Pacific Gas & Electric Co. v. United States

31 Cont. Cas. Fed. 71,411, 3 Cl. Ct. 329, 1983 U.S. Claims LEXIS 1641
CourtUnited States Court of Claims
DecidedAugust 30, 1983
DocketNo. 182-80C
StatusPublished
Cited by77 cases

This text of 31 Cont. Cas. Fed. 71,411 (Pacific Gas & Electric Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Gas & Electric Co. v. United States, 31 Cont. Cas. Fed. 71,411, 3 Cl. Ct. 329, 1983 U.S. Claims LEXIS 1641 (cc 1983).

Opinion

MEMORANDUM OF DECISION

HARKINS, Judge.

Plaintiff (Pacific Gas and Electric Company, or PG & E) filed a petition in the United States Court of Claims on April 18, 1980,1 to recover damages of $1,575,148.38 for reconstruction of a road in the Sierra National Forest, Fresno County, California. The petition stated three causes of action: (1) arbitrary and capricious abuse of discretion for failure to share costs in accordance with applicable regulations; (2) breach of an implied-in-fact contract to pay for a portion of costs of reconstruction; (3) an unconstitutional taking of property without just compensation, and a claim for recovery of prejudgment interest since 1976.2

[331]*331After the parties had completed extended discovery through depositions and production of documents, and plaintiff had submitted its response to the Court of Claims standard pretrial order on liability, defendant, on June 23, 1982, moved for summary judgment on all liability issues. At oral argument on May 25, 1983, a ruling was made that defendant is entitled to prevail on its motion for summary judgment. There is no genuine issue as to any fact material to liability issues in plaintiff’s remaining causes of action — breach of an implied-in-fact contract, or, arbitrary and capricious abuse of discretion.

The road in issue is Forest Service road No. 11S40, known as the McKinley Grove Road (MGR). It is designated by the Forest Service, Department of Agriculture, as “a special service road.” MGR is approximately 16 miles long; the portion involved in this case is entirely in the Sierra National Forest and in the Forest Service area of responsibility. It was constructed in the 1930’s by the Forest Service and in 1957-58 plaintiff added about 3.9 miles of the MGR in conjunction with its construction of the Wishon and Courtright dams. By 1971, although it had evolved into a major haul road for timber operations, and a primary access road for recreational traffic to the Wishon and Courtright reservoirs and a number of Forest Service picnic and camp grounds, it was still a narrow two-lane road without a stabilized surface. In 1971, the Forest Service had started to upgrade approximately 7.7 miles of the MGR at an estimated cost of $1,057,000.

A report dated July 3, 1972, by the engineering staff of Region 5 of the Forest Service, entitled “Feasibility Report — Reconstruction of McKinley Grove Road, 11S40,” recommended that the MGR be improved, by means of public works contracts or timber sale contracts, to provide a full two lane width over approximately 16.7 miles with a stabilized roadway surface. The work described in this feasibility report was not funded in 1972. Forest Service planning for future projects, however, included reconstruction and upgrading of the MGR over a 5- or 10-year period, to a two lane width, for summertime use only, as funds became available.

Plaintiff’s interest in reconstruction of the MGR stems from its potential for use as access to the Helms Pump Storage Project of the Federal Power Commission (FPC, now Federal Energy Regulatory Commission, FERC). On September 19,1973, plaintiff applied for a 50 year license to authorize the construction, operation and maintenance of a proposed pumped storage electric power development that would utilize the existing artificial Courtright and Wi-shon reservoirs. The MGR was plaintiff’s preferred route for all weather access to the Helms project area.

Plaintiff owned approximately 726 acres of land near the eastern end of the MGR, outside of the Sierra National Forest. No part of the MGR that was upgraded was on property owned by plaintiff, or on land obtained for the Helms project.

The FPC issued the license for the Helms project to plaintiff on May 18, 1976. On June 17, 1976, the Forest Supervisor issued to plaintiff, free of charge, a Class E special use permit for the “reconstruction, maintenance and use” of the MGR. On June 19, 1976, plaintiff contracted to have the MGR reconstructed in accordance with specifications approved by the Forest Service. Reconstruction was completed on December 23,1976, and notice of completion was given on June 16, 1977. The cost to plaintiff to complete the reconstruction, to a 20-year, all-weather standard, was $2,727,462.92.

Plaintiff initiated discussions at the district level of the Forest Service in July 1973 for use of the MGR as access to the Helms project. These discussions were concerned with plaintiff’s need for an improved all-season road that would support a large volume of heavy construction traffic during an estimated 5-year construction period. The discussions also included inquiries about cost contributions from the Forest Service for upgrading the MGR. In the discussions and negotiations, the Forest Supervisor of the Sierra National Forest, and his subordinates, were interested in having the MGR [332]*332upgraded, and to this end cooperated with plaintiff in attempts to determine the appropriate means of sharing the cost of reconstruction.

Plaintiffs discussions and negotiations for reconstruction and use of the MGR primarily were conducted with Forest Service employees at the national forest supervisory level, or below.3 No one under the level of the Regional Forester had authority to obligate the Forest Service to a contract with plaintiff concerning the costs of the MGR reconstruction. From the beginning of the negotiations on July 31,1973, the representatives of both parties discussed and were aware that the negotiators at the Forest level could not enter a final agreement and could only recommend actions to the Regional Forester.

During 1973 and 1974, the parties held many negotiating sessions in which both sides considered a cost share agreement to be an appropriate vehicle for reconstruction of the MGR. The Forest Supervisor and his associates initially pursued this approach and recommended its adoption to the Regional Forester. Plaintiff was not told officially until March 25,1975, that a cost share agreement could not be applied in the MGR reconstruction.

In accord with this belief that a cost share agreement was appropriate, on January 24,1974, the District Ranger forwarded to plaintiff extracts from the Forest Service Manual (FSM) that outlined the laws, regulations and guidelines on the operation of the Forest development road system. The material consisted of extracts from FSM § 7700, with the sections that covered the cost share agreement procedure specifically emphasized.4

On February 4, 1974, the Forest Supervisor provided an explanation of Forest system rules applicable to the MGR. This letter advised that, as the MGR was a special service road, the Forest Service would require that, (1) prior to any commercial hauling for the Helms project, the road be reconstructed to a standard approved by the Forest Service which would adequately provide for the traffic loads and intensity for a year-long operation, (2) that plaintiff participate in a road maintenance agreement, and (3) that plaintiff participate in a cost share agreement which will prorate the cost incurred in the initial construction and reconstruction of the road commensurate with their estimated project-generated use.

The February 4,1974, letter also attached preliminary calculations for the cost share agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. United States
Federal Claims, 2022
Flint v. United States
Federal Claims, 2022
Davis v. United States
Federal Claims, 2022
Calapristi v. United States
Federal Claims, 2021
Harvey v. United States
Federal Claims, 2020
Kemper
Federal Claims, 2018
Weeks v. United States
124 Fed. Cl. 630 (Federal Claims, 2016)
Rq Squared, LLC v. United States
119 Fed. Cl. 751 (Federal Claims, 2015)
Peninsula Group Capital Corp. v. United States
93 Fed. Cl. 720 (Federal Claims, 2010)
Grayton v. United States
92 Fed. Cl. 327 (Federal Claims, 2010)
Lublin Corp. v. United States
84 Fed. Cl. 678 (Federal Claims, 2008)
Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
International Data Products Corp. v. United States
70 Fed. Cl. 387 (Federal Claims, 2006)
Sinclair v. United States
56 Fed. Cl. 270 (Federal Claims, 2003)
William M. Hanlin v. United States
316 F.3d 1325 (Federal Circuit, 2003)
England v. Systems Management American Corp.
38 F. App'x 567 (Federal Circuit, 2002)
Lamirage, Inc. v. United States
44 Fed. Cl. 192 (Federal Claims, 1999)
Heydt v. United States
41 Cont. Cas. Fed. 77,173 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,411, 3 Cl. Ct. 329, 1983 U.S. Claims LEXIS 1641, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-gas-electric-co-v-united-states-cc-1983.