Neal & Co. v. United States

34 Cont. Cas. Fed. 75,366, 13 Cl. Ct. 282, 1987 U.S. Claims LEXIS 194
CourtUnited States Court of Claims
DecidedSeptember 17, 1987
DocketNo. 57-85C
StatusPublished
Cited by3 cases

This text of 34 Cont. Cas. Fed. 75,366 (Neal & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neal & Co. v. United States, 34 Cont. Cas. Fed. 75,366, 13 Cl. Ct. 282, 1987 U.S. Claims LEXIS 194 (cc 1987).

Opinion

OPINION

SMITH, Chief Judge.

This case is before the court on Defendant’s Motion for Summary Judgment. The court grants defendant’s motion because there are no genuine issues of material fact and the United States is entitled to judgment as a matter of law. This opinion follows an oral ruling given to the parties on March 26, 1987. The Claims Court has jurisdiction over the subject matter of this case pursuant to 28 U.S.C. § 1491 (1982), and the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982).

Facts

This case arises out of a contract between Neal and Company, Inc., (Neal) and [283]*283the United States Coast Guard (Coast Guard). The subject contract was awarded on March 30, 1982, for the renovation of housing units in Kodiak, Alaska. This contract was known as the Phase III contract; all three phases of the overall project concerned the renovation of family housing units for the Nemtz Park/Lake Louise area. Neal was the successful low bidder for both the Phase II contract, which was awarded to plaintiff on July 31, 1981, and the Phase III contract which was awarded on March 30, 1982. Subsequently, plaintiff filed two claims for equitable adjustments with the contracting officer, both of which were denied. Because of the interrelation of the facts in these two contracts and the legal impact of the denial of the Phase II contract claim upon the Phase III contract claim, the court must devote some attention to the facts of the Phase II contract claim even though it is the Phase III contract claim which is the subject of the instant action.

The Phase II Contract

On July 31, 1981, the Coast Guard awarded Neal the Phase II contract. Contract DTCG35-81-C-00079 was a firm fixed price contract in the amount of $895,-200.00. Pursuant to the terms of the contract, Neal was obligated to perform the total rehabilitation of twenty-six housing units at the Nemetz Park Family Housing Complex, Coast Guard Support Center, Kodiak, Alaska. • The work involved, among other things, replacing the exterior siding and renovating the interiors of certain buildings. That contract, at General Provision 5, “Termination for Damages for Delay — Time Extensions,” paragraph (a), provides in pertinent part:

If the Contractor ... fails to complete said work within such time [specified in this contract], the Government may, by written notice to the Contractor, terminate his right to proceed with the work ... Whether or not the Contractor’s right to proceed with the work is terminated, he and his sureties shall be liable for any damage to the Government resulting from his refusal or failure to complete the work within the specified time.

Furthermore, paragraph (d) of this General Provision provides:

The Contractor’s right to proceed shall not be so terminated nor the Contractor charged with resulting damage if: (1) The delay in the completion of work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor including but not restricted to, acts of God ... unusually severe weather, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and such subcontractors or suppliers____

Therefore, in the absence of any provision for liquidated damages under the contract, Neal would be rendered liable for any actual damages it or the Coast Guard sustained as a result of its failure to perform its obligations under the contract within the period specified or within any time modifications agreed to by the parties. Although the original completion date of the Phase II contract was June 13, 1982, that date was subsequently extended to August 9, 1982, by a series of contract modifications.

The contract modifications1 which extended the completion date were as follows:

New Modification Execution Date Completion Date
4 July 13, 1982 July 11, 1982
5 July 13, 1982 July 27, 1982
9 July 13, 1982 August 1, 1982
11 November 30, 1982 August 4, 1982
12 December 15, 1982 August 8, 1982
14 December 17, 1982 August 9, 1982

During the course of the Phase II contract, Neal’s painting subcontractor failed to meet the necessary deadlines and Neal’s performance was delayed beyond the required completion date, August 9, 1982. Also during this period, the Coast Guard awarded the Phase III contract work at Nemetz Park to Neal, as the low bidder on March 30, 1982. On July 21, 1982, a pre-construction conference for the Phase III [284]*284contract was held. After that conference, the status of the Phase II project was discussed and Neal was informed that the Phase II buildings were needed to house the families then occupying the Phase III buildings. Neal was also notified that the work on the Phase III contract could not begin until some or all of the Phase II buildings were completed.

On September 2, 19822, Neal formally notified the Coast Guard that it had not been allowed to start the Phase III work and that it would seek both a contract extension and an equitable adjustment to recover its additional costs. By letter dated September 8, 1982, the contracting officer responded that he believed that at the July 21st meeting, the parties had agreed to a one-for-one swap of the Phase II and III buildings and that Neal would be responsible for any additional costs associated with its failure to complete the Phase II buildings in a timely fashion.

The Phase II buildings, which were to be finished by August 9, 1982, were actually completed as follows:

Building Completion Date
723 September 15, 1982
721 September 22, 1982
720 October 8, 1982
724 October 13, 1982
722 November 2, 1982

On March 2, 1983, Neal submitted a certified claim to the contracting officer for additional costs incurred in the Phase II contract. After denial of its Phase II claim by the contracting officer, Neal filed an appeal with the Department of Transportation Contract Appeals Board (DOTCAB or Board) alleging that the company was entitled to an equitable adjustment of $85,764. On November 13, 1984, the DOTCAB denied plaintiffs Phase II claim in its entirety. Subsequently, the Court of Appeals for the Federal Circuit affirmed the judgment of the Board. Neal & Company, Inc., 85-1 BCA (CCH) ¶ 17,794 (1984), aff'd, 785 F.2d 324, (Fed.Cir.1985). The DOTCAB ruled that Neal was fully responsible for the delays in completing the Phase II work and that the extra costs incurred due to the delay in availability of the Phase II housing were sufficiently foreseeable to hold Neal liable for the additional amounts.

The Phase III Contract

As noted earlier, the Phase III follow-on contract, number DTCG35-82-C-0060, with a price of $1,233,746.00, was awarded to Neal on March 30,1982.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DWS, Inc. v. United States
35 Cont. Cas. Fed. 75,739 (Court of Claims, 1989)
SMS Data Products Group, Inc. v. United States
35 Cont. Cas. Fed. 75,647 (Court of Claims, 1989)
G & H Machinery Co. v. United States
35 Cont. Cas. Fed. 75,638 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,366, 13 Cl. Ct. 282, 1987 U.S. Claims LEXIS 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neal-co-v-united-states-cc-1987.