G & H Machinery Co. v. United States

35 Cont. Cas. Fed. 75,638, 16 Cl. Ct. 568, 1989 U.S. Claims LEXIS 44, 1989 WL 28630
CourtUnited States Court of Claims
DecidedMarch 31, 1989
DocketNo. 218-84C
StatusPublished
Cited by7 cases

This text of 35 Cont. Cas. Fed. 75,638 (G & H Machinery Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G & H Machinery Co. v. United States, 35 Cont. Cas. Fed. 75,638, 16 Cl. Ct. 568, 1989 U.S. Claims LEXIS 44, 1989 WL 28630 (cc 1989).

Opinion

OPINION

SMITH, Chief Judge.

This opinion is issued following trial and post-trial briefings. The dispute before the court arises out of a contract awarded by the General Services Administration to plaintiff, G & H Machinery Company, for the performance of certain repair services on various mechanical and electrical equipment. Plaintiff is seeking compensation beyond the amount set by the contract, based on a number of alleged breaches by the government. Based upon the court’s findings set forth below, the court holds that plaintiff’s contract claim must be denied.

[570]*570FACTS

On July 26,1975, G & H Machinery Company (G & H) was awarded General Services Administration Contract No. GS-05W-56153. The contract was an indefinite quantity, time and material services contract.1 It required G & H to perform repair services on various types of heavy construction and related equipment for a period of one year. Pursuant to the contract, G & H was entitled to receive in consideration for these services, a flat hourly labor rate of $9.12 multiplied by direct labor hours, plus payment for parts and materials. The hourly rate included all charges for direct labor, overhead and profit. The cost of parts and materials was based on current retail list prices less the discount offered in the contractor’s bid. G & H’s bid offered, a 23% discount. Under the terms of the contract, the contractor was required to have an adequate inventory of parts to service items on which offers were submitted. The contractor was also required to maintain a satisfactory source of supply for such parts as needed in the performance of the contract. The General Services Administration (GSA)2 was responsible for the administration of this contract on the government side even though the vast majority of items to be repaired came from the Air Force.

G & H fully performed under the contract, providing repair services with an estimated value of $2.4 million. Although the contract period ended on June 30, 1976, work under the contract was not in fact completed until December of 1977.

A follow-on contract was entered into between G & H and the government for the period from July 1, 1976, through June 30, 1977. The flat hourly rate for this contract was $13.68. G & H was compensated for the repair services it performed during the original contract period (July 26, 1975, through June 30, 1976) in accordance with the terms of the original contract. It was also compensated for work input prior to July 1, 1976, but performed during the period June 30, 1976, to December of 1977, in accordance with the terms of the original contract. That is, at the $9.12 hourly rate.

G & H contends that various breaches of the contract by the government3 delayed its performance beyond the time period covered by the contract. It should be remembered that only the original contact is in dispute in this case. Asserting that the original contract had expired, G & H now seeks compensation for work done during this post-contract period under the terms negotiated pursuant to the follow-on contract. Applying the terms of the second contract, G & H claims that it is owed the additional amount of $355,851.26 for services provided during this period, plus interest, attorneys’ fees and other litigation costs.

DISCUSSION

The Burden of Proof

The gravamen of plaintiff’s claim is that its completion of the contract was unreasonably delayed by a series of breaches by the government. Unreasonable delays, attributable to the government, would constitute a breach of the implied obligation not to hinder the performance of G & H. Lewis-Nicholson, Inc. v. United States, 213 Ct.Cl. 192, 550 F.2d 26 (1977); George A. Fuller Co. v. United States, 108 Ct.Cl. 70, [571]*57194, 69 F.Supp. 409, 411 (1947). This court has long held that in contract cases, where the plaintiff has alleged a breach of contract, the plaintiff must shoulder the burden of “establishing the fundamental facts of liability, causation and resultant injury.” Wunderlich Contracting Co. v. United States, 173 Ct.Cl. 180, 199, 351 F.2d 956, 968 (1965).

The burden of proof requires the plaintiff to establish three separate elements. First, it must establish the nature and extent of the government’s breach of contract. Second, it must prove that it suffered damages. Any damages must be proved with sufficient certainty so that the determination of the amount of damage would not be pure speculation. Willems Indus, v. United States, 155 Ct.Cl. 360, 376, 295 F.2d 822, 831 (1961), cert. denied, 370 U.S. 903, 82 S.Ct. 1249, 8 L.Ed.2d 400 (1962). Finally, even where damages have been verified, plaintiff is required to demonstrate that there is a causal link between the damages and defendant’s breach. River Constr. Corp. v. United States, 159 Ct.Cl. 254, 270 (1962); Boyajian v. United States, 191 Ct.Cl. 233, 239, 423 F.2d 1231, 1235 (1970).

The burden of proof stands as a threshold question. If the claimant fails to carry the burden of proof then, even in the absence of opposing evidence, he cannot recover on the breach of contract claim. In attempting to meet the burden, plaintiff has relied primarily on the oral téstimony and notes of C.W. Krietemeyer, the president of G & H during the period in question. Citing the case of Sanders v. United States Postal Serv., 801 F.2d 1328 (Fed.Cir.1986), plaintiff suggests that its uncontradicted evidence establishes a prima facie case sufficient to shift the burden of going forward with evidence to the defendant. While Sanders states the rule that the burden of going forward with evidence is put upon defendant after a prima facie case has been made, the court notes that interested parties’ evidence, even if unopposed, may not carry sufficient weight to establish the prima facie case necessary to shift the burden of going forward to defendant. The test of sufficiency is whether the evidence rises to a level whereby the trier of fact could find for the plaintiff, based solely on the evidence presented. Here the court, unlike the trier of fact in Sanders, for the reasons to be discussed, does not give sufficient weight to the plaintiff’s evidence to establish a prima facie case.

In applying this test and weighing the sufficiency of the evidence presented, the court must be on guard against testimony based on conjecture, speculation or unwarranted assumptions. Snowbank Enter, v. United States, 6 Cl.Ct. 476, 486 (1984). The weight and sufficiency of this evidence hinges on the credibility of the witnesses and the support for their testimony found in the record.

The court notes here that the plaintiff’s motion to exclude evidence of fraud was denied. Plaintiff’s argument that the evidence of fraud constituted an affirmative defense that was not plead misses the point of defendant’s evidence of fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Die Casters International, Inc. v. United States
73 Fed. Cl. 174 (Federal Claims, 2006)
Haynes v. United States
61 Fed. Cl. 788 (Federal Claims, 2004)
Fru-Con Construction Corp. v. United States
44 Fed. Cl. 298 (Federal Claims, 1999)
Transpace Carriers, Inc. v. United States
27 Fed. Cl. 269 (Federal Claims, 1992)
Weaver-Bailey Contractors, Inc. v. United States
36 Cont. Cas. Fed. 75,847 (Court of Claims, 1990)
Malissa Co. v. United States
35 Cont. Cas. Fed. 75,750 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,638, 16 Cl. Ct. 568, 1989 U.S. Claims LEXIS 44, 1989 WL 28630, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-h-machinery-co-v-united-states-cc-1989.