J. A. Ross & Co. v. United States

115 F. Supp. 187, 126 Ct. Cl. 323, 1953 U.S. Ct. Cl. LEXIS 43
CourtUnited States Court of Claims
DecidedOctober 6, 1953
DocketNo. 48882
StatusPublished
Cited by33 cases

This text of 115 F. Supp. 187 (J. A. Ross & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Ross & Co. v. United States, 115 F. Supp. 187, 126 Ct. Cl. 323, 1953 U.S. Ct. Cl. LEXIS 43 (cc 1953).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

On September 14, 1943, plaintiff and defendant entered into a contract whereby plaintiff agreed to furnish all labor and material and to perform all work necessary for the placement of concrete pavement, hard standings, and drainage at Erie Proving Ground, LaCarne, Ohio. This contract was modified on the following day, September 15,1943. As modified the contract contained 59 separate items of work, for which plaintiff was to be paid an estimated consideration of $712,153.00, based upon unit prices for the estimated quantities of work.

Plaintiff sues on four causes of action.

CAUSE OK ACTION NO. 1

Its first cause of action is for $34,624.64, compensation claimed for placing 12,683.02 cubic yards of base course material at the contract unit price of $2.73 per cubic yard. Plaintiff alleges that this material was used in the perform-[326]*326anee of the contract work, but that it has not been paid for. The proof shows that this material was in fact used in the performance of the entire contract work and that it has not been paid for. The facts underlying the controversy over defendant’s liability to pay for it follow:

The contract as modified called for the placement of two kinds of paving: (1) 140,583.45 square yards of concrete paving, and (2) 75,980.96 square yards of crushed stone surfacing or macadam pavement, sometimes called hard standings. Beneath the concrete pavement there was to be placed a base course of compacted stone or slag five inches in depth, and beneath the macadam pavement there was to be placed a similar base course sis inches in depth. Plaintiff was also to do the necessary grading and filling preparatory to placing the base course. Measurement of the material placed in the base course, for the purpose of determining the amount to be paid, was to be based upon the volume of material measured between the lines and grades established for the subgrade and the lines and grades established for the top of the base course.

The amount of material to be placed in the base course, based on 5 inches under the concrete and 6 inches under the macadam pavement, was 32,188.2 cubic yards. The plaintiff has been paid for 46,132.08 cubic yards. It would, therefore, appear that plaintiff has been paid at least as much as that called for by the specifications.

The difference between the amount paid for and the amount specified for the base course is to be accounted for in large part by the amount of base course material that went into the fills. Section 3-02 (b) of the specifications required that base course material be placed in the fills where the fills were 6 inches or less in depth, and in fills of more than 6 inches in depth where this was required by the contracting officer. No specific provision was made for payment for base course material placed in fills, but evidently this material was taken into account in measuring the base course material to be paid for.

The amount paid for exceeds by 13,943.88 the amount specified for the base course, but there remains 12,683.02 cubic yards that were used, but which has not been paid for. [327]*327Most of this sunk into the ground below the lower line of the base course. The reason for this is that a good deal of the base course material was laid on soggy ground, and when the heavy rollers were rolled over it in order to compact it, it sunk into the ground below the lower measurement line for the base course material.

The ground was soggy because the plaintiff, who was charged with the duty of draining the site, had been unable to drain it successfully. Shortly after plaintiff began laying the base course, rather heavy rains fell on the site and the drainage provided did not take care of it. There is no serious allegation that the defendant was in any way responsible for the soggy nature of the ground.

The basis of plaintiff’s claim is that the defendant required it to place the base course material on soggy ground, and that this was in violation of the terms of the contract. Plaintiff relies on that provision of section 3-02 (b) of the specifications relating to grading, which reads as follows:

* * * Fill shall not be placed in areas where the sur- ' face material is frozen or wet. * * *

Defendant says that this provision applied to earth fill and not to stone fill.

This is the way the contracting officer construed the specifications, and we cannot say that this was wrong. We quote below in full the paragraph of the specifications in which this sentence appears:

3-02. EXCAVATION AND GRADING.
(b) Grading. Grading operations in areas where no excavation is required shall be as directed by the contracting officer. No over-all stripping is contemplated but grading shall be sufficient to provide an adequate foundation. Fills shall be constructed of base course material in all areas where the required fill is six (6) inches or less in depth. Where the total thickness of base course and fill exceeds eight (8) inches the material shall be placed in courses not to exceed six (6) inches in depth. Placing and rolling shall be in accordance with the requirements of paragraph 3-03 (c). In areas where the required fill is greater than six (6) inches in depth the fill shall be constructed of base [328]*328course material or compacted earth as directed by the contracting officer. Compacted earth fills shall be constructed with material obtained from excavation _ or borrow which has been approved by the contracting officer for that use. Areas to be filled shall be stripped of unsuitable material as directed and loosened by scarifying sufficiently to provide a bond with material placed for the fill and shall be dampened if required. Fill shall not be placed in areas where the surface material is frozen or wet. Material to form the earth fill shall be placed in layers not to exceed six (6) inches (loose measure) in thickness and at the optimum moisture content for compaction by the equipment used, as determined by the contracting officer. The contractor may be required to add water or to allow the material to dry-before compacting. When moisture content and condition of the spread material are satisfactory to the contracting officer, the material shall be rolled with an approved type, tractor drawn, sheeps-foot roller until compacted to a density equivalent to that of adjacent undisturbed subgrade material. The compaction operation shall in no case consist of less than six (6) passes of the tractor and roller unit on each square foot of each layer. In areas not accessible to power equipment, the compacting may be done by other methods whieh will provide equivalent compaction and achieve the required density if approved by the contracting officer.

It will be observed that the first part of the paragraph applies to the use of base course material in the fills, and it would seem that the last part relates to earth fills. The seventh sentence begins, “compacted earth fills shall be constructed.” The rest of the paragraph seems to relate only to earth fills, although this is not necessarily so. Earth could not successfully be used in a fill if it was laid on soggy ground, but there would seem to be no reason for prohibiting a contractor from laying crushed stone on soggy ground if he wished to do so. If some of it sunk into the mud, he could still get a good fill by laying more stone on top of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flink/Vulcan v. United States
63 Fed. Cl. 292 (Federal Claims, 2004)
Croman Corp. v. United States
49 Fed. Cl. 776 (Federal Claims, 2001)
Scott Timber Co. v. United States
42 Cont. Cas. Fed. 77,312 (Federal Claims, 1998)
District of Columbia v. Organization for Environmental Growth, Inc.
700 A.2d 185 (District of Columbia Court of Appeals, 1997)
L & A Jackson Enterprises v. United States
41 Cont. Cas. Fed. 77,117 (Federal Claims, 1997)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Calfon Construction Inc. v. United States
35 Cont. Cas. Fed. 75,738 (Court of Claims, 1989)
G & H Machinery Co. v. United States
35 Cont. Cas. Fed. 75,638 (Court of Claims, 1989)
Avedon Corp. v. United States
35 Cont. Cas. Fed. 75,577 (Court of Claims, 1988)
Beauchamp Construction Co. v. United States
34 Cont. Cas. Fed. 75,453 (Court of Claims, 1988)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Law v. United States
195 Ct. Cl. 370 (Court of Claims, 1971)
Dewey Jordan v. MD.-NAT'L CAP. P. & P.
265 A.2d 892 (Court of Appeals of Maryland, 1970)
Jefferson Construction Company v. The United States
392 F.2d 1006 (Court of Claims, 1968)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Dittmore-Freimuth Corp. v. The United States
390 F.2d 664 (Court of Claims, 1968)
Merritt-Chapman & Scott Corp. v. United States
178 Ct. Cl. 883 (Court of Claims, 1967)
Luria Brothers & Company, Inc. v. The United States
369 F.2d 701 (Court of Claims, 1966)
Luria Bros. & Co. v. United States
369 F.2d 701 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 187, 126 Ct. Cl. 323, 1953 U.S. Ct. Cl. LEXIS 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-ross-co-v-united-states-cc-1953.