cases to review the action of the Cir[51]*51cuit Court of Appeals for the Eighth Circuit.1 That appellate court reversed the action of the District Court of the Eastern District of Missouri which had upheld the validity of contracts between petitioners and the United States for the purchase of land for the Weldon Springs, Missouri, ordnance plant.2 The contracts were pleaded by petitioners as defendants in eminent domain suits to establish the proper condemnation award.

The petitions for certiorari were granted, 321 U. S. 760, because of asserted conflict with United States v. Grace Evangelical Church, 132 F. 2d 460. Jurisdiction of this Court rests on § 240 of the Judicial Code.

Under the authority of the Second Supplemental National Defense Appropriation Act of 1941, 54 Stat. 872, the President approved the Weldon Springs project on October 17, 1940. Pursuant to this approval, the War Department claims that it proceeded to acquire the necessary land under the act of July 2, 1917, 40 Stat. 241, as restricted by the National Defense Act of July 2, 1940, 54 Stat. 712. The statutory authority of the War Department to proceed as it did is not questioned except on the issue of whether the purchase contracts entered into in acquiring the needed land violate the first section of the act of July 2,1940, which provides:

“Provided further, That the cost-plus-a-percentage-of-cost system of contracting shall not be used under this section; but this proviso shall not be construed to prohibit the use of the cost-plus-a-fixed-fee form of contract when such use is deemed necessary by the Secretary of War.” 54 Stat. 713.

The duty to act for the War Department in obtaining the land lay in the office of the Quartermaster General and specifically in the Real Estate Branch of that office. In an effort to expedite the acquisition of the needed land, [52]*52the head of that branch, Colonel R. D. Yalliant, contracted, with R. Newton McDowell to act as the agent for the Government in securing options, on forms approved by the United States and attached to the employment contract, from the owners for submission, to and acceptance by the United States. Mr. McDowell’s compensation for acting as agent was a “five per cent (5%) commission . . . to be paid by the vendor.” 3

The employment of McDowell as agent to secure options for the United States was confirmed by the War Department to the Citizens Committee, an informal organization of those who owned property which was needed for the proposed project. McDowell went to work to [53]*53carry out his contract. He held meetings at which he explained to the landowners the plan to secure options and the option form itself. From his explanation the landowners must have understood that their sale price would have deducted from it McDowell’s commission and other expenses. This was also the understanding, of the Government, as is shown not only by the documents themselves which were approved by the Government but also specifically by the testimony of Colonel Yalliant. While McDowell was employed and his commission set by the Government, it was arranged that McDowell should collect his money from the vendor so that a single voucher would cover the purchase price and the expenses.

The approved form of option, which was a part of McDowell’s contract with the Government, was used by McDowell in the particular transactions which are under examination in these proceedings. The option accords with the requirements of the McDowell contract and in addition provides for an agreed valuation at the option price in case of condemnation.4 The offer was accepted by the Government.

[54]*54There were a large number of landowners in the required area. Options were obtained from 270, including the petitioners, and with one exception the options were accepted by the Government at the optioned price. Almost half of the contracts were closed by acceptance of deeds and payment of the price. Criticism of the prices and manner of purchase developed and the War Department repudiated the remaining contracts and turned to condemnation. The repudiation followed upon the conclusion among other things that the contracts violated the statutory provision against the cost-plus-a-percentage-of-cost system of contracting, page 52, supra, and were contrary to public policy because of the contingent interest of McDowell, which was antagonistic to the Government.

Petitioners’ options were among those accepted only to be repudiated later, the Government then instituting condemnation proceedings to obtain petitioners’ lands. In the two condemnation proceedings instituted against petitioners, judgments were entered upon a declaration of taking which vested titles in the United States. 46 Stat. 1421. Thereafter the petitioners here filed their answers in which they consented to the condemnation and demanded that the price which was fixed in the option, accepted by the Government, be adopted by the trial court as just compensation. In reply the Government set up its repudiation of the contracts on numerous grounds including fraud, such unfairness to the Government because of gross overvaluation that the contract should not be enforced in equity and good conscience as well as the disregard of the statutory proscription and public policy, which was referred to in the preceding paragraph as the ground for repudiation.

The two' cases were decided in favor of the validity of the contracts and the compensation was fixed at the price [55]*55stated in the contract without revaluation. Consequently there was no occasion for the trial courts to determine whether valuation measured by just compensation would have varied from the agreed price. The Government makes no objection to this manner of determining compensation if the accepted options (contracts) are valid. Compare Danforth v. United States, 308 U. S. 271, 282. In one case the findings of fact and a comment appear as a memorandum opinion in United States v. Certain Land, 46 E. Supp. 921. In the other case, the decree was entered without separate findings of fact or opinion after adoption of the memorandum in the first case. We perceive nothing in the record to distinguish the cases here and shall dispose of them in a single opinion.5

The following determination appears in the opinion of the trial court for these cases, 46 F. Supp. at page 928:

“There is an absence of any showing that facts were concealed, that misrepresentations were made, or that duress was used. The price stated in the option contract is not unconscionable. There is no fraud, actual or constructive, in this case.” 6

As a result of this conclusion, the issues of corrupt action in these two instances are decided contrary to the Gov[56]*56ernment’s contention at the trial. No such contention was made by the Government here. The findings also stated, at page 925:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keith Bronner v. City of Detroit
Michigan Supreme Court, 2021
Osg Ship Management, Inc. v. Sisto Andrew
Court of Appeals of Washington, 2017
Severn Peanut Co., Inc. v. Industrial Fumigant Co.
807 F.3d 88 (Fourth Circuit, 2015)
First Liberty Ins. Corp. v. Coll, M.
Superior Court of Pennsylvania, 2015
State v. Public Safety Employees Association
323 P.3d 670 (Alaska Supreme Court, 2014)
Decatur Police Benevolent and Protective Association Labor Committee v. City of Decatur
2012 IL App (4th) 110764 (Appellate Court of Illinois, 2012)
State v. PUBLIC SAFETY EMPLOYEES ASS'N
257 P.3d 151 (Alaska Supreme Court, 2011)
Austin Firefighters Relief & Retirement Fund v. Brown
760 F. Supp. 2d 662 (S.D. Mississippi, 2010)
Kenneth H. Hughes, Inc. v. Aloha Tower Development, Corp.
654 F. Supp. 2d 1142 (D. Hawaii, 2009)
Chase v. Cohen
519 F. Supp. 2d 267 (D. Connecticut, 2007)
Guild v. Kitsap County
165 P.3d 1266 (Court of Appeals of Washington, 2007)
Chamberlain Manufacturing Co. v. Local Lodge No. 847
474 F. Supp. 2d 682 (M.D. Pennsylvania, 2007)
Gengler v. United States ex rel. Department of Defense & Navy
453 F. Supp. 2d 1217 (E.D. California, 2006)
Van Horn v. Van Horn
393 F. Supp. 2d 730 (N.D. Iowa, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
324 U.S. 49, 65 S. Ct. 442, 89 L. Ed. 744, 1945 U.S. LEXIS 2612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muschany-v-united-states-scotus-1945.