Fox Valley Engineering Inc. v. United States

151 Ct. Cl. 228, 1960 U.S. Ct. Cl. LEXIS 153, 1960 WL 8485
CourtUnited States Court of Claims
DecidedNovember 2, 1960
DocketNo. 141-58
StatusPublished
Cited by37 cases

This text of 151 Ct. Cl. 228 (Fox Valley Engineering Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fox Valley Engineering Inc. v. United States, 151 Ct. Cl. 228, 1960 U.S. Ct. Cl. LEXIS 153, 1960 WL 8485 (cc 1960).

Opinion

Per Curiam :

This case was referred pursuant to Eule 45(a) to Saul E. Gamer, a trial commissioner of this court, with directions to make findings of fact and recommendations for conclusions of law, which the commissioner has done in a report filed November 13, 1959. Exceptions to this report were taken by defendant and briefs were filed with the court by both parties. Argument by counsel was made before the court, and upon consideration thereof, together with the record made and the exceptions and briefs filed, the court, being in agreement with the findings and conclusions made by the commissioner, hereby adopts the same, as hereinafter set forth, as the basis for its judgment in this case. It is therefore concluded that the plaintiff is entitled to recover. The amount of recovery will be determined pursuant to Eule 38 (c), and such recovery will not include any costs or expenses involved in the original incorporation of tree symbols in plaintiff’s sketches.

It is so ordered.

[231]*231OPINION OF COMMISSIONER

Plaintiff entered into a contract to prepare eight lots of geodetic control sketches for the Army Map Service (AMS). Over 19,000 sketches were ultimately made by plaintiff and the controversy now before the court arises out of the rejection by defendant, during the course of contract performance, of certain lots comprising approximately 6,200 sketches, and the requirement by defendant that these lots, as well as the balance of the lots, be prepared to higher technical standards. Plaintiff contends that the rejected lots in fact met the contract specifications, that their rejection was therefore a breach of contract, and that the additional contract work on these and the remaining lots which plaintiff was required to perform should have been paid for by way of an equitable adjustment in accordance with the contract terms. Plaintiff’s claim was rejected both by the contracting officer and the Armed Services Board of Contract Appeals. So many sketches being involved, and the calculation of the amount of increased expenses caused being therefore so complex, the parties agreed, with the commissioner’s approval, that only the question of liability would be initially determined.

Plaintiff was to prepare the sketches from so-called source material, consisting of sketches of certain Eussian areas which were prepared by the Germans under battle conditions. Some of the sketches consisted of profiles of buildings, but most were planimetric. Plaintiff was to copy the German sketches (omitting certain designated parts therefrom) in accordance with numerous detailed specification requirements. It was an urgent, large-scale drafting task, to be completed in approximately TO days. Despite the many specification provisions, however, it was recognized that it was not possible to include every drafting detail and that close coordination between plaintiff’s organization and AMS would be required in order to prepare the sketches so that they would be satisfactory for their intended use. Because of the extreme urgency of the project and the large number of sketches involved, plaintiff planned, with defendant’s knowledge, an assembly line process involving ap[232]*232proximately 40 employees, with, one group of draftsmen engaged only in sketching the buildings, another performing only such linework as depicting roads, rivers, and brackets indicating distances, another doing only lettering work, and another doing only final inspecting and editing.

Contract performance commenced on February 24, 1955, with the sketches designated as Lot 16 being the first placed into production. About a week later, plaintiff’s official in charge of the project encountered certain problems regarding various drafting details, and requested AMS to send a representative to plaintiff’s plant in Aurora, Illinois, to inspect its operation and to offer guidance, and an AMS employee who was thoroughly familiar with the project and its requirements was sent to plaintiff’s plant for this purpose. This employee remained at the plant during 3 days, March 8, 9, and 10. He examined the work being performed and gave various instructions and suggestions. Among other things, he gave directions concerning the symbols to be used in designating evergreen and deciduous trees, the lightening of the shading on the building profile sketches, the manner of depicting road intersections, the avoidance of crowding of lettering or symbols, and the elimination, despite their existence on the source material, of arcs to indicate right angles. He gave no indication that the work being done was not, on an overall basis, satisfactory and in accordance with the contract specifications. On the other hand, he specifically directed that the instructions and suggestions he was making were not to be applied where to do so would cause any completed or in-process work to be redone. Since this was the early stage of the contract, there was still plenty of time to apply the recommendations to the bulk of the contract sketches. At that time Lot 16 had been practically completed, and Lots 10 and 11 were in process. Several hundred sketches from Lots 10 and 11 were examined by the AMS representative. On the same day that such representative left the plant, March 10, plaintiff shipped Lot 16, consisting of approximately 1,800 sketches. This was the first lot shipped under the contract. No complaints were made to plaintiff by AMS about this lot. It was accepted as complying with the contract specifications and ultimately a formal acceptance in writing was made by [233]*233the contracting officer by a communication which stated that “the sketches are of acceptable quality and are in compliance with the technical provisions of the Contract Specifications.”

On March 16,1955, which was approximately a week after Lot 16 was shipped, plaintiff shipped Lot 11, consisting of approximately 2,100 sketches. Two days later, March 18, it shipped one-half of Lot 10, consisting of approximately 1,400 sketches. These were the lots that were in process when the AMS field representative was at the plant and were in part examined by him. The remainder of Lot 10 was shipped March 22, and one-half of Lot 9, consisting of approximately 1,250 sketches, was shipped on March 26. In the meantime, plaintiff had received a communication from the contracting officer dated March 21, 1955, confirming various “decisions” made by the AMS representative during his visit and also confirming the representative’s instruction concerning the nonretroactivity of his directions, the letter stating “It is emphasized that these practices are not to apply to work already accomplished unless their use would materially improve the sketches.” The letter further made comments and suggestions with respect to eight sketches prepared by plaintiff which the representative took with him and which the contracting officer returned. The letter stated, however: “These sketches as prepared by your office are acceptable.”

However, on March 28, 1955, plaintiff’s official in charge of the project was advised by telephone by an authorized AMS official that many of the sketches in Lots 11, 10, and 9 recently shipped, as set forth above, were unsatisfactory and would have to be redrawn or corrected. The next day, March 29, plaintiff’s official went to Washington and conferred with AMS officials about the matter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

27-35 Jackson Ave LLC v. United States
127 F.4th 1314 (Federal Circuit, 2025)
Koga Engineering & Construction, Inc. v. State
222 P.3d 979 (Hawaii Supreme Court, 2010)
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
Metric Construction Co. v. United States
80 Fed. Cl. 178 (Federal Claims, 2008)
Hughes v. United States
71 Fed. Cl. 284 (Federal Claims, 2006)
Northrop Grumman Corp. v. United States
42 Cont. Cas. Fed. 77,381 (Federal Claims, 1998)
American National Bank & Trust Co. v. United States
36 Cont. Cas. Fed. 75,966 (Court of Claims, 1990)
Transtechnology Corp. v. United States
36 Cont. Cas. Fed. 75,953 (Court of Claims, 1990)
Essen Mall Properties v. United States
36 Cont. Cas. Fed. 75,942 (Court of Claims, 1990)
Design & Production, Inc. v. United States
35 Cont. Cas. Fed. 75,718 (Court of Claims, 1989)
G & H Machinery Co. v. United States
35 Cont. Cas. Fed. 75,638 (Court of Claims, 1989)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
National Railroad Passenger Corp. v. United States
31 Cont. Cas. Fed. 71,675 (Court of Claims, 1983)
Farrell Lines Inc. v. United States
499 F.2d 587 (Court of Claims, 1974)
Peck Iron & Metal Co. v. United States
496 F.2d 543 (Court of Claims, 1974)
Sylvania Electric Products, Inc. v. United States
458 F.2d 994 (Court of Claims, 1972)
Whittaker Corporation v. The United States
443 F.2d 1373 (Court of Claims, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
151 Ct. Cl. 228, 1960 U.S. Ct. Cl. LEXIS 153, 1960 WL 8485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fox-valley-engineering-inc-v-united-states-cc-1960.